== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/11/28 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}} ----- |
|
Line 4: | Line 17: |
* MIF + VIS | * 責任者 |
Line 6: | Line 19: |
* 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か . |
|
Line 13: | Line 20: |
. * 責任者 | * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。 * ETMYアラインメント * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 {{{#!wiki comment/dotted |
Line 15: | Line 32: |
<<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> |
|
Line 19: | Line 55: |
<<Anchor(MorningMeetings)>> | |
Line 22: | Line 59: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 25: | Line 62: |
2017/10/20(Fri) | 2017/12/7(Thur.) |
Line 28: | Line 65: |
* 作業人員(*:責任者) * MIF+VIS: *和泉、榎本、新井、正田、井上、灰野、横澤、土田、Fabian、Enzo、平田 (PHS: V-2(井上), V-3(榎本), V-7(), V-12(横澤)) |
* 作業 (*:責任者) * 位置測定: *内山、寺田(V-11, 2831) * 昨日は準備。鏡の中心を測った。今日はビームの位置を比較確認。 * アラインメント: 和泉(2829) * レーザー不調のため、アラインメントはそれほど進展がなかった。 * レーザーはFSSがロックしなかった。AOMのドライバーが不調だったが、結局電源のバナナピンの接触不良が原因であることが判明。MCも復帰した。 * ピコモーターのジョイスティックをつなげるところを間違えて、SMT1のピッチを動かしてしまった。そのためでFIを通っていない時間が存在する。FI後のQPDで確認しながら復帰。 * 現在ETMXまでは光がいっている。 * Type B: *Mark、平田、Fabian * 新しいマトリックスがうまくいって、キャリブレーションがとれた。そのためダンピングも改良できそう。 * Type A: *高橋(2637)、奥富 * EYCのペイロードがBS方向に1cmずれていることが一昨日の時点で判明。ヒートリンクが引っ剝いている可能性がある。150gGの力でこれくらいのずれになる見込み。 * トップは2mm程度のずれで、こちらは問題なさそう。 * Cry: 宮本 * actuatorのテストなどする予定。できれば伝達関数測定までしたい。 * AEL: MC WFSで問題のあったI&Q demodulatorの3chテスト結果は、特に問題ないというものだった。よって坑内で何がダメだったのかは不明。 |
Line 32: | Line 89: |
* PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。 * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。 * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを使い通過して下さい。メガネはそのまま持って行って、帰りに中央エリアを通る際は再び保護メガネの着用をお願いします。 * EXA, EYAの真空槽まわりで作業する人は保護メガネをかけください。そばを通るだけの方は保護メガネは必要ありません。 * 作業 * アラインメント(和泉) * 日に日にアラインメントがずれているようだったので、Oplevをキャリブレーションし直した。IMMTなどファクター3とか10間違っていた。 * Xエンドまで光が通った。直接光かどうかはまだ不明。PDのゲイン調整と、センサーカードで確認予定。 * PR2が100urad程度揺れている模様。 * X/Y end * EXAにカメラがインストールされた。 * 200HzのノイズはLEDと判明。リモートでオンオフできないので、現在は消してある。 * EYAにもビューポーを設置した。EYAにもカメラをつけるかどうか検討する。(井上) |
* SRラインより奥。 |
Line 48: | Line 92: |
* 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。->ほぼ目標達成。 * 10/23の週: Yエンドに光を送る。 |
* 12/4の週 * Type Aダンピングテスト。 * メインビームの再アラインメント。 * 月、火にIYC、IXCでの真空作業がある。 * 12/6,7: PR-BS相対位置測 * 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 |
Line 52: | Line 104: |
* コーチフィルターが不調。 | * PR-BS相対位置測定後、EXでの再位置測定が必要か? |
Line 58: | Line 110: |
<<Anchor(WeeklyMeetings)>> | |
Line 60: | Line 113: |
* Location: Meeting room at Hokum , or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
Line 66: | Line 123: |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 72: | Line 129: |
* Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) | |
Line 73: | Line 131: |
* [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] | |
Line 81: | Line 140: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/11/28 updated
Working people assignment
* 責任者
- PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
- ETMYアラインメント
- 12/11
- 12/12
- 12/13
- 12/14
- 12/15
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/7(Thur.)
- Daily
- 作業 (*:責任者)
- 位置測定: *内山、寺田(V-11, 2831)
- 昨日は準備。鏡の中心を測った。今日はビームの位置を比較確認。
- アラインメント: 和泉(2829)
- レーザー不調のため、アラインメントはそれほど進展がなかった。
- レーザーはFSSがロックしなかった。AOMのドライバーが不調だったが、結局電源のバナナピンの接触不良が原因であることが判明。MCも復帰した。
- ピコモーターのジョイスティックをつなげるところを間違えて、SMT1のピッチを動かしてしまった。そのためでFIを通っていない時間が存在する。FI後のQPDで確認しながら復帰。
- 現在ETMXまでは光がいっている。
- Type B: *Mark、平田、Fabian
- 新しいマトリックスがうまくいって、キャリブレーションがとれた。そのためダンピングも改良できそう。
- Type A: *高橋(2637)、奥富
- EYCのペイロードがBS方向に1cmずれていることが一昨日の時点で判明。ヒートリンクが引っ剝いている可能性がある。150gGの力でこれくらいのずれになる見込み。
- トップは2mm程度のずれで、こちらは問題なさそう。
- Cry: 宮本
- actuatorのテストなどする予定。できれば伝達関数測定までしたい。
AEL: MC WFSで問題のあったI&Q demodulatorの3chテスト結果は、特に問題ないというものだった。よって坑内で何がダメだったのかは不明。
- 位置測定: *内山、寺田(V-11, 2831)
- Laser hazard
- SRラインより奥。
- 作業 (*:責任者)
- Weekly
- 12/4の週
- Type Aダンピングテスト。
- メインビームの再アラインメント。
- 月、火にIYC、IXCでの真空作業がある。
- 12/6,7: PR-BS相対位置測
- 12/11の週
- ETMYからの戻り光確認。
- 12/18EYC閉止。
- 12/4の週
- 問題点など
- PR-BS相対位置測定後、EXでの再位置測定が必要か?
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Documents
Communication tools