Differences between revisions 137 and 211 (spanning 74 versions)
Revision 137 as of 2017-11-10 09:17:57
Size: 6304
Comment:
Revision 211 as of 2017-12-18 09:02:08
Size: 6965
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
Line 11: Line 11:
2017/11/8 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}}
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 19: Line 19:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .
Line 23: Line 20:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 30: Line 26:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * BS PDセット
  * 12/15 横澤
Line 36: Line 29:
  
Line 49: Line 43:
 * 回路: 霜出、上泉  * 回路: 上泉、霜出
Line 65: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 68: Line 62:
2017/11/10(Fri) 2017/12/18(Mon.)
Line 71: Line 65:
  * 作業
   * 下げ振り測定
    * IYCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。-X側に8mm程度ずれていた。高さはほぼぴったり。測定後IYCとBSの間のGVを閉めたので、今日真空引きを始める予定。
    * IXCの真空槽の高さが4mm高かった。
  * 作業報告 (*:責任者)
Line 76: Line 67:
   * 防振関連
    * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。
    * BSのTop filterのオフセットリリース及びMatrixの設定など。
   * アラインメント: *和泉、長野、榎本、川崎
    * BSのアルミ箔を外し、EYのPDに光をあてる。
    * IMMT2のピコモーターがスタックしているようなのでそれを直す。
    * EYのPDを回収して、スリットを使いEYのアラインメントをする。
     * Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
    * BSで光が見えたらゴール。
Line 80: Line 74:
  * 計算機関連
   * k1immtで使っていた光ファイバーケーブルは新しいラックのところまで来た。来週引き続き。
   * Type A(ETMY): *牛場、宮本
    * 揺れはOplevでみて数uradになっている。
    * アラインメントはなんとか出るところまでは持っていけた。
Line 83: Line 78:
  * 作業人員(*:責任者)
   * VIS: Mark, Enzo
   * PD設置: *横澤

   * BSカメラ設置: *苔山、川崎
    * BS付近に設置完了。


   * Type B(BS): *正田、和泉、長野
    * TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。


  * 作業予定 (*:責任者)
Line 87: Line 92:
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
   * センターは変わらずSR奥。
   * 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。

 * Weekly

  * 12/11の週
   * ETMYからの戻り光確認。

  * 12/18の週
   * EYC閉止
Line 91: Line 104:
 * Weekly
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
  * 11/13の週
   * PR系の位置測定。ただし月曜は拡大チーフ会議などがあり、作業はない見込み。
Line 98: Line 106:
  * コーチフィルターが不調。
Line 110: Line 117:
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 122: Line 131:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/18(Mon.)

  • Daily
    • 作業報告 (*:責任者)
      • アラインメント: *和泉、長野、榎本、川崎
        • BSのアルミ箔を外し、EYのPDに光をあてる。
        • IMMT2のピコモーターがスタックしているようなのでそれを直す。
        • EYのPDを回収して、スリットを使いEYのアラインメントをする。
          • Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
        • BSで光が見えたらゴール。
      • Type A(ETMY): *牛場、宮本
        • 揺れはOplevでみて数uradになっている。
        • アラインメントはなんとか出るところまでは持っていけた。
      • PD設置: *横澤
      • BSカメラ設置: *苔山、川崎
        • BS付近に設置完了。
      • Type B(BS): *正田、和泉、長野
        • TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。
    • 作業予定 (*:責任者)
    • Laser hazard
      • センターは変わらずSR奥。
      • 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。
  • Weekly
    • 12/11の週
      • ETMYからの戻り光確認。
    • 12/18の週
      • EYC閉止
  • 問題点など

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)