Differences between revisions 166 and 212 (spanning 46 versions)
Revision 166 as of 2017-11-27 09:32:03
Size: 6350
Comment:
Revision 212 as of 2017-12-18 09:27:48
Size: 7041
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * BS PDセット
  * 12/15 横澤

  
Line 58: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 61: Line 62:
2017/11/27(Mon.) 2017/12/18(Mon.)
Line 64: Line 65:
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているので締め直す必要がある。今日、明日でミラプロに頼んで締め直しをする。
    * PRMのリリースはビームのアラインメントと並行に進める。今週後半か。
   * WS
    * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
    * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
   * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。
  * 作業報告および作業予定 (*:責任者)
   * アラインメント: *和泉、長野、榎本、川崎
    * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
    * BFのピコモーターが離散的に動く。5mrad程度のステップ。
     * BFを固定した方がアラインメントはやりやすいのでは?(都丸)
    * アラインメントは今日はなし。

   * Type A(ETMY): *牛場、宮本
    * バネが動きを吸収している可能性があるので、バネを変える。
    * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
    * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。
     * 今日蓋閉めの準備のためにその作業をするので、
    * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
    * 火曜日の夕方に方向性を判断。

   * PD設置: *横澤、和泉
    * BSチェンバー内、AS側に設置完了。
    * EYAにいってViewポートを取り付ける。

   * BSカメラ設置: *苔山、川崎
    * BS付近に設置したが、レンズ交換が必要。
Line 74: Line 88:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
Line 78: Line 89:
   * 今日明日はIMMTより奥、水曜からSRラインより奥。    * センターはSR奥がハザードエリア。エンドはハザードエリアなし。
Line 81: Line 92:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直し。
   * メインビームの再アラインメント。
Line 86: Line 93:
  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
Line 94: Line 100:
  * PRMの足が浮いている。
  * D-SUBケーブルがおかしくなったものが出た。
  * 回路電源のモニターがあるといい。
Line 108: Line 113:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 121: Line 127:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/18(Mon.)

  • Daily
    • 作業報告および作業予定 (*:責任者)
      • アラインメント: *和泉、長野、榎本、川崎
        • BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
        • BFのピコモーターが離散的に動く。5mrad程度のステップ。
          • BFを固定した方がアラインメントはやりやすいのでは?(都丸)
        • アラインメントは今日はなし。
      • Type A(ETMY): *牛場、宮本
        • バネが動きを吸収している可能性があるので、バネを変える。
        • Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
        • Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。

          • 今日蓋閉めの準備のためにその作業をするので、
        • 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
        • 火曜日の夕方に方向性を判断。
      • PD設置: *横澤、和泉
        • BSチェンバー内、AS側に設置完了。
        • EYAにいってViewポートを取り付ける。
      • BSカメラ設置: *苔山、川崎
        • BS付近に設置したが、レンズ交換が必要。
    • Laser hazard
      • センターはSR奥がハザードエリア。エンドはハザードエリアなし。
  • Weekly
    • 12/18の週
      • EYC閉止
      • Type A引き続き調整。
  • 問題点など
    • 回路電源のモニターがあるといい。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)