== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
<<Anchor(Schedule)>>
=== Schedule ===




-----
== Working people assignment ==
 * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]

== Readiness for the X arm commissioning ==
 * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]

  
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==


}}}
-----

<<Anchor(Meetings)>>
Line 6: Line 37:
==== Daily Meetings (9AM) ====
Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]

==== Weekly Meetings (Tuesday 11AM) ====
Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
Line 7: Line 44:
=== Morning meeting === <<Anchor(MorningMeetings)>>
=== Daily
meeting ===
Line 10: Line 48:
 * Location: Control room, or educe  * First ~10min in the morning meeting, as short as possible
 * Location: Control room and Fan hut connected by eZuce
Line 13: Line 52:
2017/10/12(Thur) === 2019/2/21(Wed.) ===
Line 15: Line 54:
 * Daily
  * 作業人員
   * MIF: 苔山(責人者)、和泉、新井、三代、中野、榎本
=== Weekend ===
Line 19: Line 56:
  * Laser hazard
   * 現在MC出口で2mW未満。今週一杯はPRMより上流のみハザードエリアにする予定。
   * 来週以降も2mWでいこうと思っている。
=== Schedule ===
Line 23: Line 58:
  * 作業
   * IMMT2を回転させて、PR2の真ん中までビームが通った。PSLで15mW、干渉計で1.5mW。次はPR2からBSへ。
   * BS: LVDT戻して、Oplevを動かした。Oplev側のもう一方を明日剥がす。
   * BSチェンバーの位置測定は完了。(大石)
 * Yend
  --(* 1/25-2/20: Yend Pcal finalization)--
  * 2/25-3/4: Yend WAB
  * 3/6~ : Yend pumpdown 3/6~
   * 3/7,8: leak test
Line 28: Line 64:
 * Weekly
  * 今週の目標はPR3からの光がBSまで届くこと。
 * 問題点など
 * Xend
  * --(2/11-2/14: Xend NAB installation)--
  * 2/21: Removing FC, Payload release
  * 2/23-3/10: Xend Pcal finalization 1
   * Periscope installation
   * Beam position by IR and Green
  * 2/27: ETMX release
  * 3/5: ETMX aligned
  * 3/5-3/10: Xend Pcal finalization 2
  * 3/11,12 Xend WAB finalization
  * 3/19,20, Heatlink etc.
  * 3/22 Pumping down
   * Leak test
 
 * 3/11~ : Night work start

 * 2/18-3/22 DRMI commissioning
 * 3/11-4/5 Y arm commissioning
 * 3/25-4/5 FPMI commissioning

==== Note ====

==== Report of work ====

 * COM: Alingnment for PR and BS and ITMS were recovered, and Michelson fringe was seen!
 * SRM: Yaw drift exists.
 * SR2: oplev shows something hitting.
 * VAC: small leakage was found at ITMY, but we leave it.
 * PEM: Camera lens of ITM is not enough.
 * DGS: PC for ETMX and ETMY were replaced.

==== Work plan ====
 * ETMX: Removing FC afternoon.
Line 36: Line 102:
<<Anchor(WeeklyMeetings)>>
Line 37: Line 104:
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
Line 38: Line 107:
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokum Kaikan, or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||




-----
== Documents ==
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]

== Communication tools ==

 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

------
== for New members ==
 * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]]
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| ||
||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| ||
||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| ||
||58||2019/1/22||[[KAGRA/Commissioning/Weekly/20190122/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190122/Minute|Minute]]|| ||
||57||2019/1/8||[[KAGRA/Commissioning/Weekly/20190108/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190108/Minute|Minute]]|| ||
||56||2018/12/25||[[KAGRA/Commissioning/Weekly/20181225/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181225/Minute|Minute]]|| ||
||55||2018/12/17||[[KAGRA/Commissioning/Weekly/20181217/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181217/Minute|Minute]]|| ||
||54||2018/12/11||[[KAGRA/Commissioning/Weekly/20181211/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181211/Minute|Minute]]|| ||
||53||2018/12/4 ||[[KAGRA/Commissioning/Weekly/20181204/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181204/Minute|Minute]]|| ||
||52||2018/11/27||[[KAGRA/Commissioning/Weekly/20181127/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181127/Minute|Minute]]|| ||
||51||2018/11/20||[[KAGRA/Commissioning/Weekly/20181120/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181120/Minute|Minute]]|| ||
||50||2018/11/13||[[KAGRA/Commissioning/Weekly/20181113/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181113/Minute|Minute]]|| ||
||49||2018/11/6 ||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| ||
||48||2018/10/30||[[KAGRA/Commissioning/Weekly/20181030/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181030/Minute|Minute]]|| ||
||47||2018/10/23||[[KAGRA/Commissioning/Weekly/20181023/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181023/Minute|Minute]]|| ||
||46||2018/10/16||[[KAGRA/Commissioning/Weekly/20181016/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181016/Minute|Minute]]|| ||
||45||2018/10/9 ||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| ||
||44||2018/10/2 ||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| ||
||43||2018/9/18 ||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| ||
||42||2018/9/4 ||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| ||
||41||2018/8/28 ||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| ||
||40||2018/8/21 ||[[KAGRA/Commissioning/Weekly/20180821/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180821.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180821/Minute|Minute]]|| ||
||39||2018/8/7 ||[[KAGRA/Commissioning/Weekly/20180807/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180807.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180807/Minute|Minute]]|| ||
||38||2018/7/31 ||[[KAGRA/Commissioning/Weekly/201807031/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180731.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180731/Minute|Minute]]|| ||
||37||2018/7/24 ||[[KAGRA/Commissioning/Weekly/201807024/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180724.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180724/Minute|Minute]]|| ||
||36||2018/7/17 ||[[KAGRA/Commissioning/Weekly/201807017/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180717.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180717/Minute|Minute]]|| ||
||35||2018/7/3 ||[[KAGRA/Commissioning/Weekly/20180703/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioni

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/2/21(Wed.)

Weekend

Schedule

  • Yend
    • * 1/25-2/20: Yend Pcal finalization

    • 2/25-3/4: Yend WAB
    • 3/6~ : Yend pumpdown 3/6~
      • 3/7,8: leak test
  • Xend
    • 2/11-2/14: Xend NAB installation

    • 2/21: Removing FC, Payload release
    • 2/23-3/10: Xend Pcal finalization 1
      • Periscope installation
      • Beam position by IR and Green
    • 2/27: ETMX release
    • 3/5: ETMX aligned
    • 3/5-3/10: Xend Pcal finalization 2
    • 3/11,12 Xend WAB finalization
    • 3/19,20, Heatlink etc.
    • 3/22 Pumping down
      • Leak test
  • 3/11~ : Night work start
  • 2/18-3/22 DRMI commissioning
  • 3/11-4/5 Y arm commissioning
  • 3/25-4/5 FPMI commissioning

Note

Report of work

  • COM: Alingnment for PR and BS and ITMS were recovered, and Michelson fringe was seen!
  • SRM: Yaw drift exists.
  • SR2: oplev shows something hitting.
  • VAC: small leakage was found at ITMY, but we leave it.
  • PEM: Camera lens of ITM is not enough.
  • DGS: PC for ETMX and ETMY were replaced.

Work plan

  • ETMX: Removing FC afternoon.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

||35||2018/7/3 ||Agenda||[[attachment:KAGRA/Commissioning/Schedule/Commissioni

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)