Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
Line 11: Line 11:
2017/11/8 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}}
2017/1/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}}
Line 19: Line 19:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .

 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
Line 49: Line 32:
 * 回路: 霜出、上泉  * 回路: 上泉、霜出
Line 65: Line 48:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 68: Line 51:
2017/11/10(Fri) 2017/1/9(Tue.)
Line 70: Line 53:
  * 作業
   * 下げ振り測定
    * IYCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。-X側に8mm程度ずれていた。高さはほぼぴったり。測定後IYCとBSの間のGVを閉めたので、今日真空引きを始める予定。
    * IXCの真空槽の高さが4mm高かった。
 * Remote participants by educe: Izumi, Yokozawa, Miyoki
Line 75: Line 55:
   * 防振関連
    * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。
    * BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。
 * Report of work (*:responsible person)
  * IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。
  * Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。
  * Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。
Line 79: Line 60:
  * 計算機関連
   * k1immtで使っていた光ファイバーケーブルは新しいラックのところまで来た。来週引き続き。
 * Work plan (*:responsible person)
Line 82: Line 62:
 * Daily
  * 作業人員(*:責任者)
   * VIS: Mark, Enzo, 神津

  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
 * Cryo: Yendの外回りの配線チェック。
  * 光てこの話と、真空中のPDの検討をする必要がある。
Line 91: Line 66:
 * Laser hazard
  * センターはIMM奥がハザードエリア。
Line 92: Line 70:
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
  * 11/13の週
   * PR系の位置測定。ただし月曜は拡大チーフ会議などがあり、作業はない見込み。
  * Week of 1/8
   * vacuum meeting 12:30 on 1/10, at fan hut.
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
Line 97: Line 75:
 * 問題点など
  * コーチフィルターが不調。
  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.

 * Issues
Line 110: Line 92:
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 122: Line 108:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/5 updated KAGRA/Commissioning/Commissioning_schedule_20180109.png


Working people assignment

* 責任者



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/9(Tue.)

  • Remote participants by educe: Izumi, Yokozawa, Miyoki
  • Report of work (*:responsible person)
    • IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。
    • Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。
    • Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。
  • Work plan (*:responsible person)
  • Cryo: Yendの外回りの配線チェック。
    • 光てこの話と、真空中のPDの検討をする必要がある。
  • Laser hazard
    • センターはIMM奥がハザードエリア。
  • Weekly
    • Week of 1/8
      • vacuum meeting 12:30 on 1/10, at fan hut.
      • Re-alignment for IFO on 1/11, 12.
      • Damping for ETMY on 1/13, 14.
    • Week of 1/15
      • IOO works.
      • Pump down, leak check in the later of this week.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)