Line 11: | Line 11: |
2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
Line 18: | Line 18: |
* Green setting on PR2: * 12/26 *Akutsu, Yokogawa + 1 or 2 * 12/27 *Yokogawa + 1 or 2 |
|
Line 19: | Line 22: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
|
Line 58: | Line 51: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 61: | Line 54: |
2017/11/22(Wed.) | 2017/12/27(Wed.) |
Line 63: | Line 56: |
* Daily * 作業 * Type A: 復帰した。 * IOO: PSLとMCともに光軸ズレがありそう。今日もう一度確認する。 * 計算機: ほぼ復帰。k1bsとk1ey1, k1ex0, k1ey0に少しトラブルあり。 * Type Bp: PR系は信号は来ている。PR2のAAフィルターが調子が悪いので交換。PRMのリリースをしたがぶつかっている様子。 * タンクからサテライトボックスまでのD-SUBケーブルが一つダメになっている。 * PR2のBIOを一枚増やした。カードの認識がバラバラ。インプットとアウトプットさえバラバラ。 * 真空: MC復帰した。Xarm復帰した。Yarmを今日か明日復帰する。 * Yendピット内の水がまだ冠水中。今日シートをかぶせて作業を再開。 * MCFの前のGreenとPOP用光学定盤を移動させたい。 * 12時からeZuceでiKAGRAからの引き継ぎ会議。 |
* Remote participants by educe: None * 停電からの復帰関連 * DGS: PR3以外は全て復帰した。 * AEL: PR2とIOOの電源を分けた。復電後24V * IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。 * TTFSSも確認できていない。 * MCも復帰できていない。 * Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。 * PRMのみ少しキックがあった。大きさは数十uradくらい。 * Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。 * 真空: MCポンプのみ復帰。腕はそのまま。 |
Line 77: | Line 70: |
停電のため報告、作業予定特になし。 | * Report of work (*:responsible person) |
Line 79: | Line 72: |
* 作業人員(*:責任者) | * AOS: *Akutsu * PR2の横にグリーンを構築しつつある。 * 今日はビームプロファイルなど。 * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。 * 今日は引き続き作業の可能性あり。 |
Line 81: | Line 78: |
* Laser hazard * 停電のためなし。 |
* IOO: ISS準備と実験。 * Current limitを変更した。IOOは18A、その他は21Aに設定した。 * Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。 * Work plan (*:responsible person) * AOS: *Akutsu * グリーンのビームプロファイルなど。 * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。 * 今日は引き続き作業の可能性あり。 * Laser hazard * センターはSR奥がハザードエリア。 |
Line 85: | Line 100: |
* 11/20の週 * 停電のため前半は作業困難な状況。 * PR系の位置測定。 * Watch dogのテストとPRMのリリース。 |
|
Line 90: | Line 101: |
* 問題点など * 停電のため本日は作業中止。 * PR2、3のアラインメントにメインビームが必要。CRYは今週はメインビームは出して欲しくない。 |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
Line 94: | Line 106: |
* Week of 12/25 * Planed power outage in the afternoon on 12/25. * Issues * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい |
|
Line 105: | Line 123: |
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || | ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
Line 118: | Line 138: |
* Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/12/19 updated
Working people assignment
* 責任者
- Green setting on PR2:
- 12/26 *Akutsu, Yokogawa + 1 or 2
- 12/27 *Yokogawa + 1 or 2
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/27(Wed.)
- Remote participants by educe: None
- 停電からの復帰関連
- DGS: PR3以外は全て復帰した。
- AEL: PR2とIOOの電源を分けた。復電後24V
- IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
- TTFSSも確認できていない。
- MCも復帰できていない。
- Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
- PRMのみ少しキックがあった。大きさは数十uradくらい。
- Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
- 真空: MCポンプのみ復帰。腕はそのまま。
- Report of work (*:responsible person)
- AOS: *Akutsu
- PR2の横にグリーンを構築しつつある。
- 今日はビームプロファイルなど。
- EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
- 今日は引き続き作業の可能性あり。
- PR2の横にグリーンを構築しつつある。
- AOS: *Akutsu
- IOO: ISS準備と実験。
- Current limitを変更した。IOOは18A、その他は21Aに設定した。
- Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
- Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。
- Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
- Work plan (*:responsible person)
- AOS: *Akutsu
- グリーンのビームプロファイルなど。
- EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
- 今日は引き続き作業の可能性あり。
- AOS: *Akutsu
- Laser hazard
- センターはSR奥がハザードエリア。
- Weekly
- Week of 12/18
- EYC閉止。
- Type A引き続き調整。
- ETMYのアラインメント。
- Week of 12/18
- Week of 12/25
- Planed power outage in the afternoon on 12/25.
- Issues
k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|