4520
Comment:
|
7041
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
=== Phase1 === === Phase2 === |
* [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
Line 13: | Line 19: |
* ビーム位置測定 * 11/8 *木村、荒木、沢田@IXV, IXC、荒木 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 . |
|
Line 18: | Line 20: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
|
Line 19: | Line 26: |
* BS PDセット * 12/15 横澤 {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} |
|
Line 30: | Line 59: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 33: | Line 62: |
2017/11/8(Wed.) | 2017/12/18(Mon.) |
Line 36: | Line 65: |
* 作業人員(*:責任者) * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木)) * VIS: Mark, Enzo, 神津 |
* 作業報告および作業予定 (*:責任者) * アラインメント: *和泉、長野、榎本、川崎 * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。 * BFのピコモーターが離散的に動く。5mrad程度のステップ。 * BFを固定した方がアラインメントはやりやすいのでは?(都丸) * アラインメントは今日はなし。 * Type A(ETMY): *牛場、宮本 * バネが動きを吸収している可能性があるので、バネを変える。 * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった? * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。 * 今日蓋閉めの準備のためにその作業をするので、 * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。 * 火曜日の夕方に方向性を判断。 * PD設置: *横澤、和泉 * BSチェンバー内、AS側に設置完了。 * EYAにいってViewポートを取り付ける。 * BSカメラ設置: *苔山、川崎 * BS付近に設置したが、レンズ交換が必要。 |
Line 41: | Line 89: |
* PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 * 作業 * ビーム位置測定 * IYCでの位置測定をした。完了。現在まとめ中。 * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。 * 防振関連 * BSのlength sensing Oplev, オフセットリリースなど。 * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。 |
* センターはSR奥がハザードエリア。エンドはハザードエリアなし。 |
Line 55: | Line 92: |
* 11/6の週 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。 |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 |
Line 59: | Line 100: |
* コーチフィルターが不調。 | * 回路電源のモニターがあるといい。 |
Line 68: | Line 110: |
* Location: Meeting room at Hokum , or educe, Polycom | * Location: Meeting room at Hokubukaikan, or eZuce, Polycom |
Line 71: | Line 113: |
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || | ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || |
Line 82: | Line 127: |
* Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) |
|
Line 92: | Line 139: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/12/14 updated
Working people assignment
* 責任者
- ETMYアラインメント
- 12/15 和泉、長野、川﨑、榎本
- GigEカメラセット
- 12/15 苔山、川﨑
- BS PDセット
- 12/15 横澤
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/18(Mon.)
- Daily
- 作業報告および作業予定 (*:責任者)
- アラインメント: *和泉、長野、榎本、川崎
- BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
- BFのピコモーターが離散的に動く。5mrad程度のステップ。
- BFを固定した方がアラインメントはやりやすいのでは?(都丸)
- アラインメントは今日はなし。
- Type A(ETMY): *牛場、宮本
- バネが動きを吸収している可能性があるので、バネを変える。
- Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。
- 今日蓋閉めの準備のためにその作業をするので、
- 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
- 火曜日の夕方に方向性を判断。
- PD設置: *横澤、和泉
- BSチェンバー内、AS側に設置完了。
- EYAにいってViewポートを取り付ける。
- BSカメラ設置: *苔山、川崎
- BS付近に設置したが、レンズ交換が必要。
- アラインメント: *和泉、長野、榎本、川崎
- Laser hazard
- センターはSR奥がハザードエリア。エンドはハザードエリアなし。
- 作業報告および作業予定 (*:責任者)
- Weekly
- 12/18の週
- EYC閉止
- Type A引き続き調整。
- 12/18の週
- 問題点など
- 回路電源のモニターがあるといい。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Documents
Communication tools