Differences between revisions 116 and 212 (spanning 96 versions)
Revision 116 as of 2017-11-08 11:41:41
Size: 4814
Editor: AyakaShoda
Comment:
Revision 212 as of 2017-12-18 09:27:48
Size: 7041
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 13: Line 19:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .
Line 17: Line 20:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 24: Line 26:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * BS PDセット
  * 12/15 横澤
Line 30: Line 29:
   {{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==
Line 31: Line 35:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
Line 42: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 45: Line 62:
2017/11/8(Wed.) 2017/12/18(Mon.)
Line 48: Line 65:
  * 作業人員(*:責任者)
   * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木))
   * VIS: Mark, Enzo, 神津
  * 作業報告および作業予定 (*:責任者)
   * アラインメント: *和泉、長野、榎本、川崎
    * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
    * BFのピコモーターが離散的に動く。5mrad程度のステップ。
     * BFを固定した方がアラインメントはやりやすいのでは?(都丸)
    * アラインメントは今日はなし。

   * Type A(ETMY): *牛場、宮本
    * バネが動きを吸収している可能性があるので、バネを変える。
    * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
    * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。
     * 今日蓋閉めの準備のためにその作業をするので、
    * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
    * 火曜日の夕方に方向性を判断。

   * PD設置: *横澤、和泉
    * BSチェンバー内、AS側に設置完了。
    * EYAにいってViewポートを取り付ける。

   * BSカメラ設置: *苔山、川崎
    * BS付近に設置したが、レンズ交換が必要。
Line 53: Line 89:
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。

  * 作業
   * ビーム位置測定
    * IYCでの位置測定をした。完了。現在まとめ中。
    * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。

   * 防振関連
    * BSのlength sensing Oplev, オフセットリリースなど。

   * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。
   * センターはSR奥がハザードエリア。エンドはハザードエリアなし。
Line 67: Line 92:
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。

  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。

Line 71: Line 100:
  * コーチフィルターが不調。   * 回路電源のモニターがあるといい。
Line 80: Line 110:
 * Location: Meeting room at Hokum , or educe, Polycom  * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
Line 83: Line 113:
||7||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
Line 94: Line 127:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
Line 104: Line 139:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/18(Mon.)

  • Daily
    • 作業報告および作業予定 (*:責任者)
      • アラインメント: *和泉、長野、榎本、川崎
        • BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
        • BFのピコモーターが離散的に動く。5mrad程度のステップ。
          • BFを固定した方がアラインメントはやりやすいのでは?(都丸)
        • アラインメントは今日はなし。
      • Type A(ETMY): *牛場、宮本
        • バネが動きを吸収している可能性があるので、バネを変える。
        • Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
        • Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。

          • 今日蓋閉めの準備のためにその作業をするので、
        • 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
        • 火曜日の夕方に方向性を判断。
      • PD設置: *横澤、和泉
        • BSチェンバー内、AS側に設置完了。
        • EYAにいってViewポートを取り付ける。
      • BSカメラ設置: *苔山、川崎
        • BS付近に設置したが、レンズ交換が必要。
    • Laser hazard
      • センターはSR奥がハザードエリア。エンドはハザードエリアなし。
  • Weekly
    • 12/18の週
      • EYC閉止
      • Type A引き続き調整。
  • 問題点など
    • 回路電源のモニターがあるといい。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members