Line 3: Line 3:

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}


-----
Line 4: Line 17:
 * MIF
  * 10/13 苔山、*横澤、榎本、中野、三代、新井
  .
  * 10/16 横澤、井上、榎本、*中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/17 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  .
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
* 責任者
  
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 19: Line 23:
 . * 責任者  * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。

{{{#!wiki comment/dotted
Line 21: Line 33:
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
Line 25: Line 56:
<<Anchor(MorningMeetings)>>
Line 31: Line 63:
2017/10/13(Fri) 2017/11/28(Tue.)
Line 34: Line 66:
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているのでシムを入れて、傾きを補正して締め直したす。水平になっているはず。
    * PRMを今日リリースする予定。
   * アラインメント
    * PSLQPDでピッチ方向にずれ、MCTのQPDにヨー方向にずれがあった。IMMT1、2のアラインメントを取り直して、PR真空曹のフランジのセンターには当たった。
    * メインビームのアラインメントは明日の水曜以降に続ける。
   * WS
    * 昨日夕方から一部実際の作業が始まっている。
    * 物の準備はだいたい完了。一部足りないものを持ち込むなどの作業がある。

Line 35: Line 79:
   * MIF: 苔山、*横澤、榎本、中野、三代、新井    * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * Type Bp: 正田(SRの作業の合間)
Line 38: Line 83:
   * PSLから15mWで、IMC入り口で10mW、PRM以降は1mW程度。今日のPR2の作業によって来週エンドをハザードエリアにするか決める。
   * 来週以降も2mWでいこうと思っている。

  * 作業
   * PR2からの反射光が1m先で数cm下がっていた。10mradのオーダー。PR2が水平かどうかの確認。する予定。(苔山)
   * BS: ファーストコンタクトを今日剥がす(大石)。あとはブレッドボードの高さ調整と、リモートコントロールが必要。
   * 今日までIMMTより奥、明日の水曜からSRラインより奥に変更。
Line 46: Line 86:
  * 今週の目標はPR3からの光がBSまで届くこと。   * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。

  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。

Line 48: Line 99:
  * PR2の反射光を解決する必要がある。来週以降の遅れを生む可能性あり。   * D-SUBケーブルがおかしくなったものが出た。 -> AEL
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * 一部のカメラが表示されない(和泉、Stefan)。 -> 苔山
Line 54: Line 108:
<<Anchor(WeeklyMeetings)>>
Line 56: Line 111:
 * Location: Meeting room at Hokum Kaikan, or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 66: Line 127:
 * Meeting about SR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])  * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
* Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 75: Line 138:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/11/28 updated KAGRA/Commissioning/Commissioning_schedule_20171128.png


Working people assignment

* 責任者

  • PR系測定、PR2,PR3タンク蓋閉め
    • 11/16 木村、沢田、新井、*正田(蓋閉め)
    • 11/17 新井、*正田
  • Watchdog測定, PRM release
    • 11/20 *
    • 11/21 *
    • 11/22 *
    • 11/23 *
  • PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/28(Tue.)

  • Daily
    • 作業
      • Type Bp:
        • インナーフレームの足が浮いているのでシムを入れて、傾きを補正して締め直したす。水平になっているはず。
        • PRMを今日リリースする予定。
      • アラインメント
        • PSLQPDでピッチ方向にずれ、MCTのQPDにヨー方向にずれがあった。IMMT1、2のアラインメントを取り直して、PR真空曹のフランジのセンターには当たった。
        • メインビームのアラインメントは明日の水曜以降に続ける。
      • WS
        • 昨日夕方から一部実際の作業が始まっている。
        • 物の準備はだいたい完了。一部足りないものを持ち込むなどの作業がある。
    • 作業人員(*:責任者)
      • WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
      • Type Bp: 正田(SRの作業の合間)
    • Laser hazard
      • 今日までIMMTより奥、明日の水曜からSRラインより奥に変更。
  • Weekly
    • 11/27の週
      • Commissioning Work Shop(11/27-12/1)
      • PRMの締め直しと、リリース。
      • メインビームの再アラインメント。
    • 12/4の週
      • Type Aダンピングテスト。
    • 12/11の週
      • ETMYからの戻り光確認。
      • 12/18EYC閉止。
  • 問題点など
    • D-SUBケーブルがおかしくなったものが出た。 -> AEL

    • 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS

    • 一部のカメラが表示されない(和泉、Stefan)。 -> 苔山

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1