== Schedule == 2017/11/8 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}} ----- |
|
Line 13: | Line 19: |
* ビーム位置測定 * 11/6 *内山、寺田、木村、井上、沢田@IYA * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木 |
* 下げ振り測定 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 |
Line 17: | Line 22: |
* 11/8 *木村、荒木、沢田@IXV, IXC、荒木 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 |
|
Line 20: | Line 23: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/13 *新井、正田(午後~) * 11/14 *新井、正田 * 11/15 *木村、沢田、新井、正田(蓋閉め) * 11/16 *木村、沢田、新井、正田(蓋閉め) * 11/17 *新井、正田 |
|
Line 21: | Line 30: |
* Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, RefCav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * PicoMotor: 三代 * Digital: 山本、宮川 * 回路: 霜出、上泉 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} |
|
Line 35: | Line 68: |
2017/11/6(Mon.) | 2017/11/9(Thu) * 作業 * 下げ振り測定 * IXCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。2cm程度ずれていた。測定後IXCとBSの間のGVを閉めたので、今日真空引きを始める予定。 * 本日IYCで同じことをする。 * 防振関連 * BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。 * PR2のWatchdogが入ってしまった。 * Watchdogが入っても電流が多少流れる。抵抗値によるが、数十mV程度の電圧の最大値が存在し、そこまでは信号が出てしまう。線形でないが、ある程度の制御がされてしまうということ。 * 計算機関連 * k1prmのを準備してPRMの回路などをつなぎこむ。PR3を動かさないようにする。 |
Line 39: | Line 85: |
* 位置測定: *内山、寺田、木村、井上、沢田、灰野、横澤(V-6(井上), V-10(灰野), V-12(横澤)) | * 下げ振り測定: *木村、荒木、井上、澤田、宮本 (KEK-2(木村), V-6(井上), V-2(荒木)) |
Line 41: | Line 87: |
* 和泉、麻生 * 山本、横澤 |
|
Line 44: | Line 92: |
* ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xエンド1F。 * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。 * 今日のみXエンド1Fがハザートエリアになりますので、Xエンド1Fで作業をする場合は必ずレーザーグラスをかけてください。 |
* ハザードエリアはIFIより奥。 |
Line 48: | Line 94: |
* 作業 * ビーム位置測定 * 日曜 EYAでの位置確認。ビームは縦が10cm、横が10cmを超えるくらい揺れている。GVのセンターの位置を2点落としてきた。 * 今日はIYAのビーム位置を落とす。 * XエンドのEXCのビームをTcamで確認できるか試している。今日も引き続き作業を行う。 * 防振関連 * 日曜にPR3とBSのアラインメントをOSEMでとったが、その際最初方法がわからず、中野->井上で技術伝承が取られた。 * BSのexcitationの止め方がわからなかったので、今日確認する。 |
|
Line 59: | Line 96: |
* 11/6の週: 火曜日くらいまでY側のビーム位置測定。 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。 |
* 11/6の週 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。 |
Line 72: | Line 109: |
* Location: Meeting room at Hokum , or educe, Polycom | * Location: Meeting room at Hokubukaikan, or eZuce, Polycom |
Line 75: | Line 112: |
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || | ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || |
Line 96: | Line 134: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Phase1
Phase2
Schedule
2017/11/8 updated
Working people assignment
* 責任者
- 下げ振り測定
- 11/9 *木村、荒木、沢田@IYV, IYC、荒木
- PR系測定、PR2,PR3タンク蓋閉め
- 11/13 *新井、正田(午後~)
- 11/14 *新井、正田
- 11/15 *木村、沢田、新井、正田(蓋閉め)
- 11/16 *木村、沢田、新井、正田(蓋閉め)
- 11/17 *新井、正田
- Watchdog測定, PRM release
- 11/20 *
- 11/21 *
- 11/22 *
- 11/23 *
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or educe
2017/11/9(Thu)
- 作業
- 下げ振り測定
- IXCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。2cm程度ずれていた。測定後IXCとBSの間のGVを閉めたので、今日真空引きを始める予定。
- 本日IYCで同じことをする。
- 防振関連
- BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。
- PR2のWatchdogが入ってしまった。
- Watchdogが入っても電流が多少流れる。抵抗値によるが、数十mV程度の電圧の最大値が存在し、そこまでは信号が出てしまう。線形でないが、ある程度の制御がされてしまうということ。
- 下げ振り測定
- 計算機関連
- k1prmのを準備してPRMの回路などをつなぎこむ。PR3を動かさないようにする。
- Daily
- 作業人員(*:責任者)
- 下げ振り測定: *木村、荒木、井上、澤田、宮本 (KEK-2(木村), V-6(井上), V-2(荒木))
- VIS: Mark, Enzo, 神津
- 和泉、麻生
- 山本、横澤
- Laser hazard
- PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
- ハザードエリアはIFIより奥。
- 作業人員(*:責任者)
- Weekly
- 11/6の週
- フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
- 11/6の週
- 問題点など
- コーチフィルターが不調。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|