Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
Line 11: Line 11:
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}}
2017/11/8 updated
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 18: Line 19:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .
Line 22: Line 20:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田
 * ETMYアラインメント
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/14
  * 12/15
Line 29: Line 28:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * BS PDセット
  * 12/14 横澤
  * 12/15
Line 35: Line 32:
 * 遮蔽板取り外し
  * 木村
  
Line 40: Line 40:
 * Laser, RefCav, IMC: 苔山、中野  * Laser, Ref''''''Cav, IMC: 苔山、中野
Line 45: Line 45:
  * Type A: 高橋、奥富
 * PicoMotor: 三代
 * Digital: 宮川、山本
 * 回路: 宮川、上泉、戸村、霜出
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
Line 64: Line 64:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 67: Line 67:
2017/11/8(Wed.) 2017/12/14(Thu.)
Line 70: Line 70:
  * 作業人員(*:責任者)
   * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木))
   * VIS: Mark, Enzo, 神津
  * 報告と作業 (*:責任者)

   * 遮蔽板取り外し: *木村、その他
    * 朝から取り外し作業開始。終了次第宮川まで連絡。

   * アラインメント: *和泉、長野、川崎、三代木
    * ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。
    * 遮蔽板の取り外しが終わり次第アラインメント開始。
     * ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。

   * Type B: *Mark、Enzo, 正田, 和泉
    * 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。
     * それでもダンピングはまだ効いていないようである。
    * IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。

   * Type A: *牛場、宮本
    * Fishing rodの稼働実験をした。結果は残念ながら動かなかった。
     * さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。
     * unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか?
     * この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。


   * PD設置:
    * 和泉君の指示で移動のタイミングを横澤君に知らせる。
     * 時期としては今日の午後か、明日の午前くらい。

Line 75: Line 99:
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。

  * 作業
   * ビーム位置測定
    * IYCでの位置測定をした。完了。現在まとめ中。
    * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。

   * 防振関連
    * BSのlength sensing Oplev, オフセットリリースなど。

   * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。
   * SRラインより奥。
   * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
Line 89: Line 103:
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。

  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。

  * 12/18の週
   * EYC閉止

Line 93: Line 116:
  * コーチフィルターが不調。   * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川)
Line 105: Line 130:
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 117: Line 144:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/14 和泉、長野、川﨑
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/14
    • 12/15
  • BS PDセット
    • 12/14 横澤
    • 12/15
  • 遮蔽板取り外し
    • 木村



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/14(Thu.)

  • Daily
    • 報告と作業 (*:責任者)
      • 遮蔽板取り外し: *木村、その他
        • 朝から取り外し作業開始。終了次第宮川まで連絡。
      • アラインメント: *和泉、長野、川崎、三代木
        • ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。
        • 遮蔽板の取り外しが終わり次第アラインメント開始。
          • ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。
      • Type B: *Mark、Enzo, 正田, 和泉
        • 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。
          • それでもダンピングはまだ効いていないようである。
        • IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。
      • Type A: *牛場、宮本
        • Fishing rodの稼働実験をした。結果は残念ながら動かなかった。
          • さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。
          • unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか?
          • この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。
      • PD設置:
        • 和泉君の指示で移動のタイミングを横澤君に知らせる。
          • 時期としては今日の午後か、明日の午前くらい。
    • Laser hazard
      • SRラインより奥。
      • 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
  • Weekly
    • 12/11の週
      • メインビームの再アラインメント。
      • ETMYからの戻り光確認。
      • 12/13 昼休みに真空引きの前のミーティング。
      • 12/18 EYC閉止。
    • 12/18の週
      • EYC閉止
  • 問題点など
    • PR-BS相対位置測定後、EXでの再位置測定が必要か?
    • PR系のスリップが頻発している。特にPR3。
    • WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川)

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1