2651
Comment:
|
7747
|
Deletions are marked like this. | Additions are marked like this. |
Line 4: | Line 4: |
== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- <<Anchor(Schedule)>> === Schedule === ----- == Working people assignment == * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]] == Readiness for the X arm commissioning == * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == }}} ----- <<Anchor(Meetings)>> |
|
Line 6: | Line 37: |
==== Daily Meetings (9AM) ==== Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]] ==== Weekly Meetings (Tuesday 11AM) ==== Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]] |
|
Line 7: | Line 44: |
=== Morning meeting === | <<Anchor(MorningMeetings)>> === Daily meeting === |
Line 10: | Line 48: |
* Location: Control room, or educe | * First ~10min in the morning meeting, as short as possible * Location: Control room and Fan hut connected by eZuce |
Line 13: | Line 52: |
2017/10/11(Wed) | === 2019/2/18(Mon.) === |
Line 15: | Line 54: |
* Daily * 作業人員 * MIF: 苔山、横澤、新井、三代、和泉、中野、榎本 * Laser hazard: 川村 |
=== Weekend === |
Line 20: | Line 56: |
* Laser hazard * 現在MC出口で2mW未満。今週一杯はPRMより上流のみハザードエリアにする予定。 |
=== Schedule === * Current status as of 1/22: IR and Green reached X end PD. * --(1/22: Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * --(1/23: Surface inspection for SR mirrors.)-- * --(1/24-25: Cleaning HR of SR3, SRM.)-- |
Line 23: | Line 62: |
* 作業 * PRMを透過するまで光が通った。IMMT2をどこまで動かせるかを今日検討。PR2の真ん中に当てるのが目的。 * BS: Oplev側のファーストコンタクトを剥がした。もう一方は金曜くらい。今日はLVDTのキャリブレーションなど。 * BSチェンバーの位置測定を昨日、今日とする。(大石) * コミッショニング作業で人数が多い場合は分担サブグループの現場の責任者を決めて、入坑する人の取りまとめをする。 * PR2に届くまでBSの出口は塞いだままアラインメントを進める。 |
* --(1/23: BS is aligned to Y-end PD by IR.)-- * --(1/27: ITMY is aligned to REFL by IR.)-- * --(1/27: ITMX is aligned to REFL by IR.)-- * --(1/27: Beam position of IR at SR3 is confirmed how far from the center.)-- |
Line 30: | Line 67: |
* Weekly * 今週の目標はPR3からの光がBSまで届くこと。 * 問題点など |
* --(1/28-29: SR3 is aligned to SR2 center by IR.)-- * --(1/28: Alignment of SR2 -> SRM by IR.)-- * --(1/29: Green beam is injected from SR2 AR surface to Y end PD.)-- * --(1/31: Removing bellows at PR and SR area.)-- * --(1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2)-- * --(2/5: Alignment of SRM to OMMT1 by IR)-- * --(2/6: Alignment of ETMY to POS by Green)-- * --(2/8: Alignment of form OMMT to OSTM by IR)-- * --(2/8: Alignment of form OSTM to OMC by IR)-- * --(2/14: Closing door for ITM chambers)-- * --(2/15: Closing door for other central area)-- * --(2/15: pumping down for ITMs)-- * --(2/15: pumping down for other central area)-- ==== Note ==== * Starting DRMI! ==== Report of work ==== * COM: Alignment for IMC, IMMT, PRMs are done yesterday. Beams have reached to both ETMX and ETMY. * Type B: Drifts were looked on Saturday. * TF seems to be OK as before. * Pico motor did not work. * Needs some work for BS, all SRMs to implement good controls. * Type A: Drifts were looked on Saturday. * ITMX seems to be OK, but needs some time to fix and measured for ITMY. ==== Work plan ==== * restore the controls of Type-As and Type-Bs * restore the alignment of them. * check the beam at REFL, POP, POS, and OMM/OMC Chambers. |
Line 38: | Line 107: |
<<Anchor(WeeklyMeetings)>> | |
Line 39: | Line 109: |
* Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokubukaikan, or eZuce, Polycom |
|
Line 40: | Line 112: |
* Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokum Kaikan, or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| ----- == Documents == * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]] == Communication tools == * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) ------ == for New members == * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]] |
||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| || ||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| || ||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| || ||58||2019/1/22||[[KAGRA/Commissioning/Weekly/20190122/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190122/Minute|Minute]]|| || ||57||2019/1/8||[[KAGRA/Commissioning/Weekly/20190108/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190108/Minute|Minute]]|| || ||56||2018/12/25||[[KAGRA/Commissioning/Weekly/20181225/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181225/Minute|Minute]]|| || ||55||2018/12/17||[[KAGRA/Commissioning/Weekly/20181217/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181217/Minute|Minute]]|| || ||54||2018/12/11||[[KAGRA/Commissioning/Weekly/20181211/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181211/Minute|Minute]]|| || ||53||2018/12/4 ||[[KAGRA/Commissioning/Weekly/20181204/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181204/Minute|Minute]]|| || ||52||2018/11/27||[[KAGRA/Commissioning/Weekly/20181127/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181127/Minute|Minute]]|| || ||51||2018/11/20||[[KAGRA/Commissioning/Weekly/20181120/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181120/Minute|Minute]]|| || ||50||2018/11/13||[[KAGRA/Commissioning/Weekly/20181113/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181113/Minute|Minute]]|| || ||49||2018/11/6 ||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| || ||48||2018/10/30||[[KAGRA/Commissioning/Weekly/20181030/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181030/Minute|Minute]]|| || ||47||2018/10/23||[[KAGRA/Commissioning/Weekly/20181023/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181023/Minute|Minute]]|| || ||46||2018/10/16||[[KAGRA/Commissioning/Weekly/20181016/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181016/Minute|Minute]]|| || ||45||2018/10/9 ||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| || ||44||2018/10/2 ||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| || ||43||2018/9/18 ||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| || ||42||2018/9/4 ||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| || ||41||2018/8/28 ||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| || ||40||2018/8/21 ||[[KAGRA/Commissioning/Weekly/20180821/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180821.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180821/Minute|Minute]]|| || ||39||2018/8/7 ||[[KAGRA/Commissioning/Weekly/20180807/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180807.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180807/Minute|Minute]]|| || ||38||2018/7/31 ||[[KAGRA/Commissioning/Weekly/201807031/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180731.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180731/Minute|Minute]]|| || ||37||2018/7/24 ||[[KAGRA/Commissioning/Weekly/201807024/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180724.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180724/Minute|Minute]]|| || ||36||2018/7/17 ||[[KAGRA/Commissioning/Weekly/201807017/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180717.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180717/Minute|Minute]]|| || ||35||2018/7/3 ||[[KAGRA/Commissioning/Weekly/20180703/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioni |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/2/18(Mon.)
Weekend
Schedule
- Current status as of 1/22: IR and Green reached X end PD.
1/22: Surface inspection for PR mirrors. Cleaning will be done after 1/31.
1/23: Surface inspection for SR mirrors.
1/24-25: Cleaning HR of SR3, SRM.
1/23: BS is aligned to Y-end PD by IR.
1/27: ITMY is aligned to REFL by IR.
1/27: ITMX is aligned to REFL by IR.
1/27: Beam position of IR at SR3 is confirmed how far from the center.
1/28-29: SR3 is aligned to SR2 center by IR.
1/28: Alignment of SR2 -> SRM by IR.
1/29: Green beam is injected from SR2 AR surface to Y end PD.
1/31: Removing bellows at PR and SR area.
1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2
2/5: Alignment of SRM to OMMT1 by IR
2/6: Alignment of ETMY to POS by Green
2/8: Alignment of form OMMT to OSTM by IR
2/8: Alignment of form OSTM to OMC by IR
2/14: Closing door for ITM chambers
2/15: Closing door for other central area
2/15: pumping down for ITMs
2/15: pumping down for other central area
Note
- Starting DRMI!
Report of work
- COM: Alignment for IMC, IMMT, PRMs are done yesterday. Beams have reached to both ETMX and ETMY.
- Type B: Drifts were looked on Saturday.
- TF seems to be OK as before.
- Pico motor did not work.
- Needs some work for BS, all SRMs to implement good controls.
- Type A: Drifts were looked on Saturday.
- ITMX seems to be OK, but needs some time to fix and measured for ITMY.
Work plan
- restore the controls of Type-As and Type-Bs
- restore the alignment of them.
- check the beam at REFL, POP, POS, and OMM/OMC Chambers.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
||35||2018/7/3 ||Agenda||[[attachment:KAGRA/Commissioning/Schedule/Commissioni