Revision 176 as of 2017-11-30 09:16:03
Size: 7310
Comment:
Revision 216 as of 2017-12-19 09:40:48
Size: 7677
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。  * BS PDセット
  * 12/15 横澤
Line 31: Line 29:
  
Line 60: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 62:
2017/11/30(Thur.) 2017/12/19(Tue.)
Line 65: Line 64:
 * Daily
  * 作業
   * WS
    * 午後4時くらいにペリスコープに加速度計をつけようとして鏡を触ってしまい、ミスアラインメントが起きてしまった。午後6時くらいにはMCで85%の透過光くらいまでは戻った。PSLだけでは戻らなかったのでMCを少し動かした。MC透過光ももとのレベルに戻った。
    * MCの戻り光を干渉なしで直接見ても復調信号にオフセットが乗っているのでどうやらAMが載っているのは事実のようである。EOMでのジッターがAMの原因か?-40dBmレベル。メインパワーとの比率は未測定。
    * PSL出射光でのビームが楕円になっている件は何か原因を見つけたようである。その過程で、他の改良点もいくつか見つかっている。
 * 作業報告 (*:責任者)
  * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
   * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
   * Fishing rodのスタックも直した。
Line 72: Line 69:
   * アラインメント
    * 昨日でPR3までビームが当たっていることまで確認できた。今日うまくけばエンドで光が再び見えるはず。
  * Vierport: *横澤、井上
   * EYAにViewport設置完了。
Line 75: Line 72:
   * Type B:
    * BSのダンピングがかなり改善された。Oplevはまだセンサー内に光が戻ってきていない。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * コイルドライバーがおかしい可能性がある。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
   * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。

 * 作業予定 (*:責任者)
  * アラインメント: *和泉
   * 今日の昼休み12時から1時の間にスリットを置く。

  * Type A(ETMY): *高橋、牛場、都丸、和泉
   * Fishing rodが動くか確認。

  * IOO
   * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
   * MCの調子が悪い。
Line 79: Line 90:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * アラインメント: 和泉、正田、榎本
   * Type B: Mark、 Enzo、平田、正田
Line 84: Line 91:

  * Laser hazard
   * 今日からSRラインより奥に変更。
 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 午後からYend 1Fがハザートエリアになる。
Line 89: Line 96:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
Line 94: Line 97:
  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
   * ETMYのアラインメント
Line 102: Line 104:
  * D-SUBケーブルがおかしくなったものが出た。 -> 結局その先のフリッパーケーブルが問題であることが判明。
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * COACH filterのアサインメントとクリーンエアーのを確認する必要がある。->昨日は2台余っていたので、やりくりできそう。
  * 回路電源のモニターがあるといい。
  * MCの調子が悪い。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
Line 117: Line 121:
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 130: Line 136:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/14 updated KAGRA/Commissioning/Commissioning_schedule_20171213.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/19(Tue.)

  • 作業報告 (*:責任者)
    • Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
      • BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
      • Fishing rodのスタックも直した。
    • Vierport: *横澤、井上
      • EYAにViewport設置完了。
    • IMMTが動かない件
      • EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
      • コイルドライバーがおかしい可能性がある。
      • アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
      • アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。
  • 作業予定 (*:責任者)
    • アラインメント: *和泉
      • 今日の昼休み12時から1時の間にスリットを置く。
    • Type A(ETMY): *高橋、牛場、都丸、和泉
      • Fishing rodが動くか確認。
    • IOO
      • ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
      • MCの調子が悪い。
  • Laser hazard
    • センターはSR奥がハザードエリア。
    • 午後からYend 1Fがハザートエリアになる。
  • Weekly
    • 12/18の週
      • EYC閉止
      • Type A引き続き調整。
      • ETMYのアラインメント
  • 問題点など
    • 回路電源のモニターがあるといい。
    • MCの調子が悪い。
    • IMMTが動かない件
      • EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
      • アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)