Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * BS PDセット
  * 12/15 横澤

  
Line 58: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 61: Line 62:
2017/11/22(Wed.) 2017/12/15(Fri.)
Line 64: Line 65:
  * 作業
   * Type A: 復帰した。
   * IOO: PSLとMCともに光軸ズレがありそう。今日もう一度確認する。
   * 計算機: ほぼ復帰。k1bsとk1ey1, k1ex0, k1ey0に少しトラブルあり。
   * Type Bp: PR系は信号は来ている。PR2のAAフィルターが調子が悪いので交換。PRMのリリースをしたがぶつかっている様子。
    * タンクからサテライトボックスまでのD-SUBケーブルが一つダメになっている。
    * PR2のBIOを一枚増やした。カードの認識がバラバラ。インプットとアウトプットさえバラバラ。
   * 真空: MC復帰した。Xarm復帰した。Yarmを今日か明日復帰する。
   * Yendピット内の水がまだ冠水中。今日シートをかぶせて作業を再開。
   * MCFの前のGreenとPOP用光学定盤を移動させたい。
   * 12時からeZuceでiKAGRAからの引き継ぎ会議。
  * 報告と作業 (*:責任者)
Line 76: Line 67:
   * アラインメント: *和泉、長野、川崎、三代木
    * BSのアルミ箔を外し、EYのPDに光をあてる。
    * IMMT2のピコモーターがスタックしているようなのでそれを直す。
    * EYのPDを回収して、スリットを使いEYのアラインメントをする。
     * Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
    * BSで光が見えたらゴール。
Line 77: Line 74:
停電のため報告、作業予定特になし。    * Type B(BS): *正田、和泉、長野
    * TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。
Line 79: Line 77:
  * 作業人員(*:責任者)
   * Type Bp: *正田、和泉、田中
   * MIF/AOS: *道村、阿久津、中田
   * Type A(ETMY): *牛場、宮本
    * 揺れはOplevでみて数uradになっている。
    * アラインメントはなんとか出るところまでは持っていけた。

   * PD設置: *横澤
    * 和泉君の指示で移動のタイミングを横澤君に知らせる。

   * BSカメラ設置: *苔山、長野
    * 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。
Line 84: Line 88:
   * IFIより奥。    * センターは変わらずSR奥。
   * 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。
Line 87: Line 92:
  * 11/20の週
   * 昨日停電復帰。
   * PR系の位置測定。
   * Watch dogのテストとPRMのリリース。

  * 12/11の週
   * ETMYからの戻り光確認。

  * 12/18の週
   * EYC閉止
Line 94: Line 102:
  * PR2、3のアラインメントにメインビームが必要。CRYは今週はメインビームは出して欲しくない。
  * PRMがリリースしたがぶつかっている様子。
  * D-SUBケーブルがおかしくなったものが出た。
Line 109: Line 113:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 122: Line 127:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/15(Fri.)

  • Daily
    • 報告と作業 (*:責任者)
      • アラインメント: *和泉、長野、川崎、三代木
        • BSのアルミ箔を外し、EYのPDに光をあてる。
        • IMMT2のピコモーターがスタックしているようなのでそれを直す。
        • EYのPDを回収して、スリットを使いEYのアラインメントをする。
          • Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
        • BSで光が見えたらゴール。
      • Type B(BS): *正田、和泉、長野
        • TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。
      • Type A(ETMY): *牛場、宮本
        • 揺れはOplevでみて数uradになっている。
        • アラインメントはなんとか出るところまでは持っていけた。
      • PD設置: *横澤
        • 和泉君の指示で移動のタイミングを横澤君に知らせる。
      • BSカメラ設置: *苔山、長野
        • 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。
    • Laser hazard
      • センターは変わらずSR奥。
      • 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。
  • Weekly
    • 12/11の週
      • ETMYからの戻り光確認。
    • 12/18の週
      • EYC閉止
  • 問題点など

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members