Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
・PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。  * BS PDセット
  * 12/15 横澤
Line 31: Line 29:
  
Line 60: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 62:
2017/11/27(Mon.) 2017/12/19(Tue.)
Line 65: Line 64:
 * Daily
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているので締め直す必要がある。今日、明日でミラプロに頼んで締め直しをする。
    * PRMのリリースはビームのアラインメントと並行に進める。今週後半か。
   * WS
    * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
    * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
   * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。
 * 作業報告 (*:責任者)
  * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
   * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
   * Fishing rodのスタックも直した。

  * Vierport: *横澤、井上
   * EYAにViewport設置完了。

  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * コイルドライバーがおかしい可能性がある。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
   * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。

 * 作業予定 (*:責任者)
  * アラインメント: *和泉
   * 今日の昼休み12時から1時の間にスリットを置く。

  * Type A(ETMY): *高橋、牛場、都丸、和泉
   * Fishing rodが動くか確認。

  * IOO
   * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
   * MCの調子が悪い。
Line 76: Line 90:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
Line 79: Line 91:
  * Laser hazard
   * 今日明日はIMMTより奥、水曜からSRラインより奥。
 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 午後からYend 1Fがハザートエリアになる。
Line 83: Line 96:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直し。
   * メインビームの再アラインメント。
Line 88: Line 97:
  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
   * ETMYのアラインメント
Line 96: Line 104:
  * PRMの足が浮いている。
  * D-SUBケーブルがおかしくなったものが出た。
  * 回路電源のモニターがあるといい。
  * MCの調子が悪い。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
Line 110: Line 121:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 123: Line 136:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/19(Tue.)

  • 作業報告 (*:責任者)
    • Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
      • BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
      • Fishing rodのスタックも直した。
    • Vierport: *横澤、井上
      • EYAにViewport設置完了。
    • IMMTが動かない件
      • EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
      • コイルドライバーがおかしい可能性がある。
      • アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
      • アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。
  • 作業予定 (*:責任者)
    • アラインメント: *和泉
      • 今日の昼休み12時から1時の間にスリットを置く。
    • Type A(ETMY): *高橋、牛場、都丸、和泉
      • Fishing rodが動くか確認。
    • IOO
      • ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
      • MCの調子が悪い。
  • Laser hazard
    • センターはSR奥がハザードエリア。
    • 午後からYend 1Fがハザートエリアになる。
  • Weekly
    • 12/18の週
      • EYC閉止
      • Type A引き続き調整。
      • ETMYのアラインメント
  • 問題点など
    • 回路電源のモニターがあるといい。
    • MCの調子が悪い。
    • IMMTが動かない件
      • EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
      • アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1