=== Phase1 === === Phase2 === |
* [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
Line 13: | Line 19: |
* ビーム位置測定 * 11/6 *内山、寺田、木村、井上、沢田@IYA * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木 . * 11/8 *木村、荒木、沢田@IXV, IXC、荒木 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 |
Line 20: | Line 23: |
* Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
|
Line 21: | Line 29: |
{{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} |
|
Line 28: | Line 54: |
<<Anchor(MorningMeetings)>> | |
Line 34: | Line 61: |
2017/11/6(Mon.) | 2017/11/27(Mon.) |
Line 37: | Line 64: |
* 作業 * Type Bp: インナーフレームの足が浮いているので締め直す必要がある。 * 今日、明日でミラプロに頼んで締め直しをする。 * PRMのリリースはビームのアラインメントが終わってから。 * WS * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。 * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。 * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。 |
|
Line 38: | Line 75: |
* 位置測定: *内山、寺田、木村、井上、沢田、灰野、横澤(V-6(井上), V-10(灰野), V-12(横澤)) * VIS: Mark, Enzo, 神津 |
* WS: *麻生、苔山、宮川 + 20名程度(見学) |
Line 42: | Line 78: |
* PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xエンド1F。 * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。 * 今日のみXエンド1Fがハザートエリアになりますので、Xエンド1Fで作業をする場合は必ずレーザーグラスをかけてください。 * 作業 * ビーム位置測定 * 日曜 EYAでの位置確認。ビームは縦が10cm、横が10cmを超えるくらい揺れている。GVのセンターの位置を2点落としてきた。 * 今日はIYAのビーム位置を落とす。 * XエンドのEXCのビームをTcamで確認できるか試している。今日も引き続き作業を行う。 * 防振関連 * 日曜にPR3とBSのアラインメントをOSEMでとったが、その際最初方法がわからず、中野->井上で技術伝承が取られた。 * BSのexcitationの止め方がわからなかったので、今日確認する。 |
* 今週はSRラインより奥。 |
Line 58: | Line 81: |
* 11/6の週: 火曜日くらいまでY側のビーム位置測定。 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。 |
* 11/27の週 * Commissioning Work Shop(11/27-12/1) * PRMの締め直し。 * メインビームの再アラインメント。 * 12/4の週 * Type Aダンピングテスト。 * 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 |
Line 62: | Line 94: |
* コーチフィルターが不調。 | * PRMの足が浮いている。 * D-SUBケーブルがおかしくなったものが出た。 |
Line 68: | Line 102: |
<<Anchor(WeeklyMeetings)>> | |
Line 70: | Line 105: |
* Location: Meeting room at Hokum , or educe, Polycom | * Location: Meeting room at Hokubukaikan, or eZuce, Polycom |
Line 73: | Line 108: |
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || | ||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || |
Line 84: | Line 121: |
* Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) | |
Line 94: | Line 132: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/11/14 updated
Working people assignment
* 責任者
- PR系測定、PR2,PR3タンク蓋閉め
- 11/16 木村、沢田、新井、*正田(蓋閉め)
- 11/17 新井、*正田
- Watchdog測定, PRM release
- 11/20 *
- 11/21 *
- 11/22 *
- 11/23 *
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or educe
2017/11/27(Mon.)
- Daily
- 作業
- Type Bp: インナーフレームの足が浮いているので締め直す必要がある。
- 今日、明日でミラプロに頼んで締め直しをする。
- PRMのリリースはビームのアラインメントが終わってから。
- WS
- 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
- 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
- メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。
- Type Bp: インナーフレームの足が浮いているので締め直す必要がある。
- 作業人員(*:責任者)
- WS: *麻生、苔山、宮川 + 20名程度(見学)
- Laser hazard
- 今週はSRラインより奥。
- 作業
- Weekly
- 11/27の週
- Commissioning Work Shop(11/27-12/1)
- PRMの締め直し。
- メインビームの再アラインメント。
- 12/4の週
- Type Aダンピングテスト。
- 12/11の週
- ETMYからの戻り光確認。
- 12/18EYC閉止。
- 11/27の週
- 問題点など
- PRMの足が浮いている。
- D-SUBケーブルがおかしくなったものが出た。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
10 |
2017/11/21 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|