Differences between revisions 120 and 215 (spanning 95 versions)
Revision 120 as of 2017-11-08 15:56:20
Size: 5918
Comment:
Revision 215 as of 2017-12-19 09:17:14
Size: 7680
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 13: Line 19:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .
Line 17: Line 20:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 24: Line 26:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * BS PDセット
  * 12/15 横澤
Line 30: Line 29:
  
Line 32: Line 32:
<<Anchor(EmergencyContactPerson)>>
Line 34: Line 35:
 * Laser, RefCav, IMC: 苔山、中野  * Laser, Ref''''''Cav, IMC: 苔山、中野
Line 39: Line 40:
  * Type A: 高橋、奥富
 * PicoMotor: 三代
 * Digital: 宮川、山本
 * 回路: 宮川、上泉、戸村、霜出
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
Line 58: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 61: Line 62:
2017/11/8(Wed.) 2017/12/19(Tue.)
Line 63: Line 64:
 * Daily
  * 作業人員(*:責任者)
   * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木))
   * VIS: Mark, Enzo, 神津
 * 作業報告 (*:責任者)
  * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
   * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
   * Fishing rodのスタックも直した。
Line 68: Line 69:
  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
  * Vierport: *横澤、井上
   * EYAにViewport設置完了。
Line 72: Line 72:
  * 作業
   * ビーム位置測定
    * IYCでの位置測定をした。完了。現在まとめ中。
    * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * コイルドライバーがおかしい可能性がある。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
   * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。
Line 77: Line 78:
   * 防振関連
    * BSのlength sensing Oplev, オフセットリリースなど。
 * 作業予定 (*:責任者)
  * アラインメント: *和泉
   * 今日の昼休み12時から1時の間にスリットを置く。
Line 80: Line 82:
   * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。   * Type A(ETMY): *高橋、牛場、都丸、和泉
   * Fishing rodが動くか確認。

  * IOO
   * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
   * MCの調子が悪い。



 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 昼の間だけYend 1Fがハザートエリアになる。
Line 83: Line 96:
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。

  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
   * ETMYのアラインメント
Line 87: Line 104:
  * コーチフィルターが不調。   * 回路電源のモニターがあるといい。
  * MCの調子が悪い。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
Line 96: Line 118:
 * Location: Meeting room at Hokum , or educe, Polycom  * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
Line 99: Line 121:
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 111: Line 136:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/19(Tue.)

  • 作業報告 (*:責任者)
    • Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
      • BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
      • Fishing rodのスタックも直した。
    • Vierport: *横澤、井上
      • EYAにViewport設置完了。
    • IMMTが動かない件
      • EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
      • コイルドライバーがおかしい可能性がある。
      • アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
      • アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。
  • 作業予定 (*:責任者)
    • アラインメント: *和泉
      • 今日の昼休み12時から1時の間にスリットを置く。
    • Type A(ETMY): *高橋、牛場、都丸、和泉
      • Fishing rodが動くか確認。
    • IOO
      • ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
      • MCの調子が悪い。
  • Laser hazard
    • センターはSR奥がハザードエリア。
    • 昼の間だけYend 1Fがハザートエリアになる。
  • Weekly
    • 12/18の週
      • EYC閉止
      • Type A引き続き調整。
      • ETMYのアラインメント
  • 問題点など
    • 回路電源のモニターがあるといい。
    • MCの調子が悪い。
    • IMMTが動かない件
      • EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
      • アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1