Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田
Line 23: Line 20:
 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。  * BS PDセット
  * 12/15 横澤
Line 31: Line 29:
  
Line 60: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 62:
2017/11/30(Thur.) 2017/12/20(Wed.)
Line 65: Line 64:
 * Daily
  * 作業
   * WS
    * 午後4時くらいにペリスコープに加速度計をつけようとして鏡を触ってしまい、ミスアラインメントが起きてしまった。PSLだけでは戻らなかったので、10uradくらいのオーダーでMCを少し動かした。午後6時くらいにはMC透過光ももとのレベルに戻った。
    * 入射光にAMが載っているのは事実のようである。EOMでのジッターがAMの原因か?-40dBmレベル。メインパワーとの比率は未測定。
    * PSL出射光でのビームが楕円になっている件: 何か原因を見つけたようである。その過程で、他にも改善図べき点もいくつか見つかっているので、リスト化する。
 * 作業報告 (*:責任者)
  * Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
   * BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく戻った。
   * スリットを使うことで、BS側に戻すのも相当楽だった。
   * ETMYのPayloadのトーションに200uradくらいの揺れが残っている。ダンピングが必要。Pitchも数十uradくらい揺れている。Pitchはおそらく上からのエアー。
   * Yendで14000カウントでていたがBSで6000カウントになった。コンシステント。
Line 72: Line 71:
   * アラインメント
    * 昨日でPR3までビームが当たっていることを確認できた。今日うまくけばエンドで光が再び見えるはず。
  * IMMTが動かない件
   * IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度おきている。
   * DACカードの順序が入れ替わっているようである。->DGS
Line 75: Line 75:
   * Type B:
    * BSのダンピングがかなり改善された。Oplevはまだセンサー内に光が戻ってきていない。
  * IOO: 苔山、古畑、坂本、北澤
   * アラインメントがほぼ完了。

 * 作業予定 (*:責任者)
  * Alignment of ETMY: *和泉、高橋、牛場、都丸、
   * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。

  * IOO
Line 79: Line 85:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * アラインメント: 和泉、正田、榎本
   * Type B: Mark、 Enzo、平田、正田
Line 84: Line 86:

  * Laser hazard
   * 今日からSRラインより奥に変更。
 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。
Line 89: Line 91:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
Line 94: Line 92:
  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。

 * Week of 12/25
  * 停電の可能性あり。
Line 102: Line 102:
  * D-SUBケーブルがおかしくなったものが出た件 -> 結局その先のフリッパーケーブルが問題であることが判明。KAGRA標準のD-SUBケーブルは問題ない。
  * COACH filterのアサインメントとクリーンエアーのを確認する必要がある。->昨日は2台余っていたので、やりくりできそう。
  * 回路電源のモニターがあるといい。
  * MCの調子が悪い。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
Line 115: Line 119:
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 128: Line 134:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/20(Wed.)

  • 作業報告 (*:責任者)
    • Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
      • BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく戻った。
      • スリットを使うことで、BS側に戻すのも相当楽だった。
      • ETMYのPayloadのトーションに200uradくらいの揺れが残っている。ダンピングが必要。Pitchも数十uradくらい揺れている。Pitchはおそらく上からのエアー。
      • Yendで14000カウントでていたがBSで6000カウントになった。コンシステント。
    • IMMTが動かない件
      • IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度おきている。
      • DACカードの順序が入れ替わっているようである。->DGS

    • IOO: 苔山、古畑、坂本、北澤
      • アラインメントがほぼ完了。
  • 作業予定 (*:責任者)
    • Alignment of ETMY: *和泉、高橋、牛場、都丸、
      • Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。
    • IOO
  • Laser hazard
    • センターはSR奥がハザードエリア。
    • 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。
  • Weekly
    • Week of 12/18
      • EYC閉止。
      • Type A引き続き調整。
      • ETMYのアラインメント。
  • Week of 12/25
    • 停電の可能性あり。
  • 問題点など
    • 回路電源のモニターがあるといい。
    • MCの調子が悪い。
    • IMMTが動かない件
      • EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
      • アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)