Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/12/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/13 和泉
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/13
  * 12/14
  * 12/15
Line 29: Line 30:
 * BS PDセット
  * 12/13 横澤
  * 12/14
  * 12/15
  
Line 58: Line 64:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 61: Line 67:
2017/11/27(Mon.) 2017/12/13(Wed.)
Line 64: Line 70:
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているので締め直す必要がある。今日、明日でミラプロに頼んで締め直しをする。
    * PRMのリリースはビームのアラインメントと並行に進める。今週後半か。
   * WS
    * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
    * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
   * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。
  * 本日12時半よりファン小屋で真空関連の打ち合わせ。
   * 出席予定者:
    * 木村、宮川、牛場、高橋、都丸、和泉
    * (eZuce) 阿久津、井上

  * 報告と作業 (*:責任者)

   * アラインメント: *和泉
    * YendのPDに光を届けた。BSを特にいじることなく、すぐに光が通った。PR2のダンピングを調整する必要があった。
    * BSは依然10uradくらいのオーダーで揺れている。

   * Type B: *Mark、Enzo, 正田, 和泉
    * IP yaw, IM, TMのpitchのダンピングを入れた。
    * Yawの動きがまだ大きい。これは全体の回転のようである。上のマグネティックダンパーで減衰されるはずがうまく効いていない。
    * サスペンション全体が4mm程度下に下がっているかもしれない。
    * 蓋を開けなければならないので、今日やることを考える。

   * Type A: *牛場、宮本
    * Yawが回転したが、力がある閾値を超えるとガクッと回るような感じである。ベアリングが渋い可能性が高い。
    * 回るのも数分のオーダーで、微調整がかなり厳しそう。回転の方向は正しいことは確認した。
    * BFのダンピングを強くするともう少し素直に反応する可能性がある。
    * 今日は上部のダンピング制御を入れて操作して様子を見てみる。DC制御か?

   * PD設置:
Line 74: Line 96:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
Line 78: Line 99:
   * 今日明日はIMMTより奥、水曜からSRラインより奥。    * SRラインより奥。
   * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
Line 81: Line 103:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直し。

  * 12/11の週
Line 85: Line 106:

  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
Line 90: Line 107:
   * 12/18EYC閉止。    * 12/13 昼休みに真空引きの前のミーティング。
* 12/18 EYC閉止。
Line 94: Line 112:
  * PRMの足が浮いている。
  * D-SUBケーブルがおかしくなったものが出た。
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
Line 108: Line 128:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 121: Line 142:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/12 updated KAGRA/Commissioning/Commissioning_schedule_20171212.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/13 和泉
    • 12/14 和泉、長野、川﨑
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/13
    • 12/14
    • 12/15
  • BS PDセット
    • 12/13 横澤
    • 12/14
    • 12/15



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/13(Wed.)

  • Daily
    • 本日12時半よりファン小屋で真空関連の打ち合わせ。
      • 出席予定者:
        • 木村、宮川、牛場、高橋、都丸、和泉
        • (eZuce) 阿久津、井上
    • 報告と作業 (*:責任者)
      • アラインメント: *和泉
        • YendのPDに光を届けた。BSを特にいじることなく、すぐに光が通った。PR2のダンピングを調整する必要があった。
        • BSは依然10uradくらいのオーダーで揺れている。
      • Type B: *Mark、Enzo, 正田, 和泉
        • IP yaw, IM, TMのpitchのダンピングを入れた。
        • Yawの動きがまだ大きい。これは全体の回転のようである。上のマグネティックダンパーで減衰されるはずがうまく効いていない。
        • サスペンション全体が4mm程度下に下がっているかもしれない。
        • 蓋を開けなければならないので、今日やることを考える。
      • Type A: *牛場、宮本
        • Yawが回転したが、力がある閾値を超えるとガクッと回るような感じである。ベアリングが渋い可能性が高い。
        • 回るのも数分のオーダーで、微調整がかなり厳しそう。回転の方向は正しいことは確認した。
        • BFのダンピングを強くするともう少し素直に反応する可能性がある。
        • 今日は上部のダンピング制御を入れて操作して様子を見てみる。DC制御か?
      • PD設置:
    • Laser hazard
      • SRラインより奥。
      • 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
  • Weekly
    • 12/11の週
      • メインビームの再アラインメント。
      • ETMYからの戻り光確認。
      • 12/13 昼休みに真空引きの前のミーティング。
      • 12/18 EYC閉止。
  • 問題点など
    • PR-BS相対位置測定後、EXでの再位置測定が必要か?
    • PR系のスリップが頻発している。特にPR3。
    • BSテーブルにPDを置けるかどうか。
    • Eendの遮蔽板をいつ開けるか。
    • 真空引きの最終確認。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools