== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} ----- |
|
Line 4: | Line 17: |
* MIF + VIS | * 責任者 |
Line 6: | Line 19: |
* 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か . |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 |
Line 13: | Line 23: |
. * 責任者 | * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * {{{#!wiki comment/dotted |
Line 15: | Line 31: |
<<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> |
|
Line 19: | Line 54: |
<<Anchor(MorningMeetings)>> | |
Line 25: | Line 61: |
2017/10/20(Fri) | 2017/11/22(Wed.) |
Line 28: | Line 64: |
* 作業 * Type A: 復帰した。 * IOO: PSLとMCともに光軸ズレがありそう。今日もう一度確認する。 * 計算機: ほぼ復帰。k1bsとk1ey1, k1ex0, k1ey0に少しトラブルあり。 * Type Bp: PR系は信号は来ている。PR2のAAフィルターが調子が悪いので交換。PRMのリリースをしたがぶつかっている様子。 * タンクからサテライトボックスまでのD-SUBケーブルが一つダメになっている。 * PR2のBIOを一枚増やした。カードの認識がバラバラ。インプットとアウトプットさえバラバラ。 * 真空: MC復帰した。Xarm復帰した。Yarmを今日か明日復帰する。 * Yendピット内の水がまだ冠水中。今日シートをかぶせて作業を再開。 * MCFの前のGreenとPOP用光学定盤を移動させたい。 * 12時からeZuceでiKAGRAからの引き継ぎ会議。 停電のため報告、作業予定特になし。 |
|
Line 29: | Line 80: |
* MIF+VIS: *和泉、榎本、新井、正田、井上、灰野、横澤、土田、Fabian、Enzo、平田 (PHS: V-2(井上), V-3(榎本), V-7(), V-12(横澤)) | * Type Bp: *正田、和泉、田中 * MIF/AOS: *道村、阿久津、中田 |
Line 32: | Line 84: |
* PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。 * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。 * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを使い通過して下さい。メガネはそのまま持って行って、帰りに中央エリアを通る際は再び保護メガネの着用をお願いします。 * EXA, EYAの真空槽まわりで作業する人は保護メガネをかけください。そばを通るだけの方は保護メガネは必要ありません。 * 作業 * アラインメント(和泉) * 日に日にアラインメントがずれているようだったので、Oplevをキャリブレーションし直した。IMMTなどファクター3とか10間違っていた。 * Xエンドまで光が通った。直接光かどうかはまだ不明。PDのゲイン調整と、センサーカードで確認予定。 * PR2が100urad程度揺れている模様。 * X/Y end * EXAにカメラがインストールされた。 * 200HzのノイズはLEDと判明。リモートでオンオフできないので、現在は消してある。 * EYAにもビューポーを設置した。EYAにもカメラをつけるかどうか検討する。(井上) |
* IFIより奥。 |
Line 48: | Line 87: |
* 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。->ほぼ目標達成。 * 10/23の週: Yエンドに光を送る。 |
* 11/20の週 * 昨日停電復帰。 * PR系の位置測定。 * Watch dogのテストとPRMのリリース。 |
Line 52: | Line 94: |
* コーチフィルターが不調。 | * PR2、3のアラインメントにメインビームが必要。CRYは今週はメインビームは出して欲しくない。 * PRMがリリースしたがぶつかっている様子。 * D-SUBケーブルがおかしくなったものが出た。 |
Line 58: | Line 103: |
<<Anchor(WeeklyMeetings)>> | |
Line 60: | Line 106: |
* Location: Meeting room at Hokum , or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||6||2017/10/24|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
Line 66: | Line 116: |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 72: | Line 122: |
* Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) | |
Line 73: | Line 124: |
* [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] | |
Line 81: | Line 133: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/11/14 updated
Working people assignment
* 責任者
- PR系測定、PR2,PR3タンク蓋閉め
- 11/16 木村、沢田、新井、*正田(蓋閉め)
- 11/17 新井、*正田
- Watchdog測定, PRM release
- 11/20 *
- 11/21 *
- 11/22 *
- 11/23 *
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or educe
2017/11/22(Wed.)
- Daily
- 作業
- Type A: 復帰した。
- IOO: PSLとMCともに光軸ズレがありそう。今日もう一度確認する。
- 計算機: ほぼ復帰。k1bsとk1ey1, k1ex0, k1ey0に少しトラブルあり。
- Type Bp: PR系は信号は来ている。PR2のAAフィルターが調子が悪いので交換。PRMのリリースをしたがぶつかっている様子。
- タンクからサテライトボックスまでのD-SUBケーブルが一つダメになっている。
- PR2のBIOを一枚増やした。カードの認識がバラバラ。インプットとアウトプットさえバラバラ。
- 真空: MC復帰した。Xarm復帰した。Yarmを今日か明日復帰する。
- Yendピット内の水がまだ冠水中。今日シートをかぶせて作業を再開。
- MCFの前のGreenとPOP用光学定盤を移動させたい。
- 12時からeZuceでiKAGRAからの引き継ぎ会議。
- 作業
停電のため報告、作業予定特になし。
- 作業人員(*:責任者)
- Type Bp: *正田、和泉、田中
- MIF/AOS: *道村、阿久津、中田
- Laser hazard
- IFIより奥。
- Weekly
- 11/20の週
- 昨日停電復帰。
- PR系の位置測定。
- Watch dogのテストとPRMのリリース。
- 11/20の週
- 問題点など
- PR2、3のアラインメントにメインビームが必要。CRYは今週はメインビームは出して欲しくない。
- PRMがリリースしたがぶつかっている様子。
- D-SUBケーブルがおかしくなったものが出た。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
10 |
2017/11/21 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|