Line 3: Line 3:

== Task list ==

=== Phase1 ===
=== Phase2 ===

-----
Line 4: Line 11:
 * MIF + VIS * 責任者
Line 6: Line 13:
 * ビーム位置測定
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
  .
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
Line 7: Line 20:
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
  .
Line 12: Line 21:
 . * 責任者
Line 14: Line 22:

<<Anchor(Meetings)>>
Line 18: Line 28:
<<Anchor(MorningMeetings)>>
Line 24: Line 35:
2017/10/25(Wed) 2017/11/7(Tue.)
Line 28: Line 39:
   * MIF+VIS: *和泉、中野、井上、Mark、Fabian、Enzo、平田 (PHS: Mark、KEK-2(井上)、 V-3(和泉)、V-7(中野))    * 位置測定: *内山、寺田 @IYC, Yend、井上、灰野(V-6(井上), V-10(灰野))
   * VIS: Mark, Enzo, 神津
Line 31: Line 43:
   * PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。両エンドはハザードエリアではないです、真空槽まわりで作業す人は保護メガネをかけください。
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xend 1F。今日の午後からIFIから奥に移行する
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 注意: Xend 1Fが昨日に引き続き今日も
ハザードエリア。作業わり次第解除され
Line 36: Line 50:
   * 計算機
    * k1prm以外はエンドも含めて復帰した。DAQも復帰している。PRMを動かす必要度は低いので、今日の午前PR3を最優先で最低限動くようにする。
   * アラインメント
    * 光がPR3までいった。
    * MCのアラインメントがずれているよう(透過率で最大の90%程度になった)で、調べると入射光自身がずれていることがわかった。
    * 今日もう一度光をXエンドまで通す。
   * X/Y end
   * ビーム位置測定
    * IYAのビームを測定した。フロントでもpeak to peakで1cmビームは揺れている。落ち着いている時もあり、時々大きく揺れるような様子。少なくともXよりは揺れている。BSから40mくらい離れているが、その距離にしてはかなり揺れている。そのため、エンドではPDに当たらないくらい揺れている。
    * 今日はIYCでの作業。EYCはGmatの上に落としてあるだけなので、それをダクトの上に落とす。

    * XエンドのEXCの鏡の位置でのビームがTcamで確認できた。アルミニウムのスクリーンに落としてあり、かなりはっきり見えている。エンドのビューポートでクリップされたedgeが見えている。PDの影も見えている。
    * Yエンドに関してはPDのゲインがサチっているので下げる。

   * 防振関連
    * BSのOSEMのオフセットを除く試みをする。もう少し揺れは小さくなる予定。
Line 45: Line 61:
  * 10/23の週: Yエンドに光を送る。   * 11/6の週
   * 火曜日くらいまでY側のビーム位置測定。
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。
  * 11/8に見学があるので、今日11/7の午後にビームIFIのところで止める。
Line 49: Line 68:
  * k1prmの復帰。
Line 55: Line 73:
<<Anchor(WeeklyMeetings)>>
Line 58: Line 77:
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||
[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=
3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
Line 63: Line 84:
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 70: Line 91:
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]

KAGRA Commissioning Wiki


Task list

Phase1

Phase2


Working people assignment

* 責任者

  • ビーム位置測定
    • 11/6 *内山、寺田、木村、井上、沢田@IYA
    • 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
    • 11/8 *木村、荒木、沢田@IXV, IXC、荒木
    • 11/9 *木村、荒木、沢田@IYV, IYC、荒木



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/7(Tue.)

  • Daily
    • 作業人員(*:責任者)
      • 位置測定: *内山、寺田 @IYC, Yend、井上、灰野(V-6(井上), V-10(灰野))
      • VIS: Mark, Enzo, 神津
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xend 1F。今日の午後からIFIから奥に移行する。
      • Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
      • 注意: Xend 1Fが昨日に引き続き今日もハザードエリア。作業が終わり次第解除される。
    • 作業
      • ビーム位置測定
        • IYAのビームを測定した。フロントでもpeak to peakで1cmビームは揺れている。落ち着いている時もあり、時々大きく揺れるような様子。少なくともXよりは揺れている。BSから40mくらい離れているが、その距離にしてはかなり揺れている。そのため、エンドではPDに当たらないくらい揺れている。
        • 今日はIYCでの作業。EYCはGmatの上に落としてあるだけなので、それをダクトの上に落とす。
        • XエンドのEXCの鏡の位置でのビームがTcamで確認できた。アルミニウムのスクリーンに落としてあり、かなりはっきり見えている。エンドのビューポートでクリップされたedgeが見えている。PDの影も見えている。
        • Yエンドに関してはPDのゲインがサチっているので下げる。
      • 防振関連
        • BSのOSEMのオフセットを除く試みをする。もう少し揺れは小さくなる予定。
  • Weekly
    • 11/6の週
      • 火曜日くらいまでY側のビーム位置測定。
      • フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。
    • 11/8に見学があるので、今日11/7の午後にビームIFIのところで止める。
  • 問題点など
    • コーチフィルターが不調。

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokum , or educe, Polycom

No.

Date

Agenda

Schedule

Minute

Files

7

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1