5249
Comment:
|
5689
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
== Working people assignment == . * 責任者 * ビーム位置測定 * 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC * 11/1 *内山、寺田、木村、沢田@EXA . * 11/5 *内山、寺田、木村、井上、沢田@EYA * 11/6 *内山、寺田、木村、井上、沢田@IYA * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木 . * 11/8 *木村、荒木、沢田@IXV, IXC、荒木 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 |
== Task list == === Phase1 === === Phase2 === ----- == Schedule == 2017/11/8 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}} |
Line 19: | Line 16: |
== Working people assignment == * 責任者 * PR系測定、PR2,PR3タンク蓋閉め * 11/13 *新井、正田(午後~) * 11/14 *新井、正田 * 11/15 *木村、沢田、新井、正田(蓋閉め) * 11/16 *木村、沢田、新井、正田(蓋閉め) * 11/17 *新井、正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> |
|
Line 23: | Line 57: |
<<Anchor(MorningMeetings)>> | |
Line 29: | Line 64: |
2017/10/30(Mon) | 2017/11/14(Tue.) |
Line 32: | Line 67: |
* 作業 * PR系測定: 昨日COACHフィルターをつけたため、IMMTなどが大きく揺れている。 * 防振関連 * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。 * BSのTop filterのオフセットリリース及びMatrixの設定など。 * 計算機関連 * k1prmのケーブル接続。 |
|
Line 33: | Line 78: |
* 位置測定: *内山、寺田、木村、井上、沢田@IXA, IXC(PHS: V-10寺田、V-9井上) * VIS: Mark, Enzo, 神津 * ビーム調整: 中野、三代 |
* PR系測定: *新井、正田 * VIS: Mark, Enzo * 計算機: 宮川、三代 |
Line 39: | Line 84: |
* ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。 * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。 * 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。 * 作業 * アラインメント * ビーム位置測定 * IXAのタンクのベローズを外して、フランジ面を出し、IXA側にスクリーンを置きビームを見た。その位置でビームを床に落とす。ビームがダクト中心に対して53mmだけ-Y側、+13mm上側にずれていた。 * その時ゲートバルブのビューポートを見たら、IXAからゲートバルブを見て右上側(-Y側)に見えた。 * EXに光を当てた状態で、PR3の真ん中に入れると、フロントのビューポートの真ん中から3-4cmずれる。PDのカウントが11000程度になり、台風前に戻った。理論値は1.4cmだけ-Y側にずれる。 * フロントのビューポートの真ん中に入れると、PR3の真ん中からずれる。ただしクリップはされていない。PDのカウントのほとんど改善はなかった。 * 最後にPR3の真ん中に戻した。 * 今日は@IXA, IXCでビーム位置を落とす。 |
* ハザードエリアはIFIより奥。 |
Line 55: | Line 88: |
* 10/30の週: ビーム位置測定。 | * 11/13の週 * PR系の位置測定。 |
Line 59: | Line 93: |
* 防振装置の操作の伝授 | |
Line 65: | Line 98: |
<<Anchor(WeeklyMeetings)>> | |
Line 67: | Line 101: |
* Location: Meeting room at Hokum , or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
Line 74: | Line 110: |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 90: | Line 126: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Phase1
Phase2
Schedule
2017/11/8 updated
Working people assignment
* 責任者
- PR系測定、PR2,PR3タンク蓋閉め
- 11/13 *新井、正田(午後~)
- 11/14 *新井、正田
- 11/15 *木村、沢田、新井、正田(蓋閉め)
- 11/16 *木村、沢田、新井、正田(蓋閉め)
- 11/17 *新井、正田
- Watchdog測定, PRM release
- 11/20 *
- 11/21 *
- 11/22 *
- 11/23 *
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or educe
2017/11/14(Tue.)
- Daily
- 作業
- PR系測定: 昨日COACHフィルターをつけたため、IMMTなどが大きく揺れている。
- 防振関連
- IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。
- BSのTop filterのオフセットリリース及びMatrixの設定など。
- 計算機関連
- k1prmのケーブル接続。
- 作業人員(*:責任者)
- PR系測定: *新井、正田
- VIS: Mark, Enzo
- 計算機: 宮川、三代
- Laser hazard
- PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
- ハザードエリアはIFIより奥。
- 作業
- Weekly
- 11/13の週
- PR系の位置測定。
- 11/13の週
- 問題点など
- コーチフィルターが不調。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools