Line 6: | Line 6: |
=== Phase1 === === Phase2 === |
* [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/12/11 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}} |
Line 13: | Line 19: |
* 下げ振り測定 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 . |
|
Line 17: | Line 20: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/13 *新井、正田(午後~) * 11/14 *新井、正田 * 11/15 *木村、沢田、新井、正田(蓋閉め) * 11/16 *木村、沢田、新井、正田(蓋閉め) * 11/17 *新井、正田 |
* ETMYアラインメント * 12/11 * 12/12 和泉 * 12/13 和泉 * 12/14 和泉、長野、川﨑、川崎 * 12/15 和泉、長野、川﨑、榎本、川崎 * GigEカメラセット * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 |
Line 24: | Line 34: |
* Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
* BS PDセット * 12/11 * 12/12 横澤 * 12/13 横澤 * 12/14 * 12/15 {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == |
Line 30: | Line 46: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} |
|
Line 42: | Line 70: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 45: | Line 73: |
2017/11/8(Wed.) | 2017/12/11(Mon.) |
Line 48: | Line 76: |
* 作業人員(*:責任者) * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木)) * VIS: Mark, Enzo, 神津 |
* 報告と作業 (*:責任者) * アラインメント: * 現在Xエンドまで通っている。明日、明後日でEYAに通す。 * Type B: *Mark、Enzo, 神津、正田 * 今日も引き続き制御系のチェックをする。 * Type A: 午後から*高橋(2637)、奥富、宮本 * actuatorのテストなどの続き。 * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。 * PD設置: 横澤 * PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。 |
Line 53: | Line 93: |
* PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 * 作業 * ビーム位置測定 * IYCでの位置測定をした。完了。現在まとめ中。 * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。 * 防振関連 * BSのlength sensing Oplev, オフセットリリースなど。 * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。 |
* SRラインより奥。 |
Line 67: | Line 96: |
* 11/6の週 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。 |
* 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 |
Line 71: | Line 105: |
* コーチフィルターが不調。 | * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 |
Line 80: | Line 118: |
* Location: Meeting room at Hokum , or educe, Polycom | * Location: Meeting room at Hokubukaikan, or eZuce, Polycom |
Line 83: | Line 121: |
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || | ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || |
Line 94: | Line 135: |
* Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) | |
Line 104: | Line 146: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/12/11 updated
Working people assignment
* 責任者
- ETMYアラインメント
- 12/11
- 12/12 和泉
- 12/13 和泉
- 12/14 和泉、長野、川﨑、川崎
- 12/15 和泉、長野、川﨑、榎本、川崎
- GigEカメラセット
- 12/11
- 12/12
- 12/13
- 12/14
- 12/15
- BS PDセット
- 12/11
- 12/12 横澤
- 12/13 横澤
- 12/14
- 12/15
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/11(Mon.)
- Daily
- 報告と作業 (*:責任者)
- アラインメント:
- 現在Xエンドまで通っている。明日、明後日でEYAに通す。
- Type B: *Mark、Enzo, 神津、正田
- 今日も引き続き制御系のチェックをする。
- Type A: 午後から*高橋(2637)、奥富、宮本
- actuatorのテストなどの続き。
- Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。
- PD設置: 横澤
- PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。
- アラインメント:
- Laser hazard
- SRラインより奥。
- 報告と作業 (*:責任者)
- Weekly
- 12/11の週
- メインビームの再アラインメント。
- ETMYからの戻り光確認。
- 12/13 昼休みに真空引きの前のミーティング。
- 12/18 EYC閉止。
- 12/11の週
- 問題点など
- PR-BS相対位置測定後、EXでの再位置測定が必要か?
- PR系のスリップが頻発している。特にPR3。
- BSテーブルにPDを置けるかどうか。
- Eendの遮蔽板をいつ開けるか。
- 真空引きの最終確認。
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Documents
Communication tools