Differences between revisions 154 and 190 (spanning 36 versions)
Revision 154 as of 2017-11-17 11:15:27
Size: 6232
Comment:
Revision 190 as of 2017-12-11 09:10:36
Size: 6438
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/11
  * 12/12 和泉
  * 12/13 和泉
  * 12/14 和泉、長野
  * 12/15 和泉、長野、榎本
 
 * GigEカメラセット
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
Line 29: Line 34:
 * BS PDセット
  * 12/11
  * 12/12 横澤
  * 12/13 横澤
  * 12/14
  * 12/15
  
Line 58: Line 70:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 61: Line 73:
2017/11/17(Fri.) 2017/12/11(Mon.)
Line 64: Line 76:
  * 作業
   * PR系測定
    * PR2タンク上部を閉めた。
    * タンクO-ringを閉めるときに、PR2のOplevがずれてしまった可能性が高い。
    * FAROのPR2の測定結果: -Xに9mm -Zに5mmずれていることが判明。
    * 本日PR3の測定をする。来週続いてPRMも測定する。
  * 報告と作業 (*:責任者)

   * アラインメント:
    * 現在Xエンドまで通っている。明日、明後日でEYAに通す。

   * Type B: *Mark、Enzo, 神津、正田
    * 今日も引き続き制御系のチェックをする。

   * Type A: 午後から*高橋(2637)、奥富、宮本
    * actuatorのテストなどの続き。
    * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。

   * PD設置: 横澤
    * PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。
Line 72: Line 92:
  * 計算機関連
   * k1prmのケーブル接続を引き続き継続。
  * Laser hazard
   * SRラインより奥。

 * Weekly

  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。
Line 76: Line 104:
  * 作業人員(*:責任者)
   * PR系測定: *正田、新井、木村、澤田
   * 計算機: 宮川、山本

  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。

 * Weekly
  * 11/13の週
   * PR系の位置測定。
  * 11/20の週
   * PR系の位置測定。
   * Watch dogのテストとPRMのリリース。
Line 92: Line 105:
  * ケーブル、作業スペースなどの環境が恐ろしく悪い。
  * PR2、3のアラインメントにメインビームが必要。CRYは今週はメンビームは出して欲しくない。
  * フタしめの、ボルトのありかがわからない(木村) -> 内山
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
Line 107: Line 121:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 120: Line 134:
 * Meeting for closing ETY ([[/KAGRA/Commissioning/Meetings/Others/20171117|Minute]])  * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/11/28 updated KAGRA/Commissioning/Commissioning_schedule_20171128.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/11
    • 12/12 和泉
    • 12/13 和泉
    • 12/14 和泉、長野
    • 12/15 和泉、長野、榎本
  • GigEカメラセット
    • 12/11
    • 12/12
    • 12/13
    • 12/14
    • 12/15
  • BS PDセット
    • 12/11
    • 12/12 横澤
    • 12/13 横澤
    • 12/14
    • 12/15



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/11(Mon.)

  • Daily
    • 報告と作業 (*:責任者)
      • アラインメント:
        • 現在Xエンドまで通っている。明日、明後日でEYAに通す。
      • Type B: *Mark、Enzo, 神津、正田
        • 今日も引き続き制御系のチェックをする。
      • Type A: 午後から*高橋(2637)、奥富、宮本
        • actuatorのテストなどの続き。
        • Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。
      • PD設置: 横澤
        • PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。
    • Laser hazard
      • SRラインより奥。
  • Weekly
    • 12/11の週
      • メインビームの再アラインメント。
      • ETMYからの戻り光確認。
      • 12/13 昼休みに真空引きの前のミーティング。
      • 12/18 EYC閉止。
  • 問題点など
    • PR-BS相対位置測定後、EXでの再位置測定が必要か?
    • PR系のスリップが頻発している。特にPR3。
    • BSテーブルにPDを置けるかどうか。
    • Eendの遮蔽板をいつ開けるか。
    • 真空引きの最終確認。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members