Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 13: Line 19:
 * ビーム位置測定
  * 11/6 *内山、寺田、木村、井上、沢田@IYA
  * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
  .
  * 11/8 *木村、荒木、沢田@IXV, IXC、荒木
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
Line 20: Line 20:
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 21: Line 26:
 * BS PDセット
  * 12/15 横澤

  
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
Line 32: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 35: Line 62:
2017/11/7(Tue.) 2017/12/18(Mon.)
Line 37: Line 64:
 * Daily
  * 作業人員(*:責任者)
   * 位置測定: *内山、寺田 @IYC, Yend、井上、灰野(V-6(井上), V-10(灰野))
   * VIS: Mark, Enzo, 神津
 * 作業報告 (*:責任者)
  * アラインメント: *和泉、長野、榎本、川崎
   * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
   * BFのピコモーターが離散的に動く。5mrad程度のステップ。
Line 42: Line 69:
  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)及び、Xend 1F。今日の午後からIFIから奥に移行する。
   * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、レーザーグラスはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
   * 注意: Xend 1Fが昨日に引き続き今日もハザードエリア。作業が終わり次第解除される。
  * Type A(ETMY): *牛場、宮本、都丸、和泉
   * ベアリングを押しているバネが動きを吸収している可能性がある。

  * PD設置: *横澤、和泉、井上
   * BSチェンバー内、AS側に設置完了。

  * BSカメラ設置: *苔山、川崎
   * BS付近に設置したが、レンズ交換が必要。

 * 作業予定 (*:責任者)
  * アラインメント: *和泉、都丸
   * BFを固定した方がアラインメントはやりやすいのでは?(都丸)

  * Type A(ETMY): *高橋、牛場、都丸、和泉
   * バネを変える。
   * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
   * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。
    * 今日、明日くらいが蓋閉めの準備のためにその作業をするので、その間に解決することを目標にする。
   * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
   * 火曜日の夕方に方向性を判断。

  * PD設置: *横澤、井上
   * EYAにいってViewポートを取り付ける。
Line 49: Line 94:
  * 作業
   * ビーム位置測定
    * IYAのビームを測定した。フロントでもpeak to peakで1cmビームは揺れている。落ち着いている時もあり、時々大きく揺れるような様子。少なくともXよりは揺れている。BSから40mくらい離れているが、その距離にしてはかなり揺れている。そのため、エンドではPDに当たらないくらい揺れている。
    * 今日はIYCでの作業。EYCはGmatの上に落としてあるだけなので、それをダクトの上に落とす。

    * XエンドのEXCの鏡の位置でのビームがTcamで確認できた。アルミニウムのスクリーンに落としてあり、かなりはっきり見えている。エンドのビューポートでクリップされたedgeが見えている。PDの影も見えている。
    * Yエンドに関してはPDのゲインがサチっているので下げる。

   * 防振関連
    * BSのOSEMのオフセットを除く試みをする。もう少し揺れは小さくなる予定。
 * Laser hazard
   * センターはSR奥がハザードエリア。エンドはハザードエリアなし。
Line 61: Line 98:
  * 11/6の週
   * 火曜日くらいまでY側のビーム位置測定。
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。
  * 11/8に見学があるので、今日11/7の午後にビームIFIのところで止める。

  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
Line 67: Line 105:
  * コーチフィルターが不調。   * 回路電源のモニターがあるといい。
Line 76: Line 115:
 * Location: Meeting room at Hokum , or educe, Polycom  * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
Line 79: Line 118:
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
Line 90: Line 132:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
Line 100: Line 144:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/18(Mon.)

  • 作業報告 (*:責任者)
    • アラインメント: *和泉、長野、榎本、川崎
      • BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
      • BFのピコモーターが離散的に動く。5mrad程度のステップ。
    • Type A(ETMY): *牛場、宮本、都丸、和泉
      • ベアリングを押しているバネが動きを吸収している可能性がある。
    • PD設置: *横澤、和泉、井上
      • BSチェンバー内、AS側に設置完了。
    • BSカメラ設置: *苔山、川崎
      • BS付近に設置したが、レンズ交換が必要。
  • 作業予定 (*:責任者)
    • アラインメント: *和泉、都丸
      • BFを固定した方がアラインメントはやりやすいのでは?(都丸)
    • Type A(ETMY): *高橋、牛場、都丸、和泉
      • バネを変える。
      • Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
      • Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。

        • 今日、明日くらいが蓋閉めの準備のためにその作業をするので、その間に解決することを目標にする。
      • 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
      • 火曜日の夕方に方向性を判断。
    • PD設置: *横澤、井上
      • EYAにいってViewポートを取り付ける。
  • Laser hazard
    • センターはSR奥がハザードエリア。エンドはハザードエリアなし。
  • Weekly
    • 12/18の週
      • EYC閉止
      • Type A引き続き調整。
  • 問題点など
    • 回路電源のモニターがあるといい。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1