Differences between revisions 171 and 194 (spanning 23 versions)
Revision 171 as of 2017-11-28 09:13:28
Size: 6710
Comment:
Revision 194 as of 2017-12-11 15:10:06
Size: 6698
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/12/11 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/11
  * 12/12 和泉
  * 12/13 和泉
  * 12/14 和泉、長野、川﨑、川崎
  * 12/15 和泉、長野、川﨑、榎本、川崎
 
 * GigEカメラセット
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
Line 29: Line 34:
 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
 * BS PDセット
  * 12/11
  * 12/12 横澤
  * 12/13 横澤
  * 12/14
  * 12/15
  
Line 60: Line 70:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 73:
2017/11/28(Tue.) 2017/12/11(Mon.)
Line 66: Line 76:
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているのでシムを入れて、傾きを補正して締め直したす。水平になっているはず。
    * PRMを今日リリースする予定。
   * アラインメント
    * PSLQPDでピッチ方向にずれ、MCTのQPDにヨー方向にずれがあった。IMMT1、2のアラインメントを取り直して、PR真空曹のフランジのセンターには当たった。
    * メインビームのアラインメントは明日の水曜以降に続ける。
   * WS
    * 昨日夕方から一部実際の作業が始まっている。
    * 物の準備はだいたい完了。一部足りないものを持ち込むなどの作業がある。
  * 報告と作業 (*:責任者)

   * アラインメント:
    * 現在Xエンドまで通っている。明日、明後日でEYAに通す。

   * Type B: *Mark、Enzo, 神津、正田
    * 今日も引き続き制御系のチェックをする。

   * Type A: 午後から*高橋(2637)、奥富、宮本
    * actuatorのテストなどの続き。
    * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。

   * PD設置: 横澤
    * PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。
Line 78: Line 92:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * Type Bp: 正田(SRの作業の合間)
Line 83: Line 93:
   * 今日までIMMTより奥、明日の水曜からSRラインより奥に変更    * SRラインより奥。
Line 86: Line 96:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。

  * 12/11の週
Line 90: Line 99:

  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
Line 95: Line 100:
   * 12/18EYC閉止。    * 12/13 昼休みに真空引きの前のミーティング。
* 12/18 EYC閉止。
Line 99: Line 105:
  * D-SUBケーブルがおかしくなったものが出た。 -> AEL
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * 一部のカメラが表示されない(和泉、Stefan)。 -> 苔山
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
Line 114: Line 121:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/11 updated KAGRA/Commissioning/Commissioning_schedule_20171212.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/11
    • 12/12 和泉
    • 12/13 和泉
    • 12/14 和泉、長野、川﨑、川崎
    • 12/15 和泉、長野、川﨑、榎本、川崎
  • GigEカメラセット
    • 12/11
    • 12/12
    • 12/13
    • 12/14
    • 12/15
  • BS PDセット
    • 12/11
    • 12/12 横澤
    • 12/13 横澤
    • 12/14
    • 12/15



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/11(Mon.)

  • Daily
    • 報告と作業 (*:責任者)
      • アラインメント:
        • 現在Xエンドまで通っている。明日、明後日でEYAに通す。
      • Type B: *Mark、Enzo, 神津、正田
        • 今日も引き続き制御系のチェックをする。
      • Type A: 午後から*高橋(2637)、奥富、宮本
        • actuatorのテストなどの続き。
        • Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。
      • PD設置: 横澤
        • PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。
    • Laser hazard
      • SRラインより奥。
  • Weekly
    • 12/11の週
      • メインビームの再アラインメント。
      • ETMYからの戻り光確認。
      • 12/13 昼休みに真空引きの前のミーティング。
      • 12/18 EYC閉止。
  • 問題点など
    • PR-BS相対位置測定後、EXでの再位置測定が必要か?
    • PR系のスリップが頻発している。特にPR3。
    • BSテーブルにPDを置けるかどうか。
    • Eendの遮蔽板をいつ開けるか。
    • 真空引きの最終確認。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members