Differences between revisions 180 and 225 (spanning 45 versions)
Revision 180 as of 2017-12-01 23:32:32
Size: 6541
Comment:
Revision 225 as of 2017-12-27 09:32:04
Size: 7435
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
Line 18: Line 18:
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
Line 19: Line 22:

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
 * ETMYアラインメント
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
 

Line 59: Line 51:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 62: Line 54:
2017/12/1(Fri.) 2017/12/27(Wed.)
Line 64: Line 56:
 * Daily
  * 作業
   * WS
    * 午後に片付けをする。
   * アラインメント
    * 昨日はあまり進展なし。PR3まで。今日うまくけばエンドで光が再び見えるはず。
    * 来週月火に真空作業があるため時間調整が必要。
 * Remote participants by educe: None
Line 72: Line 58:
   * Type B:
    * Oplevに光が入った。もう少し解析に時間がかかる。大まかにはアラインメントはEYには向いている。
 * 停電からの復帰関連
  * DGS: PR3以外は全て復帰した。
  * AEL:
   * PR2とIOOの電源を分けた。
   * 復電後24Vの電源が一つ壊れていることが確認された。交換済み。
   * Current limitを変更した。IOOは18A、その他は21Aに設定した。
Line 75: Line 65:
   * Type A:
    * Y-endのケーブリングをしている。荷重テストと、YawのアラインメントをBFのピコモーターでする。ダンピングの進展具合は宮本君と確認。
  * IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
   * TTFSSも確認できていない。
   * MCも復帰できていない。
  * Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
   * PRMのみ少しキックがあった。大きさは数十uradくらい。
  * Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
  * 真空: MCポンプのみ復帰。腕はそのまま。
Line 79: Line 74:
  * 作業人員(*:責任者)
   * WS: 麻生、*苔山、宮川 + 20名程度
   * アラインメント: 和泉、横澤、正田
   * Type B: Mark、 Enzo、平田、正田
   * Type A: 高橋、宮本
 * Report of work (*:responsible person)

  * AOS: *Akutsu
   * PR2の横にグリーンを構築しつつある。
    * 今日はビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。
Line 86: Line 83:
  * Laser hazard
   * 今日からSRラインより奥に変更。
 * Work plan (*:responsible person)
  * AOS: *Akutsu, yokokawa, yoshioka, kokeyama
   * グリーンのビームプロファイルなど。
   * EYのマリオネット作業の可能性あり。
  * IOO: *Kokeyama, others
   * ISS準備と実験。


 * Laser hazard
   * センターはSR奥がハザードエリア。
Line 90: Line 95:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
   * BSのダンピング
   * Type Aの接続

  * 12/4の週
   * Type Aダンピングテスト。
   * メインビームの再アラインメント。
   * 月、火にIYCでの真空作業がある。

  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * Week of 12/25
   * Planed power outage in the afternoon on 12/25.
Line 107: Line 99:
 * 問題点など
   * 来週月、火に真空作業があり、ビームを止めて欲しいという要請が来ている。
 * Issues
  * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい
  * PR3計算機が動いていない。
  * MC回路が一部破損か。
Line 120: Line 114:
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 133: Line 129:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者

  • Green setting on PR2:
    • 12/26 *Akutsu, Yokogawa + 1 or 2
    • 12/27 *Yokogawa + 1 or 2



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/27(Wed.)

  • Remote participants by educe: None
  • 停電からの復帰関連
    • DGS: PR3以外は全て復帰した。
    • AEL:
      • PR2とIOOの電源を分けた。
      • 復電後24Vの電源が一つ壊れていることが確認された。交換済み。
      • Current limitを変更した。IOOは18A、その他は21Aに設定した。
    • IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
      • TTFSSも確認できていない。
      • MCも復帰できていない。
    • Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
      • PRMのみ少しキックがあった。大きさは数十uradくらい。
    • Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
    • 真空: MCポンプのみ復帰。腕はそのまま。
  • Report of work (*:responsible person)
    • AOS: *Akutsu
      • PR2の横にグリーンを構築しつつある。
        • 今日はビームプロファイルなど。
      • EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
        • 今日は引き続き作業の可能性あり。
  • Work plan (*:responsible person)
    • AOS: *Akutsu, yokokawa, yoshioka, kokeyama
      • グリーンのビームプロファイルなど。
      • EYのマリオネット作業の可能性あり。
    • IOO: *Kokeyama, others
      • ISS準備と実験。
  • Laser hazard
    • センターはSR奥がハザードエリア。
  • Weekly
    • Week of 12/25
      • Planed power outage in the afternoon on 12/25.
  • Issues
    • k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい

    • PR3計算機が動いていない。
    • MC回路が一部破損か。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1