Differences between revisions 119 and 167 (spanning 48 versions)
Revision 119 as of 2017-11-08 15:48:00
Size: 5863
Comment:
Revision 167 as of 2017-11-28 08:30:08
Size: 6426
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
Line 13: Line 19:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .
Line 18: Line 20:
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
* 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 30: Line 29:
*PR3-BS間ビーム位置測定(内山、寺田、和泉)12/6-7予定。
Line 32: Line 33:
== Contact person for subsystem == <<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==
Line 34: Line 36:
 * Laser, RefCav, IMC: 苔山、中野  * Laser, Ref''''''Cav, IMC: 苔山、中野
Line 39: Line 41:
  * Type A: 奥富、高橋
  * PicoMotor: 三代
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
Line 42: Line 44:
 * 回路: 上泉、霜出、宮川  * 回路: 上泉、霜出
Line 45: Line 47:
 * 水漏れなど: 古田、早河
Line 60: Line 63:
2017/11/8(Wed.) 2017/11/27(Mon.)
Line 63: Line 66:
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているので締め直す必要がある。今日、明日でミラプロに頼んで締め直しをする。
    * PRMのリリースはビームのアラインメントと並行に進める。今週後半か。
   * WS
    * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
    * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
   * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。

Line 64: Line 77:
   * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木))
   * VIS: Mark, Enzo, 神津
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
Line 68: Line 80:
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。

  * 作業
   * ビーム位置測定
    * IYCでの位置測定をした。完了。現在まとめ中。
    * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。

   * 防振関連
    * BSのlength sensing Oplev, オフセットリリースなど。

   * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。
   * 今日明日はIMMTより奥、水曜からSRラインより奥。
Line 82: Line 83:
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直し。
   * メインビームの再アラインメント。

  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
Line 86: Line 96:
  * コーチフィルターが不調。   * PRMの足が浮いている。
  * D-SUBケーブルがおかしくなったものが出た。
Line 95: Line 107:
 * Location: Meeting room at Hokum , or educe, Polycom  * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
Line 98: Line 110:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 110: Line 123:
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/11/14 updated KAGRA/Commissioning/Commissioning_schedule_20171114.png


Working people assignment

* 責任者

  • PR系測定、PR2,PR3タンク蓋閉め
    • 11/16 木村、沢田、新井、*正田(蓋閉め)
    • 11/17 新井、*正田
  • Watchdog測定, PRM release
    • 11/20 *
    • 11/21 *
    • 11/22 *
    • 11/23 *

*PR3-BS間ビーム位置測定(内山、寺田、和泉)12/6-7予定。



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/27(Mon.)

  • Daily
    • 作業
      • Type Bp:
        • インナーフレームの足が浮いているので締め直す必要がある。今日、明日でミラプロに頼んで締め直しをする。
        • PRMのリリースはビームのアラインメントと並行に進める。今週後半か。
      • WS
        • 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
        • 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
      • メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。
    • 作業人員(*:責任者)
      • WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
    • Laser hazard
      • 今日明日はIMMTより奥、水曜からSRラインより奥。
  • Weekly
    • 11/27の週
      • Commissioning Work Shop(11/27-12/1)
      • PRMの締め直し。
      • メインビームの再アラインメント。
    • 12/4の週
      • Type Aダンピングテスト。
    • 12/11の週
      • ETMYからの戻り光確認。
      • 12/18EYC閉止。
  • 問題点など
    • PRMの足が浮いている。
    • D-SUBケーブルがおかしくなったものが出た。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

10

2017/11/21

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)