== Working people assignment ==
  
 . * 責任者
 * ビーム位置測定
  * 10/30 *内山、寺田、木村、井上、沢田@IXA
  * 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC
  * 11/1 *内山、寺田、木村、沢田@EXA
  .
  * 11/5 *内山、寺田、木村、井上、沢田@EYA
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
  .
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木

== Task list ==

=== Phase1 ===
=== Phase2 ===

-----
== Schedule ==
2017/11/8 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}}
Line 20: Line 16:
== Working people assignment ==
* 責任者
  
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .

 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, RefCav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 高橋、奥富
 * PicoMotor: 三代
 * Digital: 宮川、山本
 * 回路: 宮川、上泉、戸村、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
Line 24: Line 61:
<<Anchor(MorningMeetings)>>
Line 30: Line 68:
2017/10/30(Mon) 2017/11/9(Thu)

  * 作業
   * 下げ振り測定
    * IXCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。2cm程度ずれていた。測定後IXCとBSの間のGVを閉めたので、今日真空引きを始める予定。
    * 本日IYCで同じことをする。

   * 防振関連
    * BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。
   * PR2のWatchdogが入ってしまった。
    * Watchdogが入っても電流が多少流れる。抵抗値によるが、数十mV程度の電圧の最大値が存在し、そこまでは信号が出てしまう。線形でないが、ある程度の制御がされてしまうということ。

  * 計算機関連
   * k1prmのを準備してPRMの回路などをつなぎこむ。PR3を動かさないようにする。
Line 34: Line 85:
   * 位置測定: *内山、寺田、木村、井上、沢田@IXA
   * VIS: Mark, Enzo
   * 下げ振り測定: *木村、荒木、井上、澤田、宮本 (KEK-2(木村), V-6(井上), V-2(荒木))
   * VIS: Mark, Enzo, 神津
   * 和泉、麻生
   * 山本、横澤
Line 39: Line 92:
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。

  * 作業
   * アラインメント
    * Yエンドでシグナルを見ることができた。PR3でYまでのアラインメントを取り、BSをDC的に戻して、PR3で揺らした。Xエンドより、Yエンドの方が揺れている。BSのダンピングが問題。
   * BSのコイルドライバーをローパワーからハイパワーに変えた。ダンピングの改良が必要。
   * ビーム位置測定
    * IXAのタンクのベローズを外し、ビームを床に落とす。床を見ることができるスクリーンとカメラを設置する。
    * 明日はクライオスタットに入る予定。
   * ハザードエリアはIFIより奥。
Line 53: Line 96:
  * 10/30の週: ビーム位置測定。   * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
Line 57: Line 101:
  * 防振装置の操作の伝授
Line 63: Line 106:
<<Anchor(WeeklyMeetings)>>
Line 65: Line 109:
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_2017110
6.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=
4|G1707278-v4]]||
||6||2017/10/24|
|[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
Line 71: Line 118:
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 78: Line 125:
 * [[CommissioningWorkshop2017|Commissioning Workshop 2017]]  * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 87: Line 134:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list

Phase1

Phase2


Schedule

2017/11/8 updated KAGRA/Commissioning/Commissioning_schedule_20171106.png


Working people assignment

* 責任者

  • 下げ振り測定
    • 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  • PR系測定、PR2,PR3タンク蓋閉め
    • 11/13 *新井、正田(午後~)
    • 11/14 *新井、正田
    • 11/15 *木村、沢田、新井、正田(蓋閉め)
    • 11/16 *木村、沢田、新井、正田(蓋閉め)
    • 11/17 *新井、正田
  • Watchdog測定, PRM release
    • 11/20 *
    • 11/21 *
    • 11/22 *
    • 11/23 *



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/9(Thu)

  • 作業
    • 下げ振り測定
      • IXCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。2cm程度ずれていた。測定後IXCとBSの間のGVを閉めたので、今日真空引きを始める予定。
      • 本日IYCで同じことをする。
    • 防振関連
      • BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。
    • PR2のWatchdogが入ってしまった。
      • Watchdogが入っても電流が多少流れる。抵抗値によるが、数十mV程度の電圧の最大値が存在し、そこまでは信号が出てしまう。線形でないが、ある程度の制御がされてしまうということ。
  • 計算機関連
    • k1prmのを準備してPRMの回路などをつなぎこむ。PR3を動かさないようにする。
  • Daily
    • 作業人員(*:責任者)
      • 下げ振り測定: *木村、荒木、井上、澤田、宮本 (KEK-2(木村), V-6(井上), V-2(荒木))
      • VIS: Mark, Enzo, 神津
      • 和泉、麻生
      • 山本、横澤
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはIFIより奥。
  • Weekly
    • 11/6の週
      • フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
  • 問題点など
    • コーチフィルターが不調。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1