Differences between revisions 72 and 225 (spanning 153 versions)
Revision 72 as of 2017-10-18 09:19:56
Size: 5276
Comment:
Revision 225 as of 2017-12-27 09:32:04
Size: 7435
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}


-----
Line 4: Line 17:
 * MIF + VIS * 責任者
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
Line 6: Line 22:
  * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  .
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==
Line 16: Line 27:
 . * 責任者  * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
Line 18: Line 41:

<<Anchor(Meetings)>>
Line 22: Line 47:
<<Anchor(MorningMeetings)>>
Line 25: Line 51:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 28: Line 54:
2017/10/17(Tue) 2017/12/27(Wed.)
Line 30: Line 56:
 * Daily
  * 作業人員(*:責任者)
   * MIF+VIS: *和泉、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井、正田、井上、灰野、横澤 (PHS: V-3(榎本), V-7, V-12(横澤))
 * Remote participants by educe: None
Line 34: Line 58:
  * Laser hazard
   * PSLから15mWで、IMC出口で10mW、PRM以降は1mW程度。
   * 今日のある時点からハザードエリアが中央エリアの1階(機械室は除く)になる。
   * 中央エリアにいる作業者全員、Yエンドの安全責任者、(必要ならYアームにいる安全責任者も)にアナウンス。
   * 中央実験室にいる人はそれ以降全員保護メガネの着用をお願いします。
   * Yエンド、Yアームに行く方は、最初にPRMラインの安全パネルの前に置いてある保護メガネを各自1個ずつ持っていって下さい。そして、もし、中央エリアがハザードエリアになった場合は、帰りなどに中央エリアを通る際は保護メガネの着用をお願いします。保護メガネは、前室の入り口横に移動される保護メガネ台に返してください。
   * Xエンドに行く方は保護メガネは必要ありません。
 * 停電からの復帰関連
  * DGS: PR3以外は全て復帰した。
  * AEL:
   * PR2とIOOの電源を分けた。
   * 復電後24Vの電源が一つ壊れていることが確認された。交換済み。
   * Current limitを変更した。IOOは18A、その他は21Aに設定した。
Line 42: Line 65:
  * 作業
   * アラインメント(中野)
    * IMMT1の中段マスの磁石をピコモーターを動かして外した。タワー全体を回したということ。PR2まで光が通った。トラバーサーを動かしてPR3まで光が通った。
    * PR3のピッチの再アラインメントでOSEMが当たってしまったので、OSEMを動かす。
    * BSも3mradくらいピッチ方向にずれている模様。
   * BS: ハードウェア的な仕事は完了した。(Fabian)
 * 両エンドにPDケーブルとも完了。信号もDAQで見えた。(井上)
 * GigEカメラをセットアップする。->麻生+ケーブル張りを誰か
  * IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
   * TTFSSも確認できていない。
   * MCも復帰できていない。
  * Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
   * PRMのみ少しキックがあった。大きさは数十uradくらい。
  * Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
  * 真空: MCポンプのみ復帰。腕はそのまま。


 * Report of work (*:responsible person)

  * AOS: *Akutsu
   * PR2の横にグリーンを構築しつつある。
    * 今日はビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。


 * Work plan (*:responsible person)
  * AOS: *Akutsu, yokokawa, yoshioka, kokeyama
   * グリーンのビームプロファイルなど。
   * EYのマリオネット作業の可能性あり。
  * IOO: *Kokeyama, others
   * ISS準備と実験。


 * Laser hazard
   * センターはSR奥がハザードエリア。
Line 52: Line 95:
  * 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。
 * 問題点など
  * PR3のミスアラインメントを解決する必要がある。2日ほどはかかるので少し遅れが発生している。
  * コーチフィルターが不調。
  * PR3の前室のクリーンブースのシートが落ちてしまっている。->中田
  * Week of 12/25
   * Planed power outage in the afternoon on 12/25.


 * Issues
  * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい
  * PR3計算機が動いていない。
  * MC回路が一部破損か。
Line 62: Line 108:
<<Anchor(WeeklyMeetings)>>
Line 64: Line 111:
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
Line 69: Line 123:
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 75: Line 129:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
Line 76: Line 132:
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 84: Line 141:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者

  • Green setting on PR2:
    • 12/26 *Akutsu, Yokogawa + 1 or 2
    • 12/27 *Yokogawa + 1 or 2



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/27(Wed.)

  • Remote participants by educe: None
  • 停電からの復帰関連
    • DGS: PR3以外は全て復帰した。
    • AEL:
      • PR2とIOOの電源を分けた。
      • 復電後24Vの電源が一つ壊れていることが確認された。交換済み。
      • Current limitを変更した。IOOは18A、その他は21Aに設定した。
    • IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
      • TTFSSも確認できていない。
      • MCも復帰できていない。
    • Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
      • PRMのみ少しキックがあった。大きさは数十uradくらい。
    • Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
    • 真空: MCポンプのみ復帰。腕はそのまま。
  • Report of work (*:responsible person)
    • AOS: *Akutsu
      • PR2の横にグリーンを構築しつつある。
        • 今日はビームプロファイルなど。
      • EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
        • 今日は引き続き作業の可能性あり。
  • Work plan (*:responsible person)
    • AOS: *Akutsu, yokokawa, yoshioka, kokeyama
      • グリーンのビームプロファイルなど。
      • EYのマリオネット作業の可能性あり。
    • IOO: *Kokeyama, others
      • ISS準備と実験。
  • Laser hazard
    • センターはSR奥がハザードエリア。
  • Weekly
    • Week of 12/25
      • Planed power outage in the afternoon on 12/25.
  • Issues
    • k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい

    • PR3計算機が動いていない。
    • MC回路が一部破損か。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)