Differences between revisions 173 and 219 (spanning 46 versions)
Revision 173 as of 2017-11-28 10:24:15
Size: 6710
Comment:
Revision 219 as of 2017-12-20 09:22:01
Size: 7858
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。  * BS PDセット
  * 12/15 横澤
Line 31: Line 29:
  
Line 60: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 62:
2017/11/28(Tue.) 2017/12/20(Wed.)
Line 65: Line 64:
 * Daily
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているのでシムを入れて、傾きを補正して締め直したす。水平になっているはず。
    * PRMを今日リリースする予定。
   * アラインメント
    * PSLQPDでピッチ方向にずれ、MCTのQPDにヨー方向にずれがあった。IMMT1、2のアラインメントを取り直して、PR真空曹のフランジのセンターには当たった。
    * メインビームのアラインメントは明日の水曜以降に続ける。
   * WS
    * 昨日夕方から一部実際の作業が始まっている。
    * 物の準備はだいたい完了。一部足りないものを持ち込むなどの作業がある。
 * 作業報告 (*:責任者)
  * Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
   * BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく光はエンドに当たった。
   * スリットを使う(三代木法)ことで、BS側に戻すのも相当順調だった。実際にスリットを外してすぐにBSのPDが反応した。
   * ETMYのPayloadのYawに200uradくらいの揺れが残っている。ヒートリンクに触ってしまった可能性が高い。ダンピングが必要。
    * Pitchも数十urad位揺れている。Pitchはおそらく上からのエアーで揺れている可能性が高い。
   * 光はYendで14000カウントでていたが、BSで6000カウントになった。予測とほぼ一致している。
Line 77: Line 72:
  * IMMTが動かない件
   * IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度起きているので、再現性がありそう。
   * DACカードの順序が入れ替わっているようである。->DGS
Line 78: Line 76:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * Type Bp: 正田(SRの作業の合間)
  * IOO: 苔山、古畑、坂本、北澤
   * ISSのアラインメントがほぼ完了。AOMを触らなければならない時点でストップした。
   * MCのBURTがきちんと戻っていなかって、MCのサーボのゲインが間違っていたのでMCが不安定だった。直したら、安定になった。(和泉)
Line 82: Line 80:
  * Laser hazard
   * 今日までIMMTより奥、明日の水曜からSRラインより奥に変更。
 * 作業予定 (*:責任者)
  * Alignment of ETMY: *和泉、高橋、牛場、都丸、宮本
   * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。

  * IOO
   * アラインメントがあるので、今日の作業は他のことをする。

  * BS: Oplevの位置の初期化をしたい。

 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。
Line 86: Line 94:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
Line 91: Line 95:
  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。

 * Week of 12/25
  * 停電の可能性あり。
Line 99: Line 105:
  * D-SUBケーブルがおかしくなったものが出た。 -> AEL
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * 一部のカメラが表示されない(和泉、Stefan)。 -> 苔山
Line 114: Line 117:
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 127: Line 132:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/20(Wed.)

  • 作業報告 (*:責任者)
    • Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
      • BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく光はエンドに当たった。
      • スリットを使う(三代木法)ことで、BS側に戻すのも相当順調だった。実際にスリットを外してすぐにBSのPDが反応した。
      • ETMYのPayloadのYawに200uradくらいの揺れが残っている。ヒートリンクに触ってしまった可能性が高い。ダンピングが必要。
        • Pitchも数十urad位揺れている。Pitchはおそらく上からのエアーで揺れている可能性が高い。
      • 光はYendで14000カウントでていたが、BSで6000カウントになった。予測とほぼ一致している。
    • IMMTが動かない件
      • IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度起きているので、再現性がありそう。
      • DACカードの順序が入れ替わっているようである。->DGS

    • IOO: 苔山、古畑、坂本、北澤
      • ISSのアラインメントがほぼ完了。AOMを触らなければならない時点でストップした。
      • MCのBURTがきちんと戻っていなかって、MCのサーボのゲインが間違っていたのでMCが不安定だった。直したら、安定になった。(和泉)
  • 作業予定 (*:責任者)
    • Alignment of ETMY: *和泉、高橋、牛場、都丸、宮本
      • Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。
    • IOO
      • アラインメントがあるので、今日の作業は他のことをする。
    • BS: Oplevの位置の初期化をしたい。
  • Laser hazard
    • センターはSR奥がハザードエリア。
    • 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。
  • Weekly
    • Week of 12/18
      • EYC閉止。
      • Type A引き続き調整。
      • ETMYのアラインメント。
  • Week of 12/25
    • 停電の可能性あり。
  • 問題点など

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1