Line 11: | Line 11: |
2017/11/28 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}} |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
Line 18: | Line 18: |
* Green setting on PR2: * 12/26 *Akutsu, Yokogawa + 1 or 2 * 12/27 *Yokogawa + 1 or 2 |
|
Line 19: | Line 22: |
* PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。 * ETMYアラインメント * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 |
|
Line 59: | Line 51: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 62: | Line 54: |
2017/12/4(Mon.) | 2017/12/21(Thu.) |
Line 64: | Line 56: |
* Daily * 作業 (*:責任者) * アラインメント: *和泉、大石、麻生 * PR3のOSEMが当たってしまったために止まっている。今日明日で、今週中にエンドで光が再び見えるはず。 * 来週月火に真空作業があるため時間調整が必要。IXCとIYCに挿フランジ、IYAのベローズを外す作業がある。今日はXのアラインメントでYは塞ぐ。 |
* Report of work (*:responsible person) * Alignment of ETMY: *Izumi, Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa * BS: ETMYに光を当てた状態で、Oplevの位置の初期化をして0点に合わせた。 * Type Aのリリースはできなかった。 |
Line 70: | Line 61: |
* Type B: *Mark、平田 * 新しいマトリックスを試す。ダンピングが改善される予定。 * Type A: *宮本、高橋さん他 * YエンドのTypeAとCryペイロードが繋がって、ケーブル接続などのインストールは終わった。今日DGS側との導通確認。 |
* Work plan (*:responsible person) * No main work today. |
Line 77: | Line 65: |
* Laser hazard * 今日からSRラインより奥に変更。 |
* Laser hazard * センターはSR奥がハザードエリア。 |
Line 81: | Line 69: |
* 12/4の週 * Type Aダンピングテスト。 * メインビームの再アラインメント。 * 月、火にIYC、IXCでの真空作業がある。 * 12/6,7: PR-BS相対位置測 |
|
Line 87: | Line 70: |
* 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 * Week of 12/25 * Planed power outage in the afternoon on 12/15. |
Line 92: | Line 79: |
* 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? |
* Issues * k1imcでDACの入れ替えが起こっている |
Line 106: | Line 92: |
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || |
|
Line 119: | Line 107: |
* Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/12/19 updated
Working people assignment
* 責任者
- Green setting on PR2:
- 12/26 *Akutsu, Yokogawa + 1 or 2
- 12/27 *Yokogawa + 1 or 2
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/12/21(Thu.)
- Report of work (*:responsible person)
- Alignment of ETMY: *Izumi, Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa
- BS: ETMYに光を当てた状態で、Oplevの位置の初期化をして0点に合わせた。
- Type Aのリリースはできなかった。
- Alignment of ETMY: *Izumi, Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa
- Work plan (*:responsible person)
- No main work today.
- Laser hazard
- センターはSR奥がハザードエリア。
- Weekly
- Week of 12/18
- EYC閉止。
- Type A引き続き調整。
- ETMYのアラインメント。
- Week of 12/18
- Week of 12/25
- Planed power outage in the afternoon on 12/15.
- Issues
- k1imcでDACの入れ替えが起こっている
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|