Differences between revisions 24 and 208 (spanning 184 versions)
Revision 24 as of 2017-10-06 09:13:10
Size: 3366
Comment:
Revision 208 as of 2017-12-14 13:57:10
Size: 8120
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
== Current task ==
Line 5: Line 4:
2017/10/6 == Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}


-----
== Working people assignment ==
* 責任者
  

 * ETMYアラインメント
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/14
  * 12/15

 * BS PDセット
  * 12/14 横澤
  * 12/15

 * 遮蔽板取り外し
  * 木村
  
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
-----
== Meetings ==

----
<<Anchor(MorningMeetings)>>
=== Morning meeting ===

 * Date and time: Every weekday, 9AM
 * Location: Control room, or eZuce


2017/12/14(Thu.)
Line 8: Line 70:
  * EYAのケーブル類設置
   * PD設置完了ケーブル張りの途中まで完了。
  * PR2の調整
   * モーターネットワークの調整をする。ローカルには動くようになったので、リモートで動くかどうかのテスト。
  * PRMのOplevがフレームと干渉してしまった。フレームを取り除くのが大変なので、とりあえずPRMを固定したままで進める。リリースできるかどうかは検討。
  * 報告と作業 (*:責任者)
Line 14: Line 72:
  * BSの調整
   * 回路の確認、修理。ステッパーモーター、GEO phoneなど。
   * 遮蔽板取り外し: *木村、その他
    * 朝から取り外し作業開始。終了次第宮川まで連絡。
Line 17: Line 75:
  * IMMT2のリリース
   * ミラーをリリースしたが、チェンバー中心からマイナスY側に2cmくらいずれていたが、Phase1ではこのまま行く。
   * ビームが新しい位置になったので、調整し直し。新井君が手伝う。
   * アラインメント: *和泉、長野、川崎、三代木
    * ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。
    * 遮蔽板の取り外しが終わり次第アラインメント開始。
     * ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。
Line 21: Line 80:
  * EX/YAのG-マットはり
   * EXAの重機の設置も合わせて、ほぼ完了。今日がEYA。
   * Type B: *Mark、Enzo, 正田, 和泉
    * 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。
     * それでもダンピングはまだ効いていないようである。
    * IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。
Line 24: Line 85:
  *

 * Weekly(来週のデフォルトスケジュール)
  * This week
   * アラインメント作業準備
  * Next week
   * IMMT2とPR2のアラインメント及びPR3のラフなアラインメント(BSの真ん中あたりにあてる)。

 * 10/10の予定
  * 光が通るように準備(BSの腕側は閉じたままにする)
  * ハザードエリア変更への対応
  * 余裕があればアラインメント開始
   * Type A: *牛場、宮本
    * Fishing rodの稼働実験をした。結果は残念ながら動かなかった。
     * さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。
     * unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか?
     * この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。
Line 38: Line 92:
2017/10/5

 * Daily
  * EYAのケーブル類設置
  * PR2の調整
  * EX/YAのG-マットはり
  * BSの調整
  * IMMT2のリリース

 * Weekly(来週のデフォルトスケジュール)
  * IMMT2とPR2のアラインメント及びPR3のラフなアラインメント(BSの真ん中あたりにあてる)

 * 10/10の予定
  * 光が通るように準備(BSの腕側は閉じたままにする)
  * ハザードエリア変更への対応
  * 余裕があればアラインメント開始
   * PD設置:
    * 和泉君の指示で移動のタイミングを横澤君に知らせる。
     * 時期としては今日の午後か、明日の午前くらい。
Line 57: Line 98:
----
== Meeting ==
=== Weekly meeting ===
  * Laser hazard
   * SRラインより奥。
   * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
Line 61: Line 102:
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokum Kaikan, or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
 * Weekly

  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。

  * 12/18の週
   * EYC閉止
Line 70: Line 114:
=== Morning meeting ===
Line 72: Line 115:
 * Date and time: Every weekday, 9AM
 * Location: Control room, or educe
 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川)

<<MonthCalendar(KAGRA/Commissioning/DailyWork)>>
Line 76: Line 123:
----
<<Anchor(WeeklyMeetings)>>
==== Weekly meeting ====
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]


-----
Line 77: Line 152:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|Commissioning plan for Phase1]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]
Line 81: Line 156:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/14 和泉、長野、川﨑
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/14
    • 12/15
  • BS PDセット
    • 12/14 横澤
    • 12/15
  • 遮蔽板取り外し
    • 木村



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/14(Thu.)

  • Daily
    • 報告と作業 (*:責任者)
      • 遮蔽板取り外し: *木村、その他
        • 朝から取り外し作業開始。終了次第宮川まで連絡。
      • アラインメント: *和泉、長野、川崎、三代木
        • ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。
        • 遮蔽板の取り外しが終わり次第アラインメント開始。
          • ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。
      • Type B: *Mark、Enzo, 正田, 和泉
        • 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。
          • それでもダンピングはまだ効いていないようである。
        • IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。
      • Type A: *牛場、宮本
        • Fishing rodの稼働実験をした。結果は残念ながら動かなかった。
          • さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。
          • unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか?
          • この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。
      • PD設置:
        • 和泉君の指示で移動のタイミングを横澤君に知らせる。
          • 時期としては今日の午後か、明日の午前くらい。
    • Laser hazard
      • SRラインより奥。
      • 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
  • Weekly
    • 12/11の週
      • メインビームの再アラインメント。
      • ETMYからの戻り光確認。
      • 12/13 昼休みに真空引きの前のミーティング。
      • 12/18 EYC閉止。
    • 12/18の週
      • EYC閉止
  • 問題点など
    • PR-BS相対位置測定後、EXでの再位置測定が必要か?
    • PR系のスリップが頻発している。特にPR3。
    • WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川)

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members