== Schedule ==
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
Line 13: Line 19:
 * ビーム位置測定
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
  .
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/15 木村、沢田、新井、*正田(蓋閉め)
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 20: Line 24:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
Line 21: Line 30:
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
Line 35: Line 62:
2017/11/6(Mon.) 2017/11/14(Wed.)
Line 38: Line 65:
  * 作業
   * PR系測定
    * PR2の位置測定が完了。解析中。
    * PR3オプティカルベンチの高さ合わせをした。
    * 今日PR2のオプティカルベンチのたかさを合わせる。PR3とPR2のフタ締めをする。

  * 計算機関連
   * k1prmのケーブル接続をする。

  * Commission workの準備: QPDの設置など
Line 39: Line 77:
   * 位置測定: *内山、寺田、木村、井上、沢田、灰野、横澤(V-6(井上), V-10(灰野), V-12(横澤))
   * VIS: Mark, Enzo, 神津
   * PR系測定: *正田、新井
   * 計算機: 宮川
   * WSの準備: 苔山、三代
   * 真空テスト: 宗宮
Line 44: Line 84:
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xエンド1F。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 今日のみXエンド1Fがハザートエリアになりますので、Xエンド1Fで作業をする場合は必ずレーザーグラスをかけてください。

  * 作業
   * ビーム位置測定
    * 日曜 EYAでの位置確認。ビームは縦が10cm、横が10cmを超えるくらい揺れている。GVのセンターの位置を2点落としてきた。
    * 今日はIYAのビーム位置を落とす。
    * XエンドのEXCのビームをTcamで確認できるか試している。今日も引き続き作業を行う。

   * 防振関連
    * 日曜にPR3とBSのアラインメントをOSEMでとったが、その際最初方法がわからず、中野->井上で技術伝承が取られた。
    * BSのexcitationの止め方がわからなかったので、今日確認する。
   * ハザードエリアはIFIより奥。
Line 59: Line 87:
  * 11/6の週: 火曜日くらいまでY側のビーム位置測定。
  * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。
  * 11/13の週
   * PR系の位置測定。
  * 11/20の週
   * Watch dogのテストとPRMのリリース。
Line 63: Line 93:
  * コーチフィルターが不調。
Line 72: Line 101:
 * Location: Meeting room at Hokum , or educe, Polycom  * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
Line 75: Line 104:
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
Line 96: Line 127:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/11/14 updated KAGRA/Commissioning/Commissioning_schedule_20171114.png


Working people assignment

* 責任者

  • PR系測定、PR2,PR3タンク蓋閉め
    • 11/15 木村、沢田、新井、*正田(蓋閉め)
    • 11/16 木村、沢田、新井、*正田(蓋閉め)
    • 11/17 新井、*正田
  • Watchdog測定, PRM release
    • 11/20 *
    • 11/21 *
    • 11/22 *
    • 11/23 *



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/14(Wed.)

  • Daily
    • 作業
      • PR系測定
        • PR2の位置測定が完了。解析中。
        • PR3オプティカルベンチの高さ合わせをした。
        • 今日PR2のオプティカルベンチのたかさを合わせる。PR3とPR2のフタ締めをする。
    • 計算機関連
      • k1prmのケーブル接続をする。
    • Commission workの準備: QPDの設置など
    • 作業人員(*:責任者)
      • PR系測定: *正田、新井
      • 計算機: 宮川
      • WSの準備: 苔山、三代
      • 真空テスト: 宗宮
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはIFIより奥。
  • Weekly
    • 11/13の週
      • PR系の位置測定。
    • 11/20の週
      • Watch dogのテストとPRMのリリース。
  • 問題点など

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

10

2017/11/21

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings