== Task list == === Phase1 === === Phase2 === ----- == Schedule == 2017/11/8 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}} ----- == Working people assignment == * 責任者 * 下げ振り測定 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 . * PR系測定、PR2,PR3タンク蓋閉め * 11/13 *新井、正田(午後~) * 11/14 *新井、正田 * 11/15 *木村、沢田、新井、正田(蓋閉め) * 11/16 *木村、沢田、新井、正田(蓋閉め) * 11/17 *新井、正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 霜出、上泉 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> ----- |
|
Line 7: | Line 61: |
<<Anchor(MorningMeetings)>> | |
Line 13: | Line 68: |
2017/10/11(Wed) | 2017/11/10(Fri) * 作業 * 下げ振り測定 * IYCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。-X側に8mm程度ずれていた。高さはほぼぴったり。測定後IYCとBSの間のGVを閉めたので、今日真空引きを始める予定。 * IXCの真空槽の高さが4mm高かった。 * 防振関連 * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。 * BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。 * 計算機関連 * k1immtで使っていた光ファイバーケーブルは新しいラックのところまで来た。来週引き続き。 |
Line 16: | Line 83: |
* 作業人員 * MIF: 和泉(責人者)、苔山、横澤、新井、三代、中野、榎本 |
* 作業人員(*:責任者) * VIS: Mark, Enzo, 神津 |
Line 20: | Line 87: |
* 現在MC出口で2mW未満。今週一杯はPRMより上流のみハザードエリアにする予定。 | * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 |
Line 22: | Line 90: |
* 作業 * PRMを透過するまで光が通った。IMMT2をどこまで動かせるかを今日検討。PR2の真ん中に当てるのが目的。 * BS: Oplev側のファーストコンタクトを剥がした。もう一方は金曜くらい。今日はLVDTのキャリブレーションなど。 * BSチェンバーの位置測定を昨日、今日とする。(大石) * コミッショニング作業で人数が多い場合は分担サブグループの現場の責任者を決めて、入坑する人の取りまとめをする。 * PR2に届くまでBSの出口は塞いだままアラインメントを進める。 |
|
Line 30: | Line 92: |
* 今週の目標はPR3からの光がBSまで届くこと。 | * 11/6の週 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。 * 11/13の週 * PR系の位置測定。ただし月曜は拡大チーフ会議などがあり、作業はない見込み。 |
Line 32: | Line 98: |
* コーチフィルターが不調。 | |
Line 37: | Line 104: |
=== Weekly meeting === | <<Anchor(WeeklyMeetings)>> ==== Weekly meeting ==== * Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 39: | Line 120: |
* Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokum Kaikan, or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
---- === Other meetings === * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] |
Line 57: | Line 132: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Phase1
Phase2
Schedule
2017/11/8 updated
Working people assignment
* 責任者
- 下げ振り測定
- 11/9 *木村、荒木、沢田@IYV, IYC、荒木
- PR系測定、PR2,PR3タンク蓋閉め
- 11/13 *新井、正田(午後~)
- 11/14 *新井、正田
- 11/15 *木村、沢田、新井、正田(蓋閉め)
- 11/16 *木村、沢田、新井、正田(蓋閉め)
- 11/17 *新井、正田
- Watchdog測定, PRM release
- 11/20 *
- 11/21 *
- 11/22 *
- 11/23 *
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or educe
2017/11/10(Fri)
- 作業
- 下げ振り測定
- IYCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。-X側に8mm程度ずれていた。高さはほぼぴったり。測定後IYCとBSの間のGVを閉めたので、今日真空引きを始める予定。
- IXCの真空槽の高さが4mm高かった。
- 防振関連
- IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。
- BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。
- 下げ振り測定
- 計算機関連
- k1immtで使っていた光ファイバーケーブルは新しいラックのところまで来た。来週引き続き。
- Daily
- 作業人員(*:責任者)
- VIS: Mark, Enzo, 神津
- Laser hazard
- PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
- ハザードエリアはIFIより奥。
- 作業人員(*:責任者)
- Weekly
- 11/6の週
- フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
- 11/13の週
- PR系の位置測定。ただし月曜は拡大チーフ会議などがあり、作業はない見込み。
- 11/6の週
- 問題点など
- コーチフィルターが不調。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|