Differences between revisions 126 and 224 (spanning 98 versions)
Revision 126 as of 2017-11-08 17:31:56
Size: 6070
Comment:
Revision 224 as of 2017-12-27 09:25:56
Size: 7733
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
Line 12: Line 14:
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}}
Line 17: Line 18:
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
Line 18: Line 22:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .

 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
Line 40: Line 27:
 * Laser, RefCav, IMC: 苔山、中野  * Laser, Ref''''''Cav, IMC: 苔山、中野
Line 45: Line 32:
  * Type A: 高橋、奥富
 * PicoMotor: 三代
 * Digital: 宮川、山本
 * 回路: 宮川、上泉、戸村、霜出
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
Line 64: Line 51:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 67: Line 54:
2017/11/8(Wed.) 2017/12/27(Wed.)
Line 69: Line 56:
 * Daily
  * 作業人員(*:責任者)
   * 下げ振り測定: *木村、荒木、井上、澤田(KEK-2(木村), V-6(井上), V-2(荒木))
   * VIS: Mark, Enzo, 神津
 * Remote participants by educe: None
Line 74: Line 58:
  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
 * 停電からの復帰関連
  * DGS: PR3以外は全て復帰した。
  * AEL: PR2とIOOの電源を分けた。復電後24V
  * IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
   * TTFSSも確認できていない。
   * MCも復帰できていない。
  * Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
   * PRMのみ少しキックがあった。大きさは数十uradくらい。
  * Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
  * 真空: MCポンプのみ復帰。腕はそのまま。
Line 78: Line 69:
  * 作業
   * ビーム位置測定
    * IYCでの位置測定をした。完了。現在まとめ中。
    * IXCでの下げ振り測定。IXCとBSの間のGVを閉めて真空引きを始める予定。
Line 83: Line 70:
   * 防振関連
    * BSのlength sensing Oplev, オフセットリリースなど。
 * Report of work (*:responsible person)
Line 86: Line 72:
   * センターで2cmほど-Y方向にずれているので、RR系の位置測定の後、さらにビーム位置をもう一度する。おそらくPR3の位置がずれていると思われるので、そのずれをトラバーサーで吸収する予定。   * AOS: *Akutsu
   * PR2の横にグリーンを構築しつつある。
    * 今日はビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。

 * IOO: ISS準備と実験。

 * Current limitを変更した。IOOは18A、その他は21Aに設定した。
 


 
  * Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
   * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。

 * Work plan (*:responsible person)
  * AOS: *Akutsu
   * グリーンのビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。



 * Laser hazard
   * センターはSR奥がハザードエリア。
Line 89: Line 100:
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
Line 92: Line 101:
 * 問題点など
  * コーチフィルターが不調。
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。

 * Week of 12/25
  * Planed power outage in the afternoon on 12/25.


 * Issues
  * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい
Line 105: Line 123:
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 117: Line 138:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者

  • Green setting on PR2:
    • 12/26 *Akutsu, Yokogawa + 1 or 2
    • 12/27 *Yokogawa + 1 or 2



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/27(Wed.)

  • Remote participants by educe: None
  • 停電からの復帰関連
    • DGS: PR3以外は全て復帰した。
    • AEL: PR2とIOOの電源を分けた。復電後24V
    • IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
      • TTFSSも確認できていない。
      • MCも復帰できていない。
    • Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
      • PRMのみ少しキックがあった。大きさは数十uradくらい。
    • Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
    • 真空: MCポンプのみ復帰。腕はそのまま。
  • Report of work (*:responsible person)
    • AOS: *Akutsu
      • PR2の横にグリーンを構築しつつある。
        • 今日はビームプロファイルなど。
      • EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
        • 今日は引き続き作業の可能性あり。
  • IOO: ISS準備と実験。
  • Current limitを変更した。IOOは18A、その他は21Aに設定した。
    • Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
      • Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。
  • Work plan (*:responsible person)
    • AOS: *Akutsu
      • グリーンのビームプロファイルなど。
      • EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
        • 今日は引き続き作業の可能性あり。
  • Laser hazard
    • センターはSR奥がハザードエリア。
  • Weekly
    • Week of 12/18
      • EYC閉止。
      • Type A引き続き調整。
      • ETMYのアラインメント。
  • Week of 12/25
    • Planed power outage in the afternoon on 12/25.
  • Issues
    • k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)