== Schedule ==
2017/12/11 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}}
Line 13: Line 19:
 * ビーム位置測定
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
  .
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
Line 20: Line 20:
 * ETMYアラインメント
  * 12/11
  * 12/12 和泉
  * 12/13 和泉
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
Line 21: Line 34:
 * BS PDセット
  * 12/11
  * 12/12 横澤
  * 12/13 横澤
  * 12/14
  * 12/15
  
{{{#!wiki comment/dotted
Line 22: Line 43:
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
Line 26: Line 66:
<<Anchor(MorningMeetings)>>
Line 29: Line 70:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 32: Line 73:
2017/11/6(Mon.) 2017/12/12(Tue.)
Line 35: Line 76:
  * 作業人員(*:責任者)
   * 位置測定: *内山、寺田、木村、井上、沢田、灰野、横澤(V-6(井上), V-10(灰野), V-12(横澤))
   * VIS: Mark, Enzo, 神津
  * 報告と作業 (*:責任者)

   * アラインメント: *和泉、苔山、野替
    * 今日午後から、Xエンドのビームの確認、その後EYAに通す予定。PR2,3のOplevのダンピングをしたい。
    * 現在PR3は固定してあるが、Phase1の間は固定したままで残すことを考えている。
     * ワイヤーのテンションをきちんと張って落ち着かせる方法をVIRGOの人から聞いたので、とりあえずSRで試してみる予定。

   * Type A: *高橋、奥富、宮本
    * Oplevのキャリブレーションについてklogに報告があった。どれだけ進んでいるのか要確認。
    * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。アルミホイルで塞ぐ方法もあるので、基本的に開ける方向で進める。

   * PD設置: 横澤
    * 明日PDをYendからBSに持ってくることになりそう。BSテーブルでのマウント方法を検討する必要がある。

   * Type B: *Mark、Enzo, 正田
    * 光学テーブルのアクチュエーターが一部働いていないところがあるのが見つかった。ハイパワーコイルドライバーでテストする。

Line 40: Line 96:
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xエンド1F。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 今日のみXエンド1Fがハザートエリアになりますので、Xエンド1Fで作業をする場合は必ずレーザーグラスをかけてください。

  * 作業
   * ビーム位置測定
    * 日曜 EYAでの位置確認。ビームは縦が10cm、横が10cmを超えるくらい揺れている。GVのセンターの位置を2点落としてきた。
    * 今日はIYAのビーム位置を落とす。
    * XエンドのEXCのビームをTcamで確認できるか試している。今日も引き続き作業を行う。

   * 防振関連
    * 日曜にPR3とBSのアラインメントをOSEMでとったが、その際最初方法がわからず、中野->井上で技術伝承が取られた。
    * BSのexcitationの止め方がわからなかったので、今日確認する。
   * SRラインより奥。
Line 56: Line 99:
  * 11/6の週: 火曜日くらいまでY側のビーム位置測定。
  * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。

  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。
Line 60: Line 108:
  * コーチフィルターが不調。   * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
Line 66: Line 118:
<<Anchor(WeeklyMeetings)>>
Line 68: Line 121:
 * Location: Meeting room at Hokum , or educe, Polycom  * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
Line 71: Line 124:
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
Line 82: Line 138:
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
Line 92: Line 149:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/11 updated KAGRA/Commissioning/Commissioning_schedule_20171212.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/11
    • 12/12 和泉
    • 12/13 和泉
    • 12/14 和泉、長野、川﨑
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/11
    • 12/12
    • 12/13
    • 12/14
    • 12/15
  • BS PDセット
    • 12/11
    • 12/12 横澤
    • 12/13 横澤
    • 12/14
    • 12/15



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/12(Tue.)

  • Daily
    • 報告と作業 (*:責任者)
      • アラインメント: *和泉、苔山、野替
        • 今日午後から、Xエンドのビームの確認、その後EYAに通す予定。PR2,3のOplevのダンピングをしたい。
        • 現在PR3は固定してあるが、Phase1の間は固定したままで残すことを考えている。
          • ワイヤーのテンションをきちんと張って落ち着かせる方法をVIRGOの人から聞いたので、とりあえずSRで試してみる予定。
      • Type A: *高橋、奥富、宮本
        • Oplevのキャリブレーションについてklogに報告があった。どれだけ進んでいるのか要確認。
        • Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。アルミホイルで塞ぐ方法もあるので、基本的に開ける方向で進める。
      • PD設置: 横澤
        • 明日PDをYendからBSに持ってくることになりそう。BSテーブルでのマウント方法を検討する必要がある。
      • Type B: *Mark、Enzo, 正田
        • 光学テーブルのアクチュエーターが一部働いていないところがあるのが見つかった。ハイパワーコイルドライバーでテストする。
    • Laser hazard
      • SRラインより奥。
  • Weekly
    • 12/11の週
      • メインビームの再アラインメント。
      • ETMYからの戻り光確認。
      • 12/13 昼休みに真空引きの前のミーティング。
      • 12/18 EYC閉止。
  • 問題点など
    • PR-BS相対位置測定後、EXでの再位置測定が必要か?
    • PR系のスリップが頻発している。特にPR3。
    • BSテーブルにPDを置けるかどうか。
    • Eendの遮蔽板をいつ開けるか。
    • 真空引きの最終確認。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1