== Readiness for the X arm commissioning == * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] |
|
Line 33: | Line 37: |
==== Daily Meetings (1PM) ==== | ==== Daily Meetings (9AM) ==== |
Line 43: | Line 47: |
* Date and time: Every weekday, 1PM * ~10min, as short as possible |
* Date and time: Every weekday, 9AM * First ~10min in the morning meeting, as short as possible |
Line 47: | Line 51: |
=== 2018/11/16(Fri.) === | |
Line 49: | Line 52: |
==== Attendance ==== | === 2019/2/22(Fri.) === |
Line 51: | Line 54: |
* Control room: Oshino, Yokogawa, Sugimoto, Miyakawa, Fukunaga, Yamamoto, Nakano, Lucia * Fan hut: * Zoom: Enomoto, Kozakai |
=== Weekend === * COM(only control ): Nakano, Guiguo |
Line 56: | Line 58: |
==== Laser hazard ==== | === Schedule === |
Line 58: | Line 60: |
|||| ||Before 3PM||After 3PM || |||| || || || ||Center||PSL ||IR & Green||IR & Green|| ||Center||around PR2 ||IR & Green||IR & Green|| ||Center||behinde SR2&Yfront||IR ||IR || ||||X end 1F ||IR & Green||IR & Green|| ||||Y end 1F ||N/A ||N/A || |
* Yend * --(1/25-2/20: Yend Pcal finalization)-- * 2/25-3/4: Yend WAB * 3/6~ : Yend pumpdown 3/6~ * 3/7,8: leak test |
Line 66: | Line 66: |
==== Night workers in the mine ==== | * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * 2/23-3/10: Xend Pcal finalization 1 * Periscope installation * Beam position by IR and Green * 2/27: ETMX release * 3/5: ETMX aligned * 3/5-3/10: Xend Pcal finalization 2 * 3/11,12 Xend WAB finalization * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work starts |
Line 68: | Line 82: |
* MIF: Enomoto, Yokogawa, Yamamoto, Sugimoto, Nakano * CAL: Kozakai, Tomigami |
* 2/18-3/22 DRMI commissioning * 3/11-4/5 Y arm commissioning * 3/25-4/5 FPMI commissioning |
Line 71: | Line 86: |
=== Weekend === | ==== Note ==== |
Line 73: | Line 88: |
* Enomoto, Oshino | ==== Report of work ==== * CRY: FC of ETMX was removed, and cryo payload was released. * COM: Michelson was locked again! * Tried to lock PRMI, but PRM was not moving somehow. Actually PRMI was locked for 1 or 2 second. * SR3 got aligned and green reached to Y end. * SR2 was also aligned. |
Line 75: | Line 95: |
==== Transition from morning work (*:responsible person) ==== | * Type B: SRM seems to be healthy. * DGS: Dolphin connection for PRM and BS were done. |
Line 77: | Line 98: |
* IR moves still several times bandwidth of cavity resonance. * Status of illuminator of ETMX should be monitored. |
|
Line 80: | Line 99: |
==== Report of work (*:responsible person) ==== | |
Line 82: | Line 100: |
* ITMX optimization. ==== Work plan (*:responsible person) ==== * Working around illuminator. |
==== Work plan ==== * Type A: needs time for tuning of ITMX. |
Line 100: | Line 114: |
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| || ||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| || ||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| || ||58||2019/1/22||[[KAGRA/Commissioning/Weekly/20190122/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190122/Minute|Minute]]|| || ||57||2019/1/8||[[KAGRA/Commissioning/Weekly/20190108/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190108/Minute|Minute]]|| || ||56||2018/12/25||[[KAGRA/Commissioning/Weekly/20181225/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181225/Minute|Minute]]|| || ||55||2018/12/17||[[KAGRA/Commissioning/Weekly/20181217/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181217/Minute|Minute]]|| || ||54||2018/12/11||[[KAGRA/Commissioning/Weekly/20181211/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181211/Minute|Minute]]|| || ||53||2018/12/4 ||[[KAGRA/Commissioning/Weekly/20181204/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181204/Minute|Minute]]|| || ||52||2018/11/27||[[KAGRA/Commissioning/Weekly/20181127/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181127/Minute|Minute]]|| || ||51||2018/11/20||[[KAGRA/Commissioning/Weekly/20181120/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181120/Minute|Minute]]|| || |
|
Line 101: | Line 126: |
||49||2018/11/6||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| || | ||49||2018/11/6 ||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| || |
Line 105: | Line 130: |
||45||2018/10/9||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| || ||44||2018/10/2||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| || ||43||2018/9/18||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| || ||42||2018/9/4||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| || ||41||2018/8/28||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| || ||40||2018/8/21||[[KAGRA/Commissioning/Weekly/20180821/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180821.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180821/Minute|Minute]]|| || ||39||2018/8/7||[[KAGRA/Commissioning/Weekly/20180807/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180807.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180807/Minute|Minute]]|| || ||38||2018/7/31||[[KAGRA/Commissioning/Weekly/201807031/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180731.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180731/Minute|Minute]]|| || ||37||2018/7/24||[[KAGRA/Commissioning/Weekly/201807024/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180724.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180724/Minute|Minute]]|| || ||36||2018/7/17||[[KAGRA/Commissioning/Weekly/201807017/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180717.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180717/Minute|Minute]]|| || ||35||2018/7/3||[[KAGRA/Commissioning/Weekly/20180703/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180703.