Transmission Monitor (TMS) at EYT (Phase 1)
- With a fixed stage.
- TMS = BRT (beam reducing telescope) + GPT (Gouy phase telescope)
|
|
Links to knowledge
- 「図3_EXT,EYTの位置.pptx」
Interferometer Layout for Both IR and Green Beams, With and Without ITMs (Michimura)
Alignment Plan for TRY Optical Table in bKAGRA Phase 1 (Michimura)
- "両角_光学系レイアウト_v4.pdf" (Morozumi)
Task list
Note: some of the tasks can be done in parallel.
- Place/install the fixed stage.
- Needs some shims... but what is the required horizontalness?
- Place/install the BRT
- What is the references...?
Signal Assign
Pin Name |
Resistance |
Equipment |
Assign |
Comment1 |
Comment2 |
Connection |