Line 3: Line 3:

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}


-----
Line 4: Line 17:
 * MIF + VIS
  * 10/13 苔山、*横澤、榎本、中野、三代、新井
  .
  * 10/16 横澤、井上、榎本、*中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/17 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  .
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
* 責任者
  
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 19: Line 23:
 . * 責任者  * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

{{{#!wiki comment/dotted
Line 21: Line 31:
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
Line 25: Line 54:
<<Anchor(MorningMeetings)>>
Line 31: Line 61:
2017/10/13(Fri) 2017/11/14(Wed.)
Line 34: Line 64:
  * 作業
   * PR系測定
    * PR2のオプティカルベンチの高さ調整と、スタンダードフィルターの調整、固定、FAROをつかった測定などをした。PR3の測定が完了。PR2もPR3の高さが5mmくらい低い。PR3とPR2のフタ締めも完了。
    * PR2に関しては、サスペンションがずれたかOplevがずれたかどちらかわからないが、いずれにしてもずれた。メインビームが必要。今週いっぱいはレーザーは出して欲しくない(CRY)。
    * PR3のタンクを占めている間におそらくOplevがずれた。いつアラインメントを直すかの検討をする。


  * 計算機関連
   * k1prmのケーブル接続を引き続き継続。

  * Commission workの準備: QPDの設置など
Line 35: Line 77:
   * MIF: 苔山、*横澤、榎本、中野、三代、新井    * PR系測定: *正田、新井、飯田、(和泉)、木村、澤田
   * 計算機: 宮川、山本
   * WSの準備: 苔山、三代
   * 真空テスト: 宗宮
Line 38: Line 83:
   * PSLから15mWで、IMC入り口で10mW、PRM以降は1mW程度。今日のPR2の作業によって来週エンドをハザードエリアにするか決める。
   * 来週以降も2mWでいこうと思っている。

  * 作業
   * PR2からの反射光が1m先で数cm下がっていた。10mradのオーダー。PR2が水平かどうかの確認。する予定。(苔山)
   * BS: ファーストコンタクトを今日剥がす(大石)。あとはブレッドボードの高さ調整と、リモートコントロールが必要。
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
Line 46: Line 87:
  * 今週の目標はPR3からの光がBSまで届くこと。   * 11/13の週
   * PR系の位置測定。
  * 11/20の週
   * Watch dogのテストとPRMのリリース。
Line 48: Line 93:
  * PR2の反射光を解決する必要がある。来週以降の遅れを生む可能性あり。   * ケーブル、作業スペースなどの環境が恐ろしく悪い。
  * PR2、3のアラインメントにメインビームが必要。CRYは今週はメンビームは出して欲しくない。
Line 54: Line 101:
<<Anchor(WeeklyMeetings)>>
Line 56: Line 104:
 * Location: Meeting room at Hokum Kaikan, or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 66: Line 120:
 * Meeting about SR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])  * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 75: Line 130:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/11/14 updated KAGRA/Commissioning/Commissioning_schedule_20171114.png


Working people assignment

* 責任者

  • PR系測定、PR2,PR3タンク蓋閉め
    • 11/16 木村、沢田、新井、*正田(蓋閉め)
    • 11/17 新井、*正田
  • Watchdog測定, PRM release
    • 11/20 *
    • 11/21 *
    • 11/22 *
    • 11/23 *



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or educe

2017/11/14(Wed.)

  • Daily
    • 作業
      • PR系測定
        • PR2のオプティカルベンチの高さ調整と、スタンダードフィルターの調整、固定、FAROをつかった測定などをした。PR3の測定が完了。PR2もPR3の高さが5mmくらい低い。PR3とPR2のフタ締めも完了。
        • PR2に関しては、サスペンションがずれたかOplevがずれたかどちらかわからないが、いずれにしてもずれた。メインビームが必要。今週いっぱいはレーザーは出して欲しくない(CRY)。
        • PR3のタンクを占めている間におそらくOplevがずれた。いつアラインメントを直すかの検討をする。
    • 計算機関連
      • k1prmのケーブル接続を引き続き継続。
    • Commission workの準備: QPDの設置など
    • 作業人員(*:責任者)
      • PR系測定: *正田、新井、飯田、(和泉)、木村、澤田
      • 計算機: 宮川、山本
      • WSの準備: 苔山、三代
      • 真空テスト: 宗宮
    • Laser hazard
      • PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
      • ハザードエリアはIFIより奥。
  • Weekly
    • 11/13の週
      • PR系の位置測定。
    • 11/20の週
      • Watch dogのテストとPRMのリリース。
  • 問題点など
    • ケーブル、作業スペースなどの環境が恐ろしく悪い。
    • PR2、3のアラインメントにメインビームが必要。CRYは今週はメンビームは出して欲しくない。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

10

2017/11/21

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1