Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。  * BS PDセット
  * 12/15 横澤
Line 31: Line 29:
  
Line 60: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 62:
2017/11/27(Mon.) 2017/12/15(Fri.)
Line 66: Line 65:
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているので締め直す必要がある。今日、明日でミラプロに頼んで締め直しをする。
    * PRMのリリースはビームのアラインメントと並行に進める。今週後半か。
   * WS
    * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
    * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
   * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。
  * 報告と作業 (*:責任者)
Line 75: Line 67:
   * アラインメント: *和泉、長野、川崎、榎本
    * BSのアルミ箔を外し、EYのPDに光をあてる。
    * IMMT2のピコモーターがスタックしているようなのでそれを直す。
    * EYのPDを回収して、スリットを使いEYのアラインメントをする。
     * Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
    * BSで光が見えたらゴール。
Line 76: Line 74:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * Type B(BS): *正田、和泉、長野
    * TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。

   * Type A(ETMY): *牛場、宮本
    * 揺れはOplevでみて数uradになっている。
    * アラインメントはなんとか出るところまでは持っていけた。

   * PD設置: *横澤
    * 和泉君の指示で移動のタイミングを横澤君に知らせる。

   * BSカメラ設置: *苔山、長野
    * 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。
Line 80: Line 88:
   * 今日明日はIMMTより奥、水曜からSRラインより奥。    * センターは変わらずSR奥。
   * 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。
Line 83: Line 92:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直し。
   * メインビームの再アラインメント。
Line 88: Line 93:
  * 12/4の週
   * Type Aダンピングテスト。
Line 92: Line 95:
  * 12/18EYC閉止
* 12/18の週
   *
EYC閉止
Line 96: Line 102:
  * PRMの足が浮いている。
  * D-SUBケーブルがおかしくなったものが出た。
Line 110: Line 113:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 123: Line 127:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/15(Fri.)

  • Daily
    • 報告と作業 (*:責任者)
      • アラインメント: *和泉、長野、川崎、榎本
        • BSのアルミ箔を外し、EYのPDに光をあてる。
        • IMMT2のピコモーターがスタックしているようなのでそれを直す。
        • EYのPDを回収して、スリットを使いEYのアラインメントをする。
          • Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
        • BSで光が見えたらゴール。
      • Type B(BS): *正田、和泉、長野
        • TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。
      • Type A(ETMY): *牛場、宮本
        • 揺れはOplevでみて数uradになっている。
        • アラインメントはなんとか出るところまでは持っていけた。
      • PD設置: *横澤
        • 和泉君の指示で移動のタイミングを横澤君に知らせる。
      • BSカメラ設置: *苔山、長野
        • 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。
    • Laser hazard
      • センターは変わらずSR奥。
      • 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。
  • Weekly
    • 12/11の週
      • ETMYからの戻り光確認。
    • 12/18の週
      • EYC閉止
  • 問題点など

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members