Line 6: | Line 6: |
=== Phase1 === === Phase2 === |
* [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] |
Line 11: | Line 11: |
2017/11/8 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}} |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
Line 19: | Line 19: |
* 下げ振り測定 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 . |
|
Line 23: | Line 20: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/13 *新井、正田(午後~) * 11/14 *新井、正田 * 11/15 *木村、沢田、新井、正田(蓋閉め) * 11/16 *木村、沢田、新井、正田(蓋閉め) * 11/17 *新井、正田 |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
Line 30: | Line 26: |
* Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
* BS PDセット * 12/15 横澤 |
Line 36: | Line 29: |
Line 49: | Line 43: |
* 回路: 霜出、上泉 | * 回路: 上泉、霜出 |
Line 65: | Line 59: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 68: | Line 62: |
2017/11/10(Fri) | 2017/12/18(Mon.) |
Line 70: | Line 64: |
* 作業 * 下げ振り測定 * IYCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。-X側に8mm程度ずれていた。高さはほぼぴったり。測定後IYCとBSの間のGVを閉めたので、今日真空引きを始める予定。 * IXCの真空槽の高さが4mm高かった。 |
* 作業報告 (*:責任者) * アラインメント: *和泉、長野、榎本、川崎 * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。 * BFのピコモーターが離散的に動く。5mrad程度のステップ。 |
Line 75: | Line 69: |
* 防振関連 * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。 * BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。 |
* Type A(ETMY): *牛場、宮本、都丸、和泉 * ベアリングを押しているバネが動きを吸収している可能性がある。 |
Line 79: | Line 72: |
* 計算機関連 * k1immtで使っていた光ファイバーケーブルは新しいラックのところまで来た。来週引き続き。 |
* PD設置: *横澤、和泉、井上 * BSチェンバー内、AS側に設置完了。 |
Line 82: | Line 75: |
* Daily * 作業人員(*:責任者) * VIS: Mark, Enzo, 神津 |
* BSカメラ設置: *苔山、川崎 * BS付近に設置したが、レンズ交換が必要。 |
Line 86: | Line 78: |
* Laser hazard * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 |
* 作業予定 (*:責任者) * アラインメント: *和泉、都丸 * BFを固定した方がアラインメントはやりやすいのでは?(都丸) * Type A(ETMY): *高橋、牛場、都丸、和泉 * バネを変える。 * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった? * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。 * 今日、明日くらいが蓋閉めの準備のためにその作業をするので、その間に解決することを目標にする。 * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。 * 火曜日の夕方に方向性を判断。 * PD設置: *横澤、井上 * EYAにいってViewポートを取り付ける。 |
Line 91: | Line 94: |
* Laser hazard * センターはSR奥がハザードエリア。エンドはハザードエリアなし。 |
|
Line 92: | Line 98: |
* 11/6の週 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。 * 11/13の週 * PR系の位置測定。ただし月曜は拡大チーフ会議などがあり、作業はない見込み。 |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 |
Line 98: | Line 105: |
* コーチフィルターが不調。 | * 回路電源のモニターがあるといい。 |
Line 110: | Line 118: |
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
|
Line 122: | Line 132: |
* Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/12/14 updated
Working people assignment
* 責任者
- ETMYアラインメント
- 12/15 和泉、長野、川﨑、榎本
- GigEカメラセット
- 12/15 苔山、川﨑
- BS PDセット
- 12/15 横澤
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/18(Mon.)
- 作業報告 (*:責任者)
- アラインメント: *和泉、長野、榎本、川崎
- BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
- BFのピコモーターが離散的に動く。5mrad程度のステップ。
- Type A(ETMY): *牛場、宮本、都丸、和泉
- ベアリングを押しているバネが動きを吸収している可能性がある。
- PD設置: *横澤、和泉、井上
- BSチェンバー内、AS側に設置完了。
- BSカメラ設置: *苔山、川崎
- BS付近に設置したが、レンズ交換が必要。
- アラインメント: *和泉、長野、榎本、川崎
- 作業予定 (*:責任者)
- アラインメント: *和泉、都丸
- BFを固定した方がアラインメントはやりやすいのでは?(都丸)
- Type A(ETMY): *高橋、牛場、都丸、和泉
- バネを変える。
- Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。
- 今日、明日くらいが蓋閉めの準備のためにその作業をするので、その間に解決することを目標にする。
- 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
- 火曜日の夕方に方向性を判断。
- PD設置: *横澤、井上
- EYAにいってViewポートを取り付ける。
- アラインメント: *和泉、都丸
- Laser hazard
- センターはSR奥がハザードエリア。エンドはハザードエリアなし。
- Weekly
- 12/18の週
- EYC閉止
- Type A引き続き調整。
- 12/18の週
- 問題点など
- 回路電源のモニターがあるといい。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|