Differences between revisions 50 and 138 (spanning 88 versions)
Revision 50 as of 2017-10-12 16:54:04
Size: 3409
Comment:
Revision 138 as of 2017-11-14 08:59:01
Size: 5689
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
== Working people ==
Line 5: Line 4:
 * 10/12 *苔山、和泉、横澤、榎本、中野
 * 10/13 苔山、*横澤、榎本、中野
 .
 * 10/16 横澤、井上、榎本、*中野、麻生、Fabian、Enzo、平田、神津、新井
 * 10/17 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
 * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
 * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
 * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
 .
 * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
 * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
 * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
 * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
 * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
== Task list ==
Line 20: Line 6:
 . * 責任者 === Phase1 ===
=== Phase2 ===
Line 22: Line 10:
== Schedule ==
2017/11/8 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}}


-----
== Working people assignment ==
* 責任者
  
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
Line 26: Line 57:
<<Anchor(MorningMeetings)>>
Line 32: Line 64:
2017/10/12(Thur) 2017/11/14(Tue.)
Line 35: Line 67:
  * 作業人員
   * MIF: 苔山(責人者)、和泉、新井、三代、中野、榎本、鍛治
  * 作業
   * PR系測定: 昨日COACHフィルターをつけたため、IMMTなどが大きく揺れている。

   * 防振関連
    * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。
    * BSのTop filterのオフセットリリース及びMatrixの設定など。

  * 計算機関連
   * k1prmのケーブル接続。

  * 作業人員(*:責任者)
   * PR系測定: *新井、正田
   * VIS: Mark, Enzo
   * 計算機: 宮川、三代
Line 39: Line 83:
   * 現在MC出口で2mW未満。今週一杯はPRMより上流のみハザードエリアにする予定。
   * 来週以降も2mWでいこうと思っている。
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
Line 42: Line 86:
  * 作業
   * IMMT2を回転させて、PR2の真ん中までビームが通った。PSLで15mW、干渉計で1.5mW。次はPR2からBSへ。
   * BS: LVDT戻して、Oplevを動かした。Oplev側のもう一方を明日剥がす。
   * BSチェンバーの位置測定は完了。(大石)
Line 48: Line 88:
  * 今週の目標はPR3からの光がBSまで届くこと。   * 11/13の週
   * PR系の位置測定。
Line 50: Line 92:
  * コーチフィルターが不調。
Line 55: Line 98:
=== Weekly meeting === <<Anchor(WeeklyMeetings)>>
==== Weekly meeting ====
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 57: Line 114:
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokum Kaikan, or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 75: Line 126:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list

Phase1

Phase2


Schedule

2017/11/8 updated KAGRA/Commissioning/Commissioning_schedule_20171106.png


Working people assignment

* 責任者

  • PR系測定、PR2,PR3タンク蓋閉め
    • 11/13 *新井、正田(午後~)
    • 11/14 *新井、正田
    • 11/15 *木村、沢田、新井、正田(蓋閉め)
    • 11/16 *木村、沢田、新井、正田(蓋閉め)
    • 11/17 *新井、正田
  • Watchdog測定, PRM release
    • 11/20 *
    • 11/21 *
    • 11/22 *
    • 11/23 *



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/14(Tue.)

  • Daily
    • 作業
      • PR系測定: 昨日COACHフィルターをつけたため、IMMTなどが大きく揺れている。
      • 防振関連
        • IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。
        • BSのTop filterのオフセットリリース及びMatrixの設定など。
    • 計算機関連
      • k1prmのケーブル接続。
    • 作業人員(*:責任者)
      • PR系測定: *新井、正田
      • VIS: Mark, Enzo
      • 計算機: 宮川、三代
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはIFIより奥。
  • Weekly
    • 11/13の週
      • PR系の位置測定。
  • 問題点など
    • コーチフィルターが不調。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)