Differences between revisions 159 and 213 (spanning 54 versions)
Revision 159 as of 2017-11-22 09:16:16
Size: 6651
Comment:
Revision 213 as of 2017-12-18 09:38:16
Size: 7241
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * BS PDセット
  * 12/15 横澤

  
Line 58: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 61: Line 62:
2017/11/22(Wed.) 2017/12/18(Mon.)
Line 63: Line 64:
 * Daily
  * 作業
   * Type A: 復帰した。
   * IOO: PSLとMCともに光軸ズレがありそう。今日もう一度確認する。
   * 計算機: ほぼ復帰。k1bsとk1ey1, k1ex0, k1ey0に少しトラブルあり。
   * Type Bp: PR系は信号は来ている。PR2のAAフィルターが調子が悪いので交換。PRMのリリースをしたがぶつかっている様子。
    * タンクからサテライトボックスまでのD-SUBケーブルが一つダメになっている。
    * PR2のBIOを一枚増やした。カードの認識がバラバラ。インプットとアウトプットさえバラバラ。
   * 真空: MC復帰した。Xarm復帰した。Yarmを今日か明日復帰する。
   * Yendピット内の水がまだ冠水中。今日シートをかぶせて作業を再開。
   * MCFの前のGreenとPOP用光学定盤を移動させたい。
   * 12時からeZuceでiKAGRAからの引き継ぎ会議。
 * 作業報告 (*:責任者)
  * アラインメント: *和泉、長野、榎本、川崎
   * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
   * BFのピコモーターが離散的に動く。5mrad程度のステップ。

  * Type A(ETMY): *牛場、宮本、都丸、和泉
   * ベアリングを押しているバネが動きを吸収している可能性がある。

  * PD設置: *横澤、和泉、井上
   * BSチェンバー内、AS側に設置完了。

  * BSカメラ設置: *苔山、川崎
   * BS付近に設置したが、レンズ交換が必要。

 * 作業予定 (*:責任者)
  * アラインメント: *和泉、都丸
   * BFを固定した方がアラインメントはやりやすいのでは?(都丸)

  * Type A(ETMY): *高橋、牛場、都丸、和泉
   * バネを変える。
   * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
   * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。
    * 今日、明日くらいが蓋閉めの準備のためにその作業をするので、その間に解決することを目標にする。
   * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
   * 火曜日の夕方に方向性を判断。

  * PD設置: *横澤、井上
   * EYAにいってViewポートを取り付ける。
Line 77: Line 94:
停電のため報告、作業予定特になし。

  * 作業人員(*:責任者)
   * Type Bp: 正田、和泉、田中
   * MIF/AOS: 道村、阿久津、中田

  * Laser hazard
   * IFIより奥。
 * Laser hazard
   * センターはSR奥がハザードエリア。エンドはハザードエリアなし。
Line 87: Line 98:
  * 11/20の週
   * 昨日停電復帰。
   * PR系の位置測定。
   * Watch dogのテストとPRMのリリース。

  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
Line 94: Line 105:
  * PR2、3のアラインメントにメインビームが必要。CRYは今週はメインビームは出して欲しくない。
  * PRMがリリースしたがぶつかっている様子。
  * D-SUBケーブルがおかしくなったものが出た。
  * 回路電源のモニターがあるといい。
Line 109: Line 118:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 122: Line 132:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/18(Mon.)

  • 作業報告 (*:責任者)
    • アラインメント: *和泉、長野、榎本、川崎
      • BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
      • BFのピコモーターが離散的に動く。5mrad程度のステップ。
    • Type A(ETMY): *牛場、宮本、都丸、和泉
      • ベアリングを押しているバネが動きを吸収している可能性がある。
    • PD設置: *横澤、和泉、井上
      • BSチェンバー内、AS側に設置完了。
    • BSカメラ設置: *苔山、川崎
      • BS付近に設置したが、レンズ交換が必要。
  • 作業予定 (*:責任者)
    • アラインメント: *和泉、都丸
      • BFを固定した方がアラインメントはやりやすいのでは?(都丸)
    • Type A(ETMY): *高橋、牛場、都丸、和泉
      • バネを変える。
      • Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
      • Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。

        • 今日、明日くらいが蓋閉めの準備のためにその作業をするので、その間に解決することを目標にする。
      • 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
      • 火曜日の夕方に方向性を判断。
    • PD設置: *横澤、井上
      • EYAにいってViewポートを取り付ける。
  • Laser hazard
    • センターはSR奥がハザードエリア。エンドはハザードエリアなし。
  • Weekly
    • 12/18の週
      • EYC閉止
      • Type A引き続き調整。
  • 問題点など
    • 回路電源のモニターがあるといい。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)