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180703/Minute|Minute]]|| || ||34||2018/6/26||[[KAGRA/Commissioning/Weekly/20180626/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180626.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180626/Minute|Minute]]|| || ||33||2018/6/19||[[KAGRA/Commissioning/Weekly/20180619/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180619.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180619/Minute|Minute]]|| || ||32||2018/6/12||[[KAGRA/Commissioning/Weekly/20180612/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180612.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180612/Minute|Minute]]|| || ||31||2018/6/5||[[KAGRA/Commissioning/Weekly/20180605/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180605.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180605/Minute|Minute]]|| || ||30||2018/5/22||[[KAGRA/Commissioning/Weekly/20180522/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180522.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180522/Minute|Minute]]|| || ||29||2018/5/8||[[KAGRA/Commissioning/Weekly/20180508/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180508.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180508/Minute|Minute]]|| || ||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| ---- === Other meetings === * 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Agenda/memo|Minute]] * 2018/8/30: 3rd Meeting for pump down at ITMX ([[/Meetings/Others/20180830|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]]) * 2018/8/23: 2nd Meeting for pump down at ITMX ([[/Meetings/Others/20180823|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]]) * 2018/8/16: Meeting for pump down at ITMX ([[/Meetings/Others/20180816|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]]) * 2018/5/28: [[KAGRA/Commissioning/Meetings/Others/20180528/Phase1|Meeting for looking back to phase1 for future of KAGRA]] as an extended chief meeting. * 2018/4/11: Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * 2018/4/5: Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * 2018/3/14: Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) * 2018/1/18: Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * 2018/1/17: Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * 2018/1/10: Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * 2017/12/13: Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * 2017/11/27~12/1[[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] * 2017/11/17: Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) * 2017/10/12: Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) ----- == Documents == * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]] == Communication tools == * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) ------ == for New members == * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]] |
||45||2018/10/9 ||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| || ||44||2018/10/2 ||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| || ||43||2018/9/18 ||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| || ||42||2018/9/4 ||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| || ||41||2018/8/28 ||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| || ||40||2018/8/21 ||[[KAGRA/Commissioning/Weekly/20180821/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180821.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180821/Minute|Minute]]|| || ||39||2018/8/7 ||[[KAGRA/Commissioning/Weekly/20180807/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180807.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180807/Minute|Minute]]|| || ||38||2018/7/31 ||[[KAGRA/Commissioning/Weekly/201807031/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180731.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180731/Minute|Minute]]|| || ||37||2018/7/24 ||[[KAGRA/Commissioning/Weekly/201807024/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180724.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180724/Minute|Minute]]|| || ||36||2018/7/17 ||[[KAGRA/Commissioning/Weekly/201807017/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180717.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180717/Minute|Minute]]|| || ||35||2018/7/3 ||[[KAGRA/Commissioning/Weekly/20180703/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioni |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/2/22(Fri.)
Weekend
- COM(only control ): Nakano, Guiguo
Schedule
- Yend
1/25-2/20: Yend Pcal finalization
- 2/25-3/4: Yend WAB
- 3/6~ : Yend pumpdown 3/6~
- 3/7,8: leak test
- Xend
2/11-2/14: Xend NAB installation
2/21: Removing FC, Payload release
- 2/23-3/10: Xend Pcal finalization 1
- Periscope installation
- Beam position by IR and Green
- 2/27: ETMX release
- 3/5: ETMX aligned
- 3/5-3/10: Xend Pcal finalization 2
- 3/11,12 Xend WAB finalization
- 3/19,20, Heatlink etc.
- 3/22 Pumping down
- Leak test
- 3/11~ : Night work starts
- 2/18-3/22 DRMI commissioning
- 3/11-4/5 Y arm commissioning
- 3/25-4/5 FPMI commissioning
Note
Report of work
- CRY: FC of ETMX was removed, and cryo payload was released.
- COM: Michelson was locked again!
- Tried to lock PRMI, but PRM was not moving somehow. Actually PRMI was locked for 1 or 2 second.
- SR3 got aligned and green reached to Y end.
- SR2 was also aligned.
- Type B: SRM seems to be healthy.
- DGS: Dolphin connection for PRM and BS were done.
Work plan
- Type A: needs time for tuning of ITMX.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
||35||2018/7/3 ||Agenda||[[attachment:KAGRA/Commissioning/Schedule/Commissioni