Differences between revisions 75 and 227 (spanning 152 versions)
Revision 75 as of 2017-10-19 09:25:28
Size: 5078
Comment:
Revision 227 as of 2018-01-05 09:12:27
Size: 6366
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}


-----
Line 4: Line 17:
 * MIF + VIS * 責任者
Line 6: Line 19:
  * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  .
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==
Line 16: Line 24:
 . * 責任者  * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
Line 18: Line 38:

<<Anchor(Meetings)>>
Line 22: Line 44:
<<Anchor(MorningMeetings)>>
Line 25: Line 48:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 28: Line 51:
2017/10/19(Thur) 2017/1/5(Fri.)
Line 30: Line 53:
 * Daily
  * 作業人員(*:責任者)
   * MIF+VIS: *和泉、榎本、中野、神津、新井、正田、井上、灰野、横澤、宮川 (PHS: V-3(榎本), V-7(中野), V-12(横澤))
 * Remote participants by educe: None
Line 34: Line 55:
Fabian、Enzo、平田、  * 停電からの復帰関連
  * DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
  * IOO: MCまで復帰。回路も特に問題ない。
  * 真空: MC再起動。腕はまだ(来週)。
  * Tcam: 2秒間隔で見えるようになった。
Line 36: Line 61:
  * Laser hazard
   * PSL直後で100mW、IMC出口で50mW程度、PRM以降は5mW程度。
   * 今日のある時点からハザードエリアがSR2とSR3の間のラインより奥(機械室は除く)になる。
   * 中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。
   * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを各自1個ずつ持っていって下さい。そして、もし、中央エリアがハザードエリアになった場合は、帰りなどに中央エリアを通る際は保護メガネの着用をお願いします。保護メガネは、前室の入り口横に移動される保護メガネ台に返してください。
   * Xエンドに行く方は保護メガネは必要ありません。
Line 43: Line 62:
  * 作業
   * アラインメント(中野)
    * BSまで光が到達した。X方向に打ち込んでいる。ゲートバルブのビューポートの端に通っている。
    * PR3のお辞儀をなおした。OSEMもレンジ内。曲率が24mなのでセンタリングに反射光の方向がすごく依存するので、まだアラインメントに確証が持てない。
    * BSも3mradくらいピッチ方向にずれている模様。
 * カメラをインストールしている。マウントとケーブル張りは完了。イルミネーターが課題。(井上)
  * PDの信号がふらついているのでそのチェッックをして欲しい。(和泉)
 * Report of work (*:responsible person)
  * Type A: Remoteで測定していた模様。

 * Work plan (*:responsible person)


 * Laser hazard
   * センターはIFI奥がハザードエリア。IR/Green用メガネを着用のこと。
Line 52: Line 72:
  * 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。
 * 問題点など
  * コーチフィルターが不調。
  * PR3の前室のクリーンブースのシートが落ちてしまっているのは直った(中田)。
  * Week of 1/5

  * Week of 1/8
   * meeting
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.

  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.

 * Issues
  * Remoteでの接続が遅い。VPNかk1gateのDNSか?
Line 61: Line 91:
<<Anchor(WeeklyMeetings)>>
Line 63: Line 94:
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
Line 68: Line 106:
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 74: Line 112:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
Line 75: Line 115:
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 83: Line 124:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/5(Fri.)

  • Remote participants by educe: None
  • 停電からの復帰関連
    • DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
    • IOO: MCまで復帰。回路も特に問題ない。
    • 真空: MC再起動。腕はまだ(来週)。
    • Tcam: 2秒間隔で見えるようになった。
  • Report of work (*:responsible person)
    • Type A: Remoteで測定していた模様。
  • Work plan (*:responsible person)
  • Laser hazard
    • センターはIFI奥がハザードエリア。IR/Green用メガネを着用のこと。
  • Weekly
    • Week of 1/5
    • Week of 1/8
      • meeting
      • Re-alignment for IFO on 1/11, 12.
      • Damping for ETMY on 1/13, 14.
    • Week of 1/15
      • IOO works.
      • Pump down, leak check in the later of this week.
  • Issues
    • Remoteでの接続が遅い。VPNかk1gateのDNSか?

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)