Differences between revisions 121 and 137 (spanning 16 versions)
Revision 121 as of 2010-10-15 23:39:59
Size: 6554
Comment:
Revision 137 as of 2010-11-02 07:55:50
Size: 7800
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
 .[[LCGT/Meeting/weekly/schedule|Schedule from September to December, 2010]]  .[[LCGT/Meeting/weekly/schedule|Schedule from October to December, 2010]]

The conference room is the Seminar room on 6th floor of the ICRR and you need to connect to the MCU provided by the Information Center in the University of Tokyo. (IP address: 133.11.205.100 which is available from 7:30am)
Line 11: Line 14:
== 32th: November 2, 2010(Tue) 8am~(JST) ==
[[LCGT/Meeting/weekly/20101102/EVO|EVO connection]] [ [[LCGT/Meeting/EVO|help]] ]

Agenda
 1. Project report
 1. Report from management support group
 1. Report of Chief meeting
 1. Plan & Status of budget expenditure (Preparation of calling for bids)
 1. Renewal of Program Advisory Board
 1. Status of MOUs (LIGO, Virgo, GEO)
 1. Guideline for Review
 1. Others

Files
 . [[attachment:LCGT/Meeting/weekly/20101102/PAB.ppt|Program Advisory Board (Kuroda)]]
 . [[attachment:LCGT/Meeting/weekly/20101102/Guideline for Review.ppt|Guideline for Review (Nakatani)]]
 . [[attachment:Tunnel sub-group 101102.pdf|Tunnel sub-group report (Uchiyama)]]
 . [[attachment:20101102_vis.pdf|Vibration isolation system sub-group report (Takahashi)]]
 . [[attachment:20101102_LCGT_Meeting.ppt|Mirror sub-group report (Mio)]]
 . [[attachment:20101102_digital.pdf|Digital system sub-group report (Miyakawa)]]
 . [[attachment:lcgt_geo_101102.pdf|Baseline interferometer sub-group report (Araya)]]
 . [[attachment:DataAna_2010Nov.pdf|Data analysis sub-group report (Kanda)]]
Line 13: Line 39:
The conference room is the Seminar room on 6th floor of the ICRR and you need to connect to the MCU provided by the Information Center in the University of Tokyo. (IP address: 133.11.205.100 which is available from 7:30am) [[LCGT/Meeting/weekly/20101018/EVO|EVO connection]] [ [[LCGT/Meeting/EVOJ|help]] ]
Line 28: Line 54:
 .クライオスタット実証器の提案(鈴木) [[attachment:LCGT/Meeting/weekly/20101018/sapphire_sus20101018.ppt|ppt]], [[attachment:LCGT/Meeting/weekly/20101018/sapphire_sus20101018.pdf|pdf]]

[[LCGT/Meeting/weekly/minute/20101018|Minute (in Japanese)]]
Line 31: Line 60:

The conference room is the Seminar room on 6th floor of the ICRR and you need to connect to the MCU provided by the Information Center in the University of Tokyo. (IP address: 133.11.205.100 which is available from 7:30am)

LCGT collaboration meeting

Meeting schedule

The conference room is the Seminar room on 6th floor of the ICRR and you need to connect to the MCU provided by the Information Center in the University of Tokyo. (IP address: 133.11.205.100 which is available from 7:30am)


32th: November 2, 2010(Tue) 8am~(JST)

EVO connection [ help ]

Agenda

  1. Project report
  2. Report from management support group
  3. Report of Chief meeting
  4. Plan & Status of budget expenditure (Preparation of calling for bids)

  5. Renewal of Program Advisory Board
  6. Status of MOUs (LIGO, Virgo, GEO)
  7. Guideline for Review
  8. Others

Files

31th: October 18, 2010(Mon) 14pm~(JST)

EVO connection [ help ]

Agenda

  1. 各種報告(マネージメント、各サブワーキンググループ)
  2. 特別作業班の検討状況報告
  3. プロジェクト予算執行状況
  4. 推進組織の改定
  5. LCGT collaboration membership
  6. 海外・各機関とのMOU及び研究協力
  7. クライオスタット実証器の提案
  8. その他

Files

Minute (in Japanese)

30th: September 7, 2010(Tue) 8am~(JST)

Agenda

  1. General report of the project (progress since the last meeting on 2nd, August)
  2. Construction Schedule in detail (based on the summary by PM support group)
  3. Revised organization diagram (renewed sub-WGs, newly created LCGT Steering Committee)
  4. Guideline to accept new members of LCGT
  5. Diameter of vacuum tube (re-confirmation)
  6. Progress report of MOU with LIGO for the cooperative research agreement (discussion point: Policy of data-exchange in future)
  7. Others

Files

29th: August 2, 2010(Mon) 2pm~(JST)

Agenda

  1. Status report (T. Kajita)
  2. Design report (O. Miyakawa) and Discussion
  3. Proposal of LCGT Organization (K. Kuroda)
  4. Proposal of the working group of LCGT roadmap (I. Nakatani)
  5. Discussion of the guideline of the membership of LCGT
  6. Others

Files

28th: July 20, 2010(Mon) 2pm~(JST)

Agenda

  1. Status report from Management group
  2. Report from Support group of Project Manager
  3. Discussion and determination of the domestic organization to execute the project
  4. Task allocation on working teams
  5. Others

Files

第27回 2010年6月28日(月) 午後2時〜5時

場所:宇宙線研大セミナー室(TV会議接続有り)

議題

  1. 最先端研究基盤事業への採択の報告とLCGT全体計画との整合性について
  2. 本事業で約束した内容を実現するための検出器の仕様
  3. 検出器仕様を満たす干渉計実現のために直ちにとるべきアクションアイテム
  4. 本事業終了までのスケジュール
  5. 役割分担
  6. その他

June 28, 2010(Mon) 2pm-5pm(JST) at ICRR 6F large conf. room

Agenda

  1. Report on 3 years funding & total plan of LCGT

  2. Detector specification satisfying the requirement of the fund
  3. Action items to realize the detector
  4. Schedule
  5. Organization of manpower
  6. Others

Files

Face to face meeting 2010年6月15日(火)〜6月16日(水)

場所:東京大学宇宙線研究所柏キャンパス

第26回 2010年5月10日(月) 午後2時〜5時

議題

  1. 定例報告
  2. LIGO近況報告(David Tanner)

  3. RSE作業部会報告(安東)
  4. その他

資料

第25回 2010年4月19日(月) 午後2時〜3時

資料

第24回 2010年4月5日(月) 午後2時〜5時

資料


Past weekly meeting

Meetings in FY2008, 2009

LCGT/Meeting/weekly (last edited 2012-06-06 12:12:28 by OsamuMiyakawa)