Size: 167
Comment:
|
Size: 7672
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
----- | |
Line 3: | Line 4: |
* [[KAGRA/Commissioning/Meeting|Meeting]] | == Task list == |
Line 5: | Line 6: |
* [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/12/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}} ----- == Working people assignment == * 責任者 * ETMYアラインメント * 12/13 和泉 * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/13 * 12/14 * 12/15 * BS PDセット * 12/13 横澤 * 12/14 * 12/15 {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> ----- == Meetings == ---- <<Anchor(MorningMeetings)>> === Morning meeting === * Date and time: Every weekday, 9AM * Location: Control room, or eZuce 2017/12/13(Wed.) * Daily * 本日12時半よりファン小屋で真空関連の打ち合わせ。 * 出席予定者: * 木村、宮川、牛場、高橋、都丸、和泉 * (eZuce) 阿久津、井上 * 報告と作業 (*:責任者) * アラインメント: *和泉 * YendのPDに光を届けた。BSを特にいじることなく、すぐに光が通った。PR2のダンピングを調整する必要があった。 * BSは依然10uradくらいのオーダーで揺れている。 * Type B: *Mark、Enzo, 正田, 和泉 * IP yaw, IM, TMのpitchのダンピングを入れた。 * Yawの動きがまだ大きい。これは全体の回転のようである。上のマグネティックダンパーで減衰されるはずがうまく効いていない。 * サスペンション全体が4mm程度下に下がっているかもしれない。 * 蓋を開けなければならないので、今日やることを考える。 * Type A: *牛場、宮本 * Yawが回転したが、力がある閾値を超えるとガクッと回るような感じである。ベアリングが渋い可能性が高い。 * 回るのも数分のオーダーで、微調整がかなり厳しそう。回転の方向は正しいことは確認した。 * BFのダンピングを強くするともう少し素直に反応する可能性がある。 * 今日は上部のダンピング制御を入れて操作して様子を見てみる。DC制御か? * PD設置: * Laser hazard * SRラインより奥。 * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。 * Weekly * 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 * 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 <<MonthCalendar(KAGRA/Commissioning/DailyWork)>> ---- <<Anchor(WeeklyMeetings)>> ==== Weekly meeting ==== * Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| ---- === Other meetings === * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] ----- == Documents == * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]] == Communication tools == * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) ------ |
|
Line 6: | Line 166: |
* [[KAGRA/Commissioning/ML|Joining commissioning mailing list]] | * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]] |
KAGRA Commissioning Wiki
Task list
Schedule
2017/12/12 updated
Working people assignment
* 責任者
- ETMYアラインメント
- 12/13 和泉
- 12/14 和泉、長野、川﨑
- 12/15 和泉、長野、川﨑、榎本
- GigEカメラセット
- 12/13
- 12/14
- 12/15
- BS PDセット
- 12/13 横澤
- 12/14
- 12/15
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/13(Wed.)
- Daily
- 本日12時半よりファン小屋で真空関連の打ち合わせ。
- 出席予定者:
- 木村、宮川、牛場、高橋、都丸、和泉
- (eZuce) 阿久津、井上
- 出席予定者:
- 報告と作業 (*:責任者)
- アラインメント: *和泉
- YendのPDに光を届けた。BSを特にいじることなく、すぐに光が通った。PR2のダンピングを調整する必要があった。
- BSは依然10uradくらいのオーダーで揺れている。
- Type B: *Mark、Enzo, 正田, 和泉
- IP yaw, IM, TMのpitchのダンピングを入れた。
- Yawの動きがまだ大きい。これは全体の回転のようである。上のマグネティックダンパーで減衰されるはずがうまく効いていない。
- サスペンション全体が4mm程度下に下がっているかもしれない。
- 蓋を開けなければならないので、今日やることを考える。
- Type A: *牛場、宮本
- Yawが回転したが、力がある閾値を超えるとガクッと回るような感じである。ベアリングが渋い可能性が高い。
- 回るのも数分のオーダーで、微調整がかなり厳しそう。回転の方向は正しいことは確認した。
- BFのダンピングを強くするともう少し素直に反応する可能性がある。
- 今日は上部のダンピング制御を入れて操作して様子を見てみる。DC制御か?
- PD設置:
- アラインメント: *和泉
- Laser hazard
- SRラインより奥。
- 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
- 本日12時半よりファン小屋で真空関連の打ち合わせ。
- Weekly
- 12/11の週
- メインビームの再アラインメント。
- ETMYからの戻り光確認。
- 12/13 昼休みに真空引きの前のミーティング。
- 12/18 EYC閉止。
- 12/11の週
- 問題点など
- PR-BS相対位置測定後、EXでの再位置測定が必要か?
- PR系のスリップが頻発している。特にPR3。
- BSテーブルにPDを置けるかどうか。
- Eendの遮蔽板をいつ開けるか。
- 真空引きの最終確認。
KAGRA/Commissioning/DailyWork << < 2025 / 5 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | |||
5 | 6 | 7 | 8 | 9 | 10 | 11 |
12 | 13 | 14 | 15 | 16 | 17 | 18 |
19 | 20 | 21 | 22 | 23 | 24 | 25 |
26 | 27 | 28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Documents
Communication tools