Line 4: Line 4:
== Meeting == == Task list ==
Line 6: Line 6:
=== Weekly meeting === === Phase1 ===
=== Phase2 ===
Line 8: Line 9:
 * 日時: 毎週火曜日、午前11時から
 * 場所、手段: 北部会館会議室、およびeZuce、ポリコムなど
-----
== Working people assignment ==
* 責任者
  
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .
Line 11: Line 17:
  * [[KAGRA/Commissioning/Meeting/Weekly|議題、議事録、資料など]]
Line 13: Line 18:
-----

<<Anchor(Meetings)>>
-----
== Meetings ==

----
<<Anchor(MorningMeetings)>>
Line 15: Line 28:
 * 日時: 平日毎日、午前9時から
 * 場所、手段: コントロールルーム、およびeZuce、ポリコムなど
 * Date and time: Every weekday, 9AM
 * Location: Control room, or educe
Line 19: Line 32:
2017/11/8(Wed.)

 * Daily
  * 作業人員(*:責任者)
   * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木))
   * VIS: Mark, Enzo, 神津

  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。

  * 作業
   * ビーム位置測定
    * IYCでの位置測定をした。完了。現在まとめ中。
    * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。

   * 防振関連
    * BSのlength sensing Oplev, オフセットリリースなど。

   * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。

 * Weekly
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。

 * 問題点など
  * コーチフィルターが不調。

<<MonthCalendar(KAGRA/Commissioning/DailyWork)>>


----
<<Anchor(WeeklyMeetings)>>
==== Weekly meeting ====
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]


-----
Line 20: Line 87:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|Commissioning plan for Phase1]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]
Line 22: Line 89:
== Other communication tools == == Communication tools ==
Line 27: Line 94:
---- ------

KAGRA Commissioning Wiki


Task list

Phase1

Phase2


Working people assignment

* 責任者

  • 下げ振り測定
    • 11/9 *木村、荒木、沢田@IYV, IYC、荒木



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/8(Wed.)

  • Daily
    • 作業人員(*:責任者)
      • 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木))
      • VIS: Mark, Enzo, 神津
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはIFIより奥。
    • 作業
      • ビーム位置測定
        • IYCでの位置測定をした。完了。現在まとめ中。
        • IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。
      • 防振関連
        • BSのlength sensing Oplev, オフセットリリースなど。
      • センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。
  • Weekly
    • 11/6の週
      • フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
  • 問題点など
    • コーチフィルターが不調。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokum , or educe, Polycom

No.

Date

Agenda

Schedule

Minute

Files

7

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents