Line 6: | Line 6: |
=== Phase1 === === Phase2 === |
* [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] |
Line 11: | Line 11: |
2017/11/8 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}} |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
Line 19: | Line 19: |
* 下げ振り測定 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 . |
|
Line 23: | Line 20: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/13 *新井、正田(午後~) * 11/14 *新井、正田 * 11/15 *木村、沢田、新井、正田(蓋閉め) * 11/16 *木村、沢田、新井、正田(蓋閉め) * 11/17 *新井、正田 |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
Line 30: | Line 26: |
* Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
* BS PDセット * 12/15 横澤 |
Line 36: | Line 29: |
Line 49: | Line 43: |
* 回路: 霜出、上泉 | * 回路: 上泉、霜出 |
Line 65: | Line 59: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 68: | Line 62: |
2017/11/10(Fri) | 2017/12/15(Fri.) |
Line 71: | Line 65: |
* 作業 * 下げ振り測定 * IYCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。-X側に8mm程度ずれていた。高さはほぼぴったり。測定後IYCとBSの間のGVを閉めたので、今日真空引きを始める予定。 * IXCの真空槽の高さが4mm高かった。 |
* 報告と作業 (*:責任者) |
Line 76: | Line 67: |
* 防振関連 * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。 * BSのTop filterのオフセットリリース及びMatrixの設定など。 |
* アラインメント: *和泉、長野、川崎、榎本 * BSのアルミ箔を外し、EYのPDに光をあてる。 * IMMT2のピコモーターがスタックしているようなのでそれを直す。 * EYのPDを回収して、スリットを使いEYのアラインメントをする。 * Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。 * BSで光が見えたらゴール。 |
Line 80: | Line 74: |
* 計算機関連 * k1immtで使っていた光ファイバーケーブルは新しいラックのところまで来た。来週引き続き。 |
* Type B(BS): *正田、和泉、長野 * TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。 |
Line 83: | Line 77: |
* 作業人員(*:責任者) * VIS: Mark, Enzo |
* Type A(ETMY): *牛場、宮本 * 揺れはOplevでみて数uradになっている。 * アラインメントはなんとか出るところまでは持っていけた。 * PD設置: *横澤 * 和泉君の指示で移動のタイミングを横澤君に知らせる。 * BSカメラ設置: *苔山、長野 * 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。 |
Line 87: | Line 88: |
* PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 |
* センターは変わらずSR奥。 * 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。 * Weekly * 12/11の週 * ETMYからの戻り光確認。 * 12/18の週 * EYC閉止 |
Line 91: | Line 100: |
* Weekly * 11/6の週 * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。 * 11/13の週 * PR系の位置測定。ただし月曜は拡大チーフ会議などがあり、作業はない見込み。 |
|
Line 98: | Line 102: |
* コーチフィルターが不調。 | |
Line 110: | Line 113: |
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
|
Line 122: | Line 127: |
* Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/12/14 updated
Working people assignment
* 責任者
- ETMYアラインメント
- 12/15 和泉、長野、川﨑、榎本
- GigEカメラセット
- 12/15 苔山、川﨑
- BS PDセット
- 12/15 横澤
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/15(Fri.)
- Daily
- 報告と作業 (*:責任者)
- アラインメント: *和泉、長野、川崎、榎本
- BSのアルミ箔を外し、EYのPDに光をあてる。
- IMMT2のピコモーターがスタックしているようなのでそれを直す。
- EYのPDを回収して、スリットを使いEYのアラインメントをする。
- Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
- BSで光が見えたらゴール。
- Type B(BS): *正田、和泉、長野
- TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。
- Type A(ETMY): *牛場、宮本
- 揺れはOplevでみて数uradになっている。
- アラインメントはなんとか出るところまでは持っていけた。
- PD設置: *横澤
- 和泉君の指示で移動のタイミングを横澤君に知らせる。
- BSカメラ設置: *苔山、長野
- 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。
- アラインメント: *和泉、長野、川崎、榎本
- Laser hazard
- センターは変わらずSR奥。
- 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。
- 報告と作業 (*:責任者)
- Weekly
- 12/11の週
- ETMYからの戻り光確認。
- 12/18の週
- EYC閉止
- 12/11の週
- 問題点など
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|