4864
Comment:
|
6145
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} ----- |
|
Line 4: | Line 17: |
* MIF + VIS | * 責任者 |
Line 6: | Line 19: |
* 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 . * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 |
Line 14: | Line 23: |
. * 責任者 | * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * {{{#!wiki comment/dotted |
Line 16: | Line 31: |
<<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> |
|
Line 20: | Line 54: |
<<Anchor(MorningMeetings)>> | |
Line 26: | Line 61: |
2017/10/19(Thur) | 2017/11/17(Fri.) |
Line 29: | Line 64: |
* 作業 * PR系測定 * PR2タンク上部を閉めた。 * タンクO-ringを閉めるときに、PR2のOplevがずれてしまった可能性が高い。 * FAROのPR2の測定結果: -Xに9mm -Zに5mmずれていることが判明。 * 本日PR3の測定をする。来週続いてPRMも測定する。 * 計算機関連 * k1prmのケーブル接続を引き続き継続。 |
|
Line 30: | Line 77: |
* MIF+VIS: *和泉、榎本、中野、神津、新井、正田、井上、灰野、横澤、宮川 (PHS: V-3(榎本), V-7(中野), V-12(横澤)) Fabian、Enzo、平田、 |
* PR系測定: *正田、新井、木村、澤田 * 計算機: 宮川、山本 |
Line 35: | Line 81: |
* PSL直後で100mW、IMC出口で50mW程度、PRM以降は5mW程度。 * 今日のある時点からハザードエリアがSR2とSR3の間のラインより奥(機械室は除く)になる。 * 中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。 * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを各自1個ずつ持っていって下さい。そして、もし、中央エリアがハザードエリアになった場合は、帰りなどに中央エリアを通る際は保護メガネの着用をお願いします。保護メガネは、前室の入り口横に移動される保護メガネ台に返してください。 * Xエンドに行く方は保護メガネは必要ありません。 * 作業 * アラインメント(中野) * BSまで光が到達した。X方向に打ち込んでいる。ゲートバルブのビューポートの端に通っている。 * PR3のお辞儀をなおした。OSEMもレンジ内。曲率が24mなのでセンタリングに反射光の方向がすごく依存するので、まだアラインメントに確証が持てない。 * BSも3mradくらいピッチ方向にずれている模様。 * カメラをインストールしている。マウントとケーブル張りは完了。イルミネーターが課題。(井上) * PDの信号がふらついているのでそのチェッックをして欲しい。(和泉) |
* PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 |
Line 50: | Line 85: |
* 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。 | * 11/13の週 * PR系の位置測定。 * 11/20の週 * PR系の位置測定。 * Watch dogのテストとPRMのリリース。 |
Line 52: | Line 92: |
* コーチフィルターが不調。 * PR3の前室のクリーンブースのシートが落ちてしまっているのは直った(中田)。 |
* ケーブル、作業スペースなどの環境が恐ろしく悪い。 * PR2、3のアラインメントにメインビームが必要。CRYは今週はメンビームは出して欲しくない。 * フタしめの、ボルトのありかがわからない(木村) -> 内山 |
Line 59: | Line 101: |
<<Anchor(WeeklyMeetings)>> | |
Line 61: | Line 104: |
* Location: Meeting room at Hokum , or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
Line 66: | Line 114: |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 73: | Line 121: |
* [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] | |
Line 81: | Line 130: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/11/14 updated
Working people assignment
* 責任者
- PR系測定、PR2,PR3タンク蓋閉め
- 11/16 木村、沢田、新井、*正田(蓋閉め)
- 11/17 新井、*正田
- Watchdog測定, PRM release
- 11/20 *
- 11/21 *
- 11/22 *
- 11/23 *
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or educe
2017/11/17(Fri.)
- Daily
- 作業
- PR系測定
- PR2タンク上部を閉めた。
- タンクO-ringを閉めるときに、PR2のOplevがずれてしまった可能性が高い。
- FAROのPR2の測定結果: -Xに9mm -Zに5mmずれていることが判明。
- 本日PR3の測定をする。来週続いてPRMも測定する。
- PR系測定
- 計算機関連
- k1prmのケーブル接続を引き続き継続。
- 作業人員(*:責任者)
- PR系測定: *正田、新井、木村、澤田
- 計算機: 宮川、山本
- Laser hazard
- PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
- ハザードエリアはIFIより奥。
- 作業
- Weekly
- 11/13の週
- PR系の位置測定。
- 11/20の週
- PR系の位置測定。
- Watch dogのテストとPRMのリリース。
- 11/13の週
- 問題点など
- ケーブル、作業スペースなどの環境が恐ろしく悪い。
- PR2、3のアラインメントにメインビームが必要。CRYは今週はメンビームは出して欲しくない。
フタしめの、ボルトのありかがわからない(木村) -> 内山
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
10 |
2017/11/21 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